Attachment 1 - 2 CS Access Control Statement of Work.pdf
PDF 908 KB Posted
- Attached to
- Paxton Access Control/Secure Comm Rooms
- Solicitation number
- FA460824QS018
About this file
This document is a Statement of Work for the installation of a turn-key Paxton Access Control System around Barksdale Air Force Base. The contractor must install 77 Paxton Access Control Units and Net2 Plus POE keypads at various building locations, along with new lever locks and door hardware. The contractor must be a Paxton certified installer with a minimum of 3 years' experience and provide 3 references. All parts must be new and compatible with the existing Paxton system.
The related federal contract opportunity is a Request for Quotation (RFQ) for this Paxton Access Control System installation. It is a total small business set-aside with a NAICS code of 561622 and a $25.0M size standard. The solicitation includes a site visit on June 11, 2024, with questions due by June 12 and quotes due by June 28. Quotes must be valid for 120 days due to funds not being presently available. The contracting office is the Department of the Air Force Global Strike Command.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work Install Paxton Access Control, Various Buildings on Barksdale AFB
OBJECTIVE: Install turn-key Paxton Access Control System around Barksdale Air Force Base as outlined below. All parts shall be new, the use of used or refurbished parts is strictly prohibited. Parts and pieces must be compatible with existing Paxton system.
QUALIFICATIONS:
1. Paxton certified installer with minimum 3-years’ experience.
2. Provide (3) references from recently completed similar jobs.
SCOPE OF WORK:
1. Install (77) Paxton Access Control Units (ACU’s) and Net2 Plus POE keypads at door locations indicated on AF 332.
2. Install door wrap or plates as needed.
3. Install new lever lock with new cores master keyed to existing system.
4. Remove existing mechanical hardware.
MATERIALS
1. Parts to be used:
Nomenclature/Part# UI Qty Net 2 Plus in US MTL Enclosure EA 77 Net 2 KP75 Key Pad EA 77 HES Electric Strike EA 77 GLS Grade 2 Storeroom Lever IC EA 77
BEST SFIC keyed to master EA 77 GLS Door Wraps EA 77 POE Ejectors: Trendnet TI-SG104 EA 77 Wiring, mounting, tracking, and supplies. EA 1
2. Parts on hand at 2 CS:
Nomenclature/Part# UI Qty
Net 2 Plus in US MTL Enclosure EA 31 375-110-US Key Pad EA 30
5000C-12/24D-630 Electric Strike EA 48 Dormakaba QCL271E62654118FLC Lever EA 76
Dexter C2000 Lever EA 11
Cores: Keyed 1-1 EA 68 Wrap: 9K-S-CW EA 75 Wrap: 12-S-CW EA 15 POE Ejectors: Trendnet TI-SG104 EA 39
3. Any and all remaining parts aside from what is on hand at 2 CS will need to be purchased.
4. Submittals required on all parts and pieces.
5. An area will be provided on or near work site as required to store contractors LOM.
Attachment 1
FA460824QS018
SPECIFICS:
1. Facility ceilings are suspended type.
2. No computers required.
3. No UPS’s required.
4. No CAD design required.
5. Bond & Insurance Per 2 CONS requirement.
INSTALLATION
1. Each ACU installation location shall be discussed and approved by SCOI prior to install.
2. Installation will be done in a neat and professional manner, to include but not limited to the use of mounting hardware and cable management.
3. Any damage to the facility caused by the contractor will be repaired per 2 CS in conjunction with
2 CONS
INSPECTION, TESTING and CERTIFICATION:
1. Spot checks will be performed by SCOI on a daily basis.
2. Each install location will be tested by 2 CS to verify 100 percent serviceability.
WORKSITE LOCATION:
1. Different Buildings located at Barksdale AFB, LA 71110
2. Contractor Working Days/Hours:
a. Normal duty time M-F, 0730-1630
b. Days and hours can be adjusted as required with prior approval from 2 CONS and 2 CS
48HRS prior to a proposed change.
2 CS Shall:
1. Coordinate contractor base access as required to complete project.
2. Program network switch ports for connectivity and assign required IP’s.
3. Program the enclosures.
PERMITS:
1. No permits required for this project.
PERIOD OF PERFORMANCE:
1. Onsite work start date to be determined between contractor and 2 CS.
2. 2 CONS and contractor will determine award date based on the onsite start and completion date identified.
