Attachment 05 - SOW Fisher House Sitework.pdf

PDF 66 KB Posted

Attached to
Z2LB--Fisher House Site Preparation, Minor Construction Project
Solicitation number
553-305
Issued by

About this file

This Statement of Work (SOW) details a minor construction project for the Detroit Fisher House site preparation, divided into two phases. Phase one involves removing and replacing 1,500 square feet of damaged sidewalk along Bethune Street and adding 180 square feet of new sidewalk at the Fisher House entry. Phase two includes removing and replacing 220 linear feet of curbing, gutter, and catch basins, expanding the existing irrigation system, adding green space, and planting six Bosque Elm canopy trees.

The project is a Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside with a contract value between $100,000 and $250,000, managed by the Department of Veterans Affairs Technology Acquisition Center Austin. Work will be performed at the John D. Dingell VA Fisher House in Detroit, Michigan, during weekday hours from 7:00am to 4:30pm, with a total completion timeline of 45 calendar days after receiving the Notice to Proceed. The contractor is responsible for installing safety fencing, coordinating with the City of Detroit, and obtaining all necessary city permits.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work Fisher House Sitework, Detroit, MI

Description of Work

The construction project will remove and replace existing sidewalk, catch basins, gutter, curbing, and provide landscaping along Bethune Street at the Detroit Fisher House as described below. It is anticipated that the work will be broken up into two (2) phases. Phase one will remove and replace fifteen hundred (1500) sqft of damaged sidewalk along Bethune Street and add one hundred eighty

(180) sqft of new sidewalk at the Fisher House entry. Phase two will remove and replace two hundred twenty (220) LF of curbing, gutter, and catch basins, tie into, and expand on the existing irrigation system, add green space, and plant six (6) new Trees. The contractor is responsible for installing safety fencing to keep pedestrian and automobile traffic out of work site, coordinating all work with the City of Detroit, and obtaining all city permitting for the satisfactory completion of all work. Work shall be performed during the hours of 7:00am – 4:30pm Monday through Friday located at John D. Dingell VA Fisher House, Detroit, Michigan. All work shall be completed within forty-five

(45) calendar days after receipt of Notice to Proceed.

Remove and Replace Existing Sidewalk(s):

Existing sidewalk concrete shall be replaced in accordance with design specifications, and city of Detroit engineering division D.P.W standards and details. Remove and replace concrete as described below.

Remove existing concrete, haul off site, and dispose of as required by local law. Recycle concrete as much as possible.

Install new concrete sidewalk in area(s) shown in drawings. Concrete will be 6” thick 3500# with control joints and will be doweled into the adjoining slabs at 12” o.c. using NO. 13 (½” ) bar, broom finished to match adjoining surfaces in accordance with city of Detroit engineering division D.P.W standards and details. Construction areas shall remain barricaded and fenced off until area is cured properly and can support foot traffic.

Addition of New Sidewalk(s):

Install new concrete sidewalk in area(s) shown in drawings. Concrete will be 6” thick 3500# with control joints and will be doweled into the adjoining slabs at 12” o.c. using NO. 13 (½” ) bar, broom finished to match adjoining surfaces in accordance with city of Detroit engineering division D.P.W standards and details. Construction areas shall remain barricaded and fenced off until area is

Remove and Replace Existing Curbing and Gutter:

Remove and replace curbing and gutter in accordance with design specifications, and city of Detroit engineering division D.P.W standards and details. Remove and replace concrete as described below.

Remove existing concrete, haul off site, and dispose of as required by local law. Recycle concrete as much as possible.

Install new integral concrete curbing and gutter in areas shown on drawings. Concrete curb shall meet the city of Detroit city engineering division, D.P.W. standard plan for standard curb details, doweled into the adjoining slabs at using NO 13 (½”) bar. Finish concrete surface to match adjoining curb surfaces. Construction areas shall remain barricaded and fenced off until area is

Landscaping:

Prepare green space for new sod, six (6”) inch depth, topsoil, new irrigation lines and tie-in to existing, pop-up spray heads four (4) inch riser, and six (6) Bosque Elm canopy trees to match existing.

Remove excess spoils, haul off site, and dispose of as required in accordance with Federal, State, and local law.