This document provides details for a federal construction services solicitation. The solicitation seeks proposals to correct electrical panelboard deficiencies at Building 1 for the Gainesville Veterans Affairs Medical Center. Proposals are due by August 31, 2022 at 3:30 PM. The requirement is set aside for Service-Disabled Veteran-Owned Small Businesses, which can be verified on the Vendor Verification portal. The point of contact for the project is Eugene Rusiecki, and a mandatory site visit is scheduled for August 10, 2022 at 1:00 PM at the Gainesville VAMC. The work will be awarded under Solicitation Number 36C24822R0157 by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 8.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Total Construction Cost

CONSTRUCTION COST PROGRAM - ESTIMATE WORKSHEETDATE:12/31/99
PROJECT NO.PROJECT TITLELOCATIONsDATE:
000$0.00
ESTIMATORTOTAL CONSTRUCTION COST SUMMARYBUILDING NO(S)DRAWING NOs.$0.00
000$0.00
NRMLABOR (w/ equip)MATERIALS
CODECSI #The StartSYSTEMS/SUBSYSTEMQTYUNIT$/UNITTOTAL$/UNITTOTALTOTAL
16 DIV. CONSTRUCTION COST$0
TOTAL CONSTRUCTION COST (Low Bid)$0
$0
Subtotal$0
Impact Cost with R.O.P
Subtotal$0
Subtotal$0
TOTAL PROJECT COSTS$0

&RSHEET NO &P OF &N

Detail Base Offer Cost Breakdown

"FOR OFFICIAL USE ONLY"

ESTIMATE WORKSHEET
Project NumberLocationPROJECT NAMEDATE:
TYPE OF ESTIMATE:ESTIMATOR:BUILDING NO./LOCATION:
LABORMATERIALS/EQUIPMENTTOTAL COST BY ITEM
CODE:The StartSYSTEM/SUBSYSTEMQTYUNIT$/UNITTOTAL$/UNITTOTAL
1GENERAL CONDITIONS$0.00
1Mobilization/Demobilization
2Permits/Environmental Regulations Compliance
3Safety Requirements
4Maintenance of Traffic (MOT)
2Existing Conditionsea$0.00$0.00$0.00
1Removal of Wood Floor Systemea$0.00$0.00$0.00
2Removal of Metal Floor System and Connectionsea$0.00$0.00$0.00
3Paint Removalea$0.00$0.00$0.00
4Chain-Link Fabric Removalea$0.00$0.00$0.00
5Miscellaneous Removal (signs, wiring,conduits, etc.ea'$0.00$0.00$0.00
3CONCRETEea$0.00$0.00$0.00
1Cracks Repairs at Concrete Rampsea$0.00$0.00$0.00
4METALSea$0.00$0.00$0.00
1Retrofit of Existing Structural Connectionsea$0.00$0.00$0.00
2New Floor Systemea$0.00$0.00$0.00
3New Connections for Floor Systemea$0.00$0.00$0.00
5FINISHESea$0.00$0.00$0.00
1Protective Paint Coating (Epoxy)ea$0.00$0.00$0.00
2Finish Paint Coatingea$0.00$0.00$0.00
6SPECIALTIESea$0.00$0.00$0.00
1New Vinyl Coated Chain Link Fabricea$0.00$0.00$0.00
2New Green Chain Link Fence Privacy Slatsea$0.00$0.00$0.00
3New Signageea$0.00$0.00$0.00
7ELECTRICALea$0.00$0.00$0.00
1Electrical Conduits, Wiring, Junctions, Lightingea$0.00$0.00$0.00
8BRIDGE MODIFICATIONSea$0.00$0.00$0.00
1Lightning Protection Systemea$0.00$0.00$0.00
2Structure Adaptations (To comply with current codes)$0.00$0.00$0.00
3Roof Cover$0.00$0.00$0.00
$0.00$0.00$0.00
$0.00$0.00$0.00
$0.00$0.00$0.00
$0.00$0.00$0.00
$0.00$0.00$0.00
Subtotal$0.00$0.00$0.00
Overhead %
Profit %
Bond %$$
Overhead/Profit Subtotals:$0.00$0.00$0.00
Total Base Offer Cost

&RSHEET NO &P OF &N

File details come from the government source that posted it. Updated .