3. The facility beneficial occupancy date (BOD) and the dates above will be monitored monthly and any required adjustment will be coordinated with 2 CONS as necessary.
ACRONYMS
1. POE Power over Ethernet
2. ES Electrified Strike
3. EL Electrified Lock
4. ET Electrified Trim
5. MLR Motorized Latch Retraction
Attachment 1
PAXTON Access Control System
1. General Requirements
1.1. Contractor will assemble/setup on site and will be responsible for all labor, transportation, materials, and equipment for the Paxton Net-2 system.
1.2. Contractor liable for any damage caused by or due to setup. To include building facilities.
1.3. Paxton must be compatible to existing Paxton Net-2 systems currently installed.
2. System Requirements
2.1. Install/provide all wiring to get from door(s) to building access node Must be in conduit.
2.2. Install door electric latch retraction to include door frame hardware
2.3. Install, Paxton Net-2 system with Power over Ethernet (PoE)
3. Building 6415
3.1. Install, Exterior Keypad
3.2. Install, ACU/Control panel-PoE
3.3. Install door electric latch retraction-including any door frame hardware necessary
3.4. Connect to building access node
3.5. Verify operational capability, to include:
3.5.1. Viewing lock in Net2 Access Control
3.5.2. Connecting to lock in Net2 Access Control
3.5.3. Lock can be opened with a key FOB
4. Building 6448 (x2)
4.1. Install, Exterior Keypad
4.2. Install, ACU/Control panel-PoE
4.3. Install door electric latch retraction-including any door frame hardware necessary
4.4. Connect to building access node
4.5. Verify operational capability, to include:
4.5.1. Viewing lock in Net2 Access Control
4.5.2. Connecting to lock in Net2 Access Control
4.5.3. Lock can be opened with a key FOB
5. Building 6566
5.1. Install, Exterior Keypad
5.2. Install, ACU/Control panel-PoE
5.3. Install door electric latch retraction-including any door frame hardware necessary
5.4. Connect to building access node
5.5. Verify operational capability, to include:
5.5.1. Viewing lock in Net2 Access Control
5.5.2. Connecting to lock in Net2 Access Control
5.5.3. Lock can be opened with a key FOB
6. Building 6568
6.1. Install, Exterior Keypad
6.2. Install, ACU/Control panel-PoE
6.3. Install door electric latch retraction-including any door frame hardware necessary
6.4. Connect to building access node
6.5. Verify operational capability, to include:
Attachment 1
6.5.1. Viewing lock in Net2 Access Control
6.5.2. Connecting to lock in Net2 Access Control
6.5.3. Lock can be opened with a key FOB
7. Building 6603
7.1. Install, Exterior Keypad
7.2. Install, ACU/Control panel-PoE
7.3. Install door electric latch retraction-including any door frame hardware necessary
7.4. Connect to building access node
7.5. Verify operational capability, to include:
7.5.1. Viewing lock in Net2 Access Control
7.5.2. Connecting to lock in Net2 Access Control
7.5.3. Lock can be opened with a key FOB
8. Building 6614
8.1. Install, Exterior Keypad
8.2. Install, ACU/Control panel-PoE
8.3. Install door electric latch retraction-including any door frame hardware necessary
8.4. Connect to building access node
8.5. Verify operational capability, to include:
8.5.1. Viewing lock in Net2 Access Control
8.5.2. Connecting to lock in Net2 Access Control
8.5.3. Lock can be opened with a key FOB
9. Building 6615
9.1. Install, Exterior Keypad
9.2. Install, ACU/Control panel-PoE
9.3. Install door electric latch retraction-including any door frame hardware necessary
9.4. Connect to building access node
9.5. Verify operational capability, to include:
9.5.1. Viewing lock in Net2 Access Control
9.5.2. Connecting to lock in Net2 Access Control
9.5.3. Lock can be opened with a key FOB
10. Building 6626
10.1. Install, Exterior Keypad
10.2. Install, ACU/Control panel-PoE
10.3. Install door electric latch retraction-including any door frame hardware necessary
10.4. Connect to building access node
10.5. Verify operational capability, to include:
10.5.1. Viewing lock in Net2 Access Control
10.5.2. Connecting to lock in Net2 Access Control
10.5.3. Lock can be opened with a key FOB
11. Building 6628 (x2)
11.1. Install, Exterior Keypad
