This is a Statement of Work for nitrogen supply services to the Bureau of Reclamation's Mt. Elbert Powerplant in Twin Lakes, Colorado. The requirement is to maintain a continuous, slightly pressurized nitrogen blanket on Transformer K2A to preserve and protect the transformer's insulation system during the period of performance from May 1, 2026, through April 31, 2027.

Nitrogen shall be supplied in two forms: 330-pound cylinders (bottled gas) and bulk liquid nitrogen. For the cylinder supply, the contractor must provide ultra-high purity nitrogen in 330-pound cylinders that are rented from the supplier, with the supplier responsible for all maintenance, testing, and replacement. Six cylinders must remain connected and available on the manifold simultaneously. For bulk liquid supply, the product must be UN-1977 liquid nitrogen delivered in gaseous form only. All connections for both supply options must be compatible with standard gas fittings. Deliveries must occur Monday through Thursday between 8:00 a.m. and 4:00 p.m. Mountain Time, within five business days after receipt of order. Orders and deliveries shall be initiated by the government throughout the period of performance. The delivery location is Bureau of Reclamation, Mt. Elbert Powerplant, 5583 Highway 82, Twin Lakes, Colorado 81251.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bureau of Reclamation Mt. Elbert Powerplant Twin Lakes, Colorado

Statement of Work

Nitrogen for K2A Requirement

Background: The Mt. Elbert Powerplant must maintain a continuous, slightly pressurized nitrogen (N2) blanket on Transformer K2A. This is a critical and ongoing requirement necessary to preserve and protect the transformer's insulation system.

Period of Performance: 05/01/2026 04/31/2027

Orders/Deliveries shall be initiated by the government throughout the Period of Performance.

Delivery Requirements: Nitrogen shall be delivered to:

Bureau of Reclamation Mt. Elbert Powerplant 5583 Highway 82 Twin Lakes, CO 81251

Deliveries must take place Monday - Thursday 8am to 4pm, MT.

Delivery shall occur within five (5) business days after receipt of order.

Nitrogen shall be supplied in both 330-lb cylinders (bottled gas) and bulk liquid form.

Salient Characteristics for Nitrogen:

Cylinder (330-lb Bottle) Requirements:

Cylinder Requirements:

Cylinders shall be 330 pounds each.

Nitrogen must be ultra-high purity.

Cylinders will be rented from the supplier.

The supplier is responsible for all maintenance, required testing, and replacement of rented cylinders.

Six (6) cylinders will be connected and used simultaneously and must remain available on the manifold at all times.

Bulk Liquid Requirements:

Bulk Liquid Requirements:

Product shall be UN-1977 liquid nitrogen.

The system must deliver nitrogen in gaseous form only.

See picture examples

Connection Requirements:

For both bulk liquid and 330-lb cylinder supply options, all connections must be compatible with standard gas fittings.

140R6026Q0048 Attachment 1 Bureau of Reclamation Missouri Basin Region

File details come from the government source that posted it. Updated .