This is a Statement of Work for a roofing project at VA Illiana Healthcare System in Danville, Illinois (Building 58). The contractor must complete all work within sixty (60) calendar days of receiving the Notice to Proceed, working Monday through Friday from 0700-1630 hours, excluding Federal Holidays.
The scope of work includes: tearing off and removing all existing roofing material down to the deck; installing 7/16" OSB on top of existing decking; repairing damaged sheathing, trim, fascia, dormer framing, gutters, vents, soffit, and decking; ensuring no gaps in flashing; painting newly installed exposed wood to match existing conditions; repairing the roof hatch; installing new felt roofing underlayment and new asphalt shingles of the same style currently in place; replacing flashing and decking as needed; caulking and sealing as needed; providing temporary metal fencing around the work area to protect pedestrians and vehicles from falling debris; performing post-completion magnetic sweeps to collect loose nails; and patching any holes that could allow animal entry. The contractor is solely responsible for OSHA fall protection compliance and must verify approved anchor points rather than make assumptions. The contractor must submit a work schedule to the Contracting Officer's Representative prior to beginning onsite work. If unable to meet the required performance period, the contractor must submit a revised schedule with justification and a request for additional time. The work location is VA Illiana Health Care System, 1900 East Main Street, Danville, IL 61832. C&A requirements and Security Accreditation Packages do not apply to this contract.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 2 - B58 Egress Locations.pdf | ||
| Attachment 1 -Pre-Bid RFI 550-27-111 answered.xlsx | XLSX spreadsheet | |
| 36C25226B0038 0002.docx | DOCX document | |
| S06 36C25226B0038 Amend 0001.pdf | ||
| Attachment 4 SAM Wage Determination 550-27-111.pdf | ||
| S02 Attachment 3 - 550-27-111 Specs.pdf | ||
| 36C25226B0038_1.docx | DOCX document | |
| Attachment 2 - 550-27-111 Drawings.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK for 550-27-111
1. Scope of Work:
VA Illiana Healthcare System, Danville, IL seeks a contractor to perform the work prescribed within this document to re-roof Building 58 and perform associated work:
-Tear off and remove from site all existing roofing material down to the existing decking.
-Install 7/16” OSB on top of existing decking.
-Repair any damaged sheathing, trim, fascia, dormer framing, gutter, vents, soffit, and decking.
-There shall be no gaps in flashing.
-Paint any newly installed exposed wood to match existing
-Repair roof hatch to match rest of roof.
-Install new felt roofing underlayment
-Install new asphalt shingles of the same style currently in place
-Replace flashing and decking as needed.
-Caulk and seal as needed
-Contractor to provide temporary metal fencing around work area to protect pedestrians/vehicles from falling debris
-Contractor to be solely responsible for adherence to OSHA requirements for fall protection, no assumption of approved anchor points should be made. Contractor to verify
-Post-completion, sweep all surrounding areas with magnetic sweep to collect any loose nails
-Patch any holes that would allow for animals to enter the building.
3. Performance Period
Contractor shall complete all work associated with this project within sixty (60) calendar days of the receipt of the Notice to Proceed (NTP). Normal working hours are Monday through Friday, 0700-1630, excluding Federal Holidays. Contractor shall provide a schedule to the Contracting Officer’s Representative, through the Contracting Officer, prior to any onsite work taking place. If for any reason the contractor can’t meet the required period of performance for this project he/she must submit, in writing, to the Contracting Officer, a revised schedule, justification, and request for additional time.
Contractor shall make all concerted efforts to minimize the duration of downtime to each building. The C&A requirements do not apply and a Security Accreditation Package is not required.
4. Background:
Work will be performed at:
VA Illiana Health Care System
1900 East Main St.
Danville, IL 61832
Shaded areas are in scope
| 550-27-111 SOW |
| Roofing project b58 shading |
File details come from the government source that posted it. Updated .