This is a Construction Specification 21—Excavation document for the Daugherty WRE project in Clark County, Illinois, dated May 5, 2025.

The specification outlines excavation requirements divided into three classifications: common excavation (materials removable by heavy ripping equipment, wheel tractor-scrapers, or standard excavators rated one cubic yard or larger); rock excavation (hard, compacted, or cemented materials requiring blasting or larger equipment, including isolated boulders exceeding one cubic yard); and unclassified excavation (all materials regardless of nature or removal method). Blasting operations, when required, must be directed by qualified personnel and conducted to prevent damage to work or unnecessary fracturing. Excavated material suitable for earthfill or rockfill shall be reused per Method 1 (required use to extent needed) or Method 2 (optional use). Waste material disposal follows Method 1 (designated locations shown on drawings) or Method 2 (contractor-selected sites in environmentally acceptable manner). Excavations must comply with OSHA Construction Industry Standards (29 CFR Part 1926, Subpart P) and maintain safe, stable conditions. Over-excavation in rock is corrected with Portland cement concrete; in earth, with approved compacted earthfill.

Two specific bid items are detailed: Bid Item #4 – Excavation, Common (20,943 cubic yards) covers pool and tile exploration trench excavation using common excavation methods, with estimated quantities used unless significant plan changes occur, paid at contract unit price. Bid Item #7 – Tile Exploration Trench (4,323 linear feet) requires trenching to minimum depth of six feet to expose existing tile, with NRCS inspection before backfill, and includes tile decommissioning and clearing/grubbing. Grubbing requirements specify minimum six-inch depth for grass vegetation and removal of woody material exceeding one-inch diameter. Grubbed material is segregated into earthen and woody components with specific placement requirements; spoil piles limited to 6:1 side slopes and seven-foot maximum height. Payment for both items is by lump sum, with estimated volumes used unless contractor proves significant plan changes to the COTR.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DAUGHERTY WRE Clark County, IL May 5, 2025 21-1

Construction Specification 21—Excavation

1. Scope

The work shall consist of the excavation required by the drawings and specifications and disposal of the excavated materials.

2. Classification

Excavation is classified as common excavation, rock excavation, or unclassified excavation in accordance with the following definitions.

Common excavation is defined as the excavation of all materials that can be excavated, transported, and unloaded using heavy ripping equipment and wheel tractor-scrapers with pusher tractors or that can be excavated and dumped into place or loaded onto hauling equipment by excavators having a rated capacity of one cubic yard or larger and equipped with attachments (shovel, bucket, backhoe, dragline, or clam shell) appropriate to the material type, character, and nature of the materials.

Rock excavation is defined as the excavation of all hard, compacted, or cemented materials that require blasting or the use of ripping and excavating equipment larger than defined for common excavation. The excavation and removal of isolated boulders or rock fragments larger than 1 cubic yard encountered in materials otherwise conforming to the definition of common excavation shall be classified as rock excavation. The presence of isolated boulders or rock fragments larger than 1 cubic yard is not in itself sufficient cause to change the classification of the surrounding material.

For the purpose of these classifications, the following definitions shall apply:

Heavy ripping equipment is a rear-mounted, heavy duty, single-tooth, ripping attachment mounted on a track type tractor having a power rating of at least 250 flywheel horsepower unless otherwise specified in section 10.

Wheel tractor-scraper is a self-loading (not elevating) and unloading scraper having a struck bowl capacity of at least 12 cubic yards.

Pusher tractor is a track type tractor having a power rating of at least 250 flywheel horsepower equipped with appropriate attachments.

Unclassified excavation is defined as the excavation of all materials encountered, including rock materials, regardless of their nature or the manner in which they are removed.

3. Blasting

The transportation, handling, storage, and use of dynamite and other explosives shall be directed and supervised by a person(s) of proven experience and ability who is authorized and qualified to conduct blasting operations.

Blasting shall be done in a manner to prevent damage to the work or unnecessary fracturing of the underlying rock materials and shall conform to any special requirements in section 10 of this specification.

When specified in section 10, the contractor shall furnish the engineer, in writing, a blasting plan before blasting operations begin.

4. Use of excavated material

Method 1—To the extent they are needed, all suitable material from the specified excavations shall be used in the construction of required permanent earthfill or rockfill. The suitability of material for specific

May 5, 2025 21-2 purposes is determined by the engineer. The contractor shall not waste or otherwise dispose of suitable excavated material.

Method 2—Suitable material from the specified excavations may be used in the construction of required earthfill or rockfill. The suitability of material for specific purposes is determined by the engineer.

5. Disposal of waste materials

Method 1—All surplus or unsuitable excavated materials are designated as waste and shall be disposed of at the locations shown on the drawings.

Method 2—All surplus or unsuitable excavated materials are designated as waste and shall be disposed of by the contractor at sites of his own choosing away from the site of the work. The disposal shall be in an environmentally acceptable manner that does not violate local rules and regulations.

