This is a Scope of Work (SOW) for the replacement of storefront doors at the Visitor Center at Craters of the Moon National Monument and Preserve in Arco, Idaho.

The contractor shall remove and replace five existing storefront door assemblies, consisting of one exterior single door (3'-0" W x 7'-0" H), one exterior single door (3'-0" W x 7'-6" H), one interior single door (3'-0" W x 7'-0" H), one interior double door (6'-0" W x 7'-0" H), and two exterior double doors (6'-0" W x 7'-0" H each). All doors must be commercial-grade aluminum storefront systems manufactured by Kawneer, YKK AP, Tubelite, or an approved equal, with clear anodized aluminum finish or matching the existing finish. Exterior doors require 1-inch insulated tempered safety glass with Low-E recommended for energy efficiency, while interior doors require ¼-inch tempered safety glass. Hardware must include panic exit devices on egress doors, ADA/ABA-compliant door closers, continuous hinges or heavy-duty pivots, and exterior-grade thresholds and weatherstripping. The contractor is responsible for all labor, materials, equipment, supervision, and incidentals necessary for removal, installation, and site restoration.

Work must comply with the International Building Code (IBC), NFPA 101 Life Safety Code, Architectural Barriers Act (ABA), ADA Accessibility Guidelines (ADAAG), OSHA standards, and National Park Service Facility Management policies. The contractor shall field-verify existing openings prior to fabrication, install frames plumb and level, seal all exterior joints with weather-resistant sealant, and maintain ADA clearances and opening forces. Any doors currently equipped with automatic door openers must be replaced with doors that include automatic door openers. Quality control requires submission of shop drawings and product data for NPS approval, glazing certifications, and final inspection and operational testing. The contractor must coordinate work to minimize disruption to Visitor Center operations and maintain safe ingress and egress for visitors and staff at all times. Exclusions include fire alarm or security system modifications, structural modifications to door openings, and permitting fees unless otherwise directed by the Contracting Officer.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT 1_SCOPE OF WORK (SOW)

Project Title: Storefront Door Replacement Location: Visitor Center, Craters of the Moon National Monument and Preserve (NPS) 1266 Craters Loop Rd. Arco, Idaho 83213

1. GENERAL DESCRIPTION

Brand Name or equal to: Kawneer, YKK AP, Tubelite, or approved equal. Commercial-grade aluminum storefront door systems The contractor shall provide all labor, materials, equipment, supervision, and incidentals necessary to remove and replace existing storefront door assemblies at the Visitor Center at Craters of the Moon National Monument and Preserve.

The project includes replacement of both interior and exterior aluminum storefront doors that serve as primary public access, egress routes, and interior circulation points within the facility. The work will ensure the doors meet current life safety, accessibility (ADA/ABA), and building code requirements, while improving durability and performance in the monument’s high-desert climate conditions.

All work shall comply with applicable International Building Code (IBC), NFPA 101 Life Safety Code, Architectural Barriers Act (ABA), ADA Accessibility Guidelines (ADAAG), OSHA standards, and National Park Service Facility Management policies.

2. DOOR SCHEDULE

Qty Location Configuration Size

1 Exterior Single Door 3’-0” W x 7’-0” H

1 Exterior Single Door 3’-0” W x 7’-6” H

1 Interior Single Door 3’-0” W x 7’-0” H

1 Interior Double Door 6’-0” W x 7’-0” H

2 Exterior Double Doors 6’-0” W x 7’-0” H

3. MATERIALS & SYSTEM REQUIREMENTS

3.1 Doors and Frames

• Commercial-grade aluminum storefront door systems (Kawneer, YKK AP, Tubelite, or approved equal)

• Finish: Clear anodized aluminum or match existing

• Frames sized to existing openings; field-verified prior to fabrication

3.2 Glazing

• Exterior doors: 1-inch insulated, tempered safety glass (Low-E recommended for energy efficiency)

• Interior doors: ¼-inch tempered safety glass

3.3 Hardware

• Panic exit devices on egress doors

• ADA/ABA-compliant door closers

• Continuous hinges or heavy-duty pivots

• Exterior-grade thresholds and weatherstripping

• Hardware finish to match existing or as approved by NPS

3.4 Environmental Considerations

Materials and installation shall be suitable for extreme temperature fluctuations, wind exposure, and seasonal conditions typical of Craters of the Moon National Monument.

4. DEMOLITION

• Remove existing storefront doors, frames, glazing, and hardware

• Protect adjacent finishes, walls, and glazing systems

• Maintain safe public access during construction

• Dispose of all removed materials off-site in accordance with federal, state, and local regulations

5. INSTALLATION

• Field verify all existing openings and conditions prior to fabrication

• Install new frames plumb, level, and square

• Install doors, glazing, hardware, and closers

• Seal all exterior joints with weather-resistant sealant

• Adjust doors to ensure smooth operation, proper alignment, and code compliance

• Maintain required ADA clearances and opening forces

• Ensure that any doors currently equipped with automatic door openers are replaced with doors that include automatic door openers.

6. QUALITY CONTROL & CLOSEOUT

• Submit shop drawings and product data for NPS review and approval

• Provide glazing certifications and hardware specifications

• Perform final inspection and operational testing of all doors

• Correct deficiencies prior to acceptance

• Clean all surfaces and leave site in a neat, usable condition

7. PHASING & SITE CONDITIONS

• Coordinate work to minimize disruption to Visitor Center operations

• Maintain safe ingress and egress for visitors and staff at all times

• Provide temporary barriers or signage as needed

8. EXCLUSIONS

• Fire alarm or security system modifications

• Structural modifications to door openings

• Permitting fees unless otherwise directed by the Contracting Officer

9. SAFETY & COMPLIANCE

The contractor shall comply with all applicable OSHA safety standards and NPS site-specific safety requirements. Work shall be performed in a manner that ensures the safety of visitors, staff, and construction personnel in an active public facility.