11.2. Install, ACU/Control panel-PoE
11.3. Install door electric latch retraction-including any door frame hardware necessary
Attachment 1
11.4. Connect to building access node
11.5. Verify operational capability, to include:
11.5.1. Viewing lock in Net2 Access Control
11.5.2. Connecting to lock in Net2 Access Control
11.5.3. Lock can be opened with a key FOB
12. Building 6638
12.1. Install, Exterior Keypad
12.2. Install, ACU/Control panel-PoE
12.3. Install door electric latch retraction-including any door frame hardware necessary
12.4. Connect to building access node
12.5. Verify operational capability, to include:
12.5.1. Viewing lock in Net2 Access Control
12.5.2. Connecting to lock in Net2 Access Control
12.5.3. Lock can be opened with a key FOB
13. Building 6649
13.1. Install, Exterior Keypad
13.2. Install, ACU/Control panel-PoE
13.3. Install door electric latch retraction-including any door frame hardware necessary
13.4. Connect to building access node
13.5. Verify operational capability, to include:
13.5.1. Viewing lock in Net2 Access Control
13.5.2. Connecting to lock in Net2 Access Control
13.5.3. Lock can be opened with a key FOB
14. Building 6850
14.1. Install, Exterior Keypad
14.2. Install, ACU/Control panel-PoE
14.3. Install door electric latch retraction-including any door frame hardware necessary
14.4. Connect to building access node
14.5. Verify operational capability, to include:
14.5.1. Viewing lock in Net2 Access Control
14.5.2. Connecting to lock in Net2 Access Control
14.5.3. Lock can be opened with a key FOB
15. Building 6847
15.1. Install, Exterior Keypad
15.2. Install, ACU/Control panel-PoE
15.3. Install door electric latch retraction-including any door frame hardware necessary
15.4. Connect to building access node
15.5. Verify operational capability, to include:
15.5.1. Viewing lock in Net2 Access Control
15.5.2. Connecting to lock in Net2 Access Control
15.5.3. Lock can be opened with a key FOB
Attachment 1
16. Building 6836
16.1. Install, Exterior Keypad
16.2. Install, ACU/Control panel-PoE
16.3. Install door electric latch retraction-including any door frame hardware necessary
16.4. Connect to building access node
16.5. Verify operational capability, to include:
16.5.1. Viewing lock in Net2 Access Control
16.5.2. Connecting to lock in Net2 Access Control
16.5.3. Lock can be opened with a key FOB
17. Building 6832
17.1. Install, Exterior Keypad
17.2. Install, ACU/Control panel-PoE
17.3. Install door electric latch retraction-including any door frame hardware necessary
17.4. Connect to building access node
17.5. Verify operational capability, to include:
17.5.1. Viewing lock in Net2 Access Control
17.5.2. Connecting to lock in Net2 Access Control
17.5.3. Lock can be opened with a key FOB
18. Building 6830
18.1. Install, Exterior Keypad
18.2. Install, ACU/Control panel-PoE
18.3. Install door electric latch retraction-including any door frame hardware necessary
18.4. Connect to building access node
18.5. Verify operational capability, to include:
18.5.1. Viewing lock in Net2 Access Control
18.5.2. Connecting to lock in Net2 Access Control
18.5.3. Lock can be opened with a key FOB
19. Building 6827
19.1. Install, Exterior Keypad
19.2. Install, ACU/Control panel-PoE
19.3. Install door electric latch retraction-including any door frame hardware necessary
19.4. Connect to building access node
19.5. Verify operational capability, to include:
19.5.1. Viewing lock in Net2 Access Control
19.5.2. Connecting to lock in Net2 Access Control
19.5.3. Lock can be opened with a key FOB
20. Building 6825 (x4)
20.1. Install, Exterior Keypad
20.2. Install, ACU/Control panel-PoE
Attachment 1
20.3. Install door electric latch retraction-including any door frame hardware necessary
20.4. Connect to building access node
20.5. Verify operational capability, to include:
20.5.1. Viewing lock in Net2 Access Control
20.5.2. Connecting to lock in Net2 Access Control
20.5.3. Lock can be opened with a key FOB
21. Building 6820
21.1. Install, Exterior Keypad
21.2. Install, ACU/Control panel-PoE
21.3. Install door electric latch retraction-including any door frame hardware necessary