6. Excavation limits

Excavations shall comply with OSHA Construction Industry Standards (29CFR Part 1926) Subpart P, Excavations, Trenching, and Shoring. All excavations shall be completed and maintained in a safe and stable condition throughout the total construction phase. Structure and trench excavations shall be completed to the specified elevations and to the length and width required to safely install, adjust, and remove any forms, bracing, or supports necessary for the installation of the work. Excavations outside the lines and limits shown on the drawings or specified herein required to meet safety requirements shall be the responsibility of the contractor in constructing and maintaining a safe and stable excavation.

7. Borrow excavation

When the quantities of suitable material obtained from specified excavations are insufficient to construct the specified earth fills and earth backfills, additional material shall be obtained from the designated borrow areas. The extent and depth of borrow pits within the limits of the designated borrow areas shall be as specified in section 10 or as approved by the engineer.

Borrow pits shall be excavated and finally dressed to blend with the existing topography and sloped to prevent ponding and to provide drainage.

8. Over excavation

Excavation in rock beyond the specified lines and grades shall be corrected by filling the resulting voids with Portland cement concrete made of materials and mix proportions approved by the engineer. Concrete that will be exposed to the atmosphere when construction is completed shall meet the requirements of concrete selected for use under Construction Specification 31, Concrete for Major Structures, or 32, Structure Concrete, as appropriate.

Concrete that will be permanently covered shall contain not less than five bags of cement per cubic yard.

The concrete shall be placed and cured as specified by the engineer.

Excavation in earth beyond the specified lines and grades shall be corrected by filling the resulting voids with approved, compacted earthfill. The exception to this is that if the earth is to become the subgrade for riprap, rockfill, sand or gravel bedding, or drainfill, the voids may be filled with material conforming to the specifications for the riprap, rockfill, bedding, or drainfill. Before correcting an over excavation condition, the contractor shall review the planned corrective action with the engineer and obtain approval of the corrective measures.

May 5, 2025 21-3

9. Measurement and payment

For items of work for which specific unit prices are established in the contract, the volume of each type and class of excavation within the specified pay limits is measured and computed to the nearest cubic yard by the method of average cross-sectional end areas or by methods outlined in section 10 of this specification.

Regardless of quantities excavated, the measurement for payment is made to the specified pay limits except that excavation outside the specified lines and grades directed by the engineer to remove unsuitable material is included. Excavation required because unsuitable conditions result from the contractor's improper construction operations, as determined by the engineer, is not included for measurement and payment.

Method 1—The pay limits shall be as designated on the drawings.

Method 2—The pay limits shall be defined as follows:

a. The upper limit shall be the original ground surface as it existed before the start of construction operations except that where excavation is performed within areas designated for previous excavation or earthfill, the upper limit shall be the modified ground surface resulting from the specified previous excavation or earthfill.

b. The lower and lateral limits shall be the neat lines and grades shown on the drawings.

Method 3—The pay limits shall be defined as follows:

a. The upper limit shall be the original ground surface as it existed before the start of construction operations except that where excavation is performed within areas designated for previous excavation or earthfill, the upper limit shall be the modified ground surface resulting from the specified previous excavation or earthfill.

b. The lower and lateral limits shall be the true surface of the completed excavation as directed by the engineer.

Method 4—The pay limits shall be defined as follows:

a. The upper limit shall be the original ground surface as it existed before the start of construction operations except that where excavation is performed within areas designated for previous excavation or earthfill, the upper limit shall be the modified ground surface resulting from the specified previous excavation or earthfill.

b. The lower limit shall be at the bottom surface of the proposed structure.

c. The lateral limits shall be 18 inches outside of the outside surface of the proposed structure or shall be vertical planes 18 inches outside of and parallel to the footings, whichever gives the larger pay quantity, except as provided in d below.

d. For trapezoidal channel linings or similar structures that are to be supported upon the sides of the excavation without intervening forms, the lateral limits shall be at the underside of the proposed lining or structure.

e. For the purposes of the definitions in b, c, and d, above, any specified bedding or drainfill directly beneath or beside the structure will be considered to be a part of the structure.

All methods—The following provisions apply to all methods of measurement and payment.

Payment for each type and class of excavation is made at the contract unit price for that type and class of excavation. Such payment will constitute full compensation for all labor, materials, equipment, and all other items necessary and incidental to the performance of the work except that extra payment for backfilling over excavation will be made in accordance with the following provisions.

Payment for backfilling over excavation, as specified in section 8 of this specification, is made only if the excavation outside specified lines and grades is directed by the engineer to remove unsuitable material and if the unsuitable condition is not a result of the contractor's improper construction operations as determined by the engineer.

Compensation for any item of work described in the contract, but not listed in the bid schedule, is included in the payment for the item of work to which it is made subsidiary. Such items and the items to which they

May 5, 2025 21-4 are made subsidiary are identified in section 10 of this specification.

10. Items of work and construction details

Bid Item# 4 – Excavation, Common –20,943 cy

1 . This i t em sha l l cons i s t o f common excavation w h i c h includes excavation of pools and t i l e e x p l o r a t i o n t r e n c h .

2. All excavation in this contract is anticipated to meet the definition of common excavation as described in Section 2 Classification of this specification.

The disposal of excavated material will be by Method 1 under Item 5 Disposal of Waste Materials.

The Contractor shall take great care to not over excavate beyond the specified maximum depth in the borrow areas required for construction.

Under Section 9 -Measurement and payment, payment shall be by Method 1 , with the exception that the final quantities shall not be measured unless there is a significant change to the plans. It shall be the contractor's responsibility to prove this quantity difference to the COTR. If there are no changes to the plans, then the estimated volumes shall be used.

Bid Item#7 – Tile Exploration Trench – 4,323 ft

1. This item shall consist of the common excavation required to excavate a trench to expose any existing tile as shown on drawings and as described in the specifications and construction plans.

2. The tile exploration trench shall be inspected by NRCS prior to backfill. The contractor is to coordinate the timing to ensure NRCS inspector is present during excavation if the contractor wants to backfill immediately after exploration trench is dug.

3. Exploration trench requirements

a. Excavate to a minimum depth of 6.’

b. Trench shall be immediately backfilled in all locations where no drains are found after

NRCS inspection or shall have side slopes of trench sloped back or benched to meet OSHA requirements.

c. Backfill has no compaction requirements but shall be mounded for settlement.

d. In the event of located drain,

i. area shall not be backfilled and shall have side slopes of trench pulled back at 2:1 or flatter.

ii. NRCS shall be notified of all locations where tile drains were found.

iii. The contractor shall provide NRCS the following information.

iv. Location and/or station of drain

v. Size of drain found.

vi. Type of drain material

vii. Direction of flow

viii. Determine if tile drains adjacent property.

1. If determined to drain adjacent property, NRCS shall provide additional decommissioning instructions according with IL drainage law.

Additional criteria will consist of using non-perforated tile of similar material and size under the footprint of the pool to a point 200’ beyond those footprints.

2. If tile is found to not drain adjacent land, then contractor is to excavate the existing drain 200’. This will be included in the contractor’s expense.

May 5, 2025 21-5

In section 5, Disposal of Waste Materials, Method 1 will apply.

Under Section 9 -Measurement and payment, no payment method shall be used. Payment for each type of excavation is made at the contract unit price for that type of excavation. Such payment will constitute full compensation for all labor, material, equipment, and all other items necessary and incidental to the performance of the work, with the exception that the final quantities shall not be measured unless there is a significant change to the plans. This includes cost to meet all decommissioning procedures and quantities according to the plans. It shall be the contractor's responsibility to prove this quantity difference to the COTR. If there are no changes to the plans, then the estimated volumes shall be used.

Payment is by lump sum.

3 . This i t em sha l l cons i s t o f common excavation w h i c h includes, tile decommissioning and clearing and grubbing.

4. All excavation in this contract is anticipated to meet the definition of common excavation as described in Section 2 Classification of this specification.

5. Grubbing shall be a minimum of 6" depth for grass type vegetation, woody material shall be grubbed to a depth to remove root material and will vary based on size of woody material. It shall be grubbed to remove any vegetative material greater than 1" diameter of root material.

Clearing and grubbing shall be in the following areas: All pools shall be grubbed of vegetation.

Grub material shall be hauled to the habitat mound areas marked on the plans.

Grubbed Material

a. The grub material that mainly consists of earthen material shall:

i. Be grubbed to a depth of 6” minimum. Grub material shall be placed in designated locations per the construction plans.

b. The grubbed material that mainly consists of woody trunks, stems, root wads shall:

i. Be handled in a manner to reduce the amount of earthen material retained on woody vegetation.

ii. Shall be placed in a manner that prevents debris from being easily displaced and entering the adjacent channel by a flood event.

iii. Shredding of woody vegetation is permitted but shall be shredded or grubbed to a depth to remove the root wad.

6. Access paths/haul roads

i. This area does not require grubbing and clearing, the contractor shall develop routes to minimize damage to current vegetation.

ii. Access routes/ haul roads shall be approved by engineer prior to construction.

5. Spoil piles shall be constructed so the side slope does not exceed 6:1 and the height does not exceed 7 feet. The excess material pile(s) cannot block or divert drainage in a manner to cause damage to adjacent land.

6. Any trash or hazardous material found shall be removed and properly disposed of by the contractor.

The disposal of excavated material will be by Method 1 under Item 5 Disposal of Waste Materials.

The Contractor shall take great care to not over excavate beyond the specified maximum depth in the borrow areas required for construction.

Under Section 9 -Measurement and payment, no payment method shall be used. Payment for each type of excavation is made at the contract unit price for that type of excavation. Such payment will constitute full compensation for all labor, material, equipment, and all other items necessary and incidental to the performance of the work, with the exception that the final quantities shall not be measured unless there is a significant change to the plans. This includes cost to meet all decommissioning procedures and quantity according to the plans. It shall be the contractor's responsibility to prove this quantity difference to the

May 5, 2025 21-6

COTR. If there are no changes to the plans, then the estimated volumes shall be used.

Payment is by lump sum.