21.4. Connect to building access node
21.5. Verify operational capability, to include:
21.5.1. Viewing lock in Net2 Access Control
21.5.2. Connecting to lock in Net2 Access Control
21.5.3. Lock can be opened with a key FOB
22. Building 6815
22.1. Install, Exterior Keypad
22.2. Install, ACU/Control panel-PoE
22.3. Install door electric latch retraction-including any door frame hardware necessary
22.4. Connect to building access node
22.5. Verify operational capability, to include:
22.5.1. Viewing lock in Net2 Access Control
22.5.2. Connecting to lock in Net2 Access Control
22.5.3. Lock can be opened with a key FOB
23. Building 6813
23.1. Install, Exterior Keypad
23.2. Install, ACU/Control panel-PoE
23.3. Install door electric latch retraction-including any door frame hardware necessary
23.4. Connect to building access node
23.5. Verify operational capability, to include:
23.5.1. Viewing lock in Net2 Access Control
23.5.2. Connecting to lock in Net2 Access Control
23.5.3. Lock can be opened with a key FOB
24. Building 6812
24.1. Install, Exterior Keypad
24.2. Install, ACU/Control panel-PoE
24.3. Install door electric latch retraction-including any door frame hardware necessary
24.4. Connect to building access node
24.5. Verify operational capability, to include:
24.5.1. Viewing lock in Net2 Access Control
Attachment 1
24.5.2. Connecting to lock in Net2 Access Control
24.5.3. Lock can be opened with a key FOB
25. Building 6809
25.1. Install, Exterior Keypad
25.2. Install, ACU/Control panel-PoE
25.3. Install door electric latch retraction-including any door frame hardware necessary
25.4. Connect to building access node
25.5. Verify operational capability, to include:
25.5.1. Viewing lock in Net2 Access Control
25.5.2. Connecting to lock in Net2 Access Control
25.5.3. Lock can be opened with a key FOB
26. Building 4565 (x4)
26.1. Install, Exterior Keypad
26.2. Install, ACU/Control panel-PoE
26.3. Install door electric latch retraction-including any door frame hardware necessary
26.4. Connect to building access node
26.5. Verify operational capability, to include:
26.5.1. Viewing lock in Net2 Access Control
26.5.2. Connecting to lock in Net2 Access Control
26.5.3. Lock can be opened with a key FOB
27. Building 5576 (x4)
27.1. Install, Exterior Keypad
27.2. Install, ACU/Control panel-PoE
27.3. Install door electric latch retraction-including any door frame hardware necessary
27.4. Connect to building access node
27.5. Verify operational capability, to include:
27.5.1. Viewing lock in Net2 Access Control
27.5.2. Connecting to lock in Net2 Access Control
27.5.3. Lock can be opened with a key FOB
28. Building 5541 (x4)
28.1. Install, Exterior Keypad
28.2. Install, ACU/Control panel-PoE
28.3. Install door electric latch retraction-including any door frame hardware necessary
28.4. Connect to building access node
28.5. Verify operational capability, to include:
28.5.1. Viewing lock in Net2 Access Control
28.5.2. Connecting to lock in Net2 Access Control
28.5.3. Lock can be opened with a key FOB
Attachment 1
29. Building 5341 (x4)
29.1. Install, Exterior Keypad
29.2. Install, ACU/Control panel-PoE
29.3. Install door electric latch retraction-including any door frame hardware necessary
29.4. Connect to building access node
29.5. Verify operational capability, to include:
29.5.1. Viewing lock in Net2 Access Control
29.5.2. Connecting to lock in Net2 Access Control
29.5.3. Lock can be opened with a key FOB
30. Building 4400 (x3)
30.1. Install, Exterior Keypad
30.2. Install, ACU/Control panel-PoE
30.3. Install door electric latch retraction-including any door frame hardware necessary
30.4. Connect to building access node
30.5. Verify operational capability, to include:
30.5.1. Viewing lock in Net2 Access Control
30.5.2. Connecting to lock in Net2 Access Control
30.5.3. Lock can be opened with a key FOB
31. Building 3433 (x6)
31.1. Install, Exterior Keypad
31.2. Install, ACU/Control panel-PoE
31.3. Install door electric latch retraction-including any door frame hardware necessary
31.4. Connect to building access node
31.5. Verify operational capability, to include:
31.5.1. Viewing lock in Net2 Access Control
31.5.2. Connecting to lock in Net2 Access Control
31.5.3. Lock can be opened with a key FOB
32. Building 6803 (x2)
32.1. Install, Exterior Keypad
32.2. Install, ACU/Control panel-PoE
32.3. Install door electric latch retraction-including any door frame hardware necessary
32.4. Connect to building access node
32.5. Verify operational capability, to include:
32.5.1. Viewing lock in Net2 Access Control
32.5.2. Connecting to lock in Net2 Access Control
32.5.3. Lock can be opened with a key FOB
33. Building 6402 (x2)
33.1. Install, Exterior Keypad
33.2. Install, ACU/Control panel-PoE
33.3. Install door electric latch retraction-including any door frame hardware necessary
33.4. Connect to building access node
Attachment 1
33.5. Verify operational capability, to include:
33.5.1. Viewing lock in Net2 Access Control
33.5.2. Connecting to lock in Net2 Access Control
33.5.3. Lock can be opened with a key FOB
34. Building 6000 (x2)
34.1. Install, Exterior Keypad
34.2. Install, ACU/Control panel-PoE
34.3. Install door electric latch retraction-including any door frame hardware necessary
34.4. Connect to building access node
34.5. Verify operational capability, to include:
34.5.1. Viewing lock in Net2 Access Control
34.5.2. Connecting to lock in Net2 Access Control
34.5.3. Lock can be opened with a key FOB
35. Building 5822
35.1. Install, Exterior Keypad
35.2. Install, ACU/Control panel-PoE
35.3. Install door electric latch retraction-including any door frame hardware necessary
35.4. Connect to building access node
35.5. Verify operational capability, to include:
35.5.1. Viewing lock in Net2 Access Control
35.5.2. Connecting to lock in Net2 Access Control
35.5.3. Lock can be opened with a key FOB
36. Building 5376 (x4)
36.1. Install, Exterior Keypad
36.2. Install, ACU/Control panel-PoE
36.3. Install door electric latch retraction-including any door frame hardware necessary
36.4. Connect to building access node
36.5. Verify operational capability, to include:
36.5.1. Viewing lock in Net2 Access Control
36.5.2. Connecting to lock in Net2 Access Control
36.5.3. Lock can be opened with a key FOB
37. Building 5546 (x6)
37.1. Install, Exterior Keypad
37.2. Install, ACU/Control panel-PoE
37.3. Install door electric latch retraction-including any door frame hardware necessary
37.4. Connect to building access node
37.5. Verify operational capability, to include:
37.5.1. Viewing lock in Net2 Access Control
37.5.2. Connecting to lock in Net2 Access Control
37.5.3. Lock can be opened with a key FOB
Attachment 1
38. Building 5345 (x4)
38.1. Install, Exterior Keypad
38.2. Install, ACU/Control panel-PoE
38.3. Install door electric latch retraction-including any door frame hardware necessary
38.4. Connect to building access node
38.5. Verify operational capability, to include:
38.5.1. Viewing lock in Net2 Access Control
38.5.2. Connecting to lock in Net2 Access Control
38.5.3. Lock can be opened with a key FOB
39. Building 3435 (x2)
39.1. Install, Exterior Keypad
39.2. Install, ACU/Control panel-PoE
39.3. Install door electric latch retraction-including any door frame hardware necessary
39.4. Connect to building access node
39.5. Verify operational capability, to include:
39.5.1. Viewing lock in Net2 Access Control
39.5.2. Connecting to lock in Net2 Access Control
39.5.3. Lock can be opened with a key FOB
40. Building 3433
40.1. Install, Exterior Keypad
40.2. Install, ACU/Control panel-PoE
40.3. Install door electric latch retraction-including any door frame hardware necessary
40.4. Connect to building access node
40.5. Verify operational capability, to include:
40.5.1. Viewing lock in Net2 Access Control
40.5.2. Connecting to lock in Net2 Access Control
40.5.3. Lock can be opened with a key FOB
41. Delivery Information:
41.1. Delivery No Later Than 90 days after contract award
41.2. Delivery to include installation:
2 CS/SCOI Bldg. 3458
105 Barksdale Blvd East
Barksdale AFB, LA 71110
42. Removal & Installation
42.1. Contractor shall remove all shipping and packaging materials from location
43. Warranty
43.1. Contractor shall include a minimum 12-month warranty of all parts and services on doors and wiring
Attachment 1