USDA Forest Service Project Specifications
5/14/2020 PNW – Olympia Asbestos Abatement 1 OF 23
TABLE OF CONTENTS
SECTION 00 00 50 - PROJECT DESCRIPTION
SECTION 00 01 00 - MEASUREMENT AND PAYMENT
SECTION 00 19 00 – MOBILIZATION
SECTION 01 40 00 - QUALITY REQUIREMENTS
SECTION 02 82 13 – ASBESTOS ABATEMENT
SECTION 09 65 00 – RESILIENT FLOORING
5/14/2020 PNW – Olympia Asbestos Abatement 2 OF 23
SECTION 00 00 50
PROJECT DESCRIPTION
1. PART I – GENERAL
1.01 PROJECT DESCRIPTION
1. Move room furnishings (tables, desk, refrigerators, lab equipment; items identified during Pre-Bid walk-through) and coordinate with the COR the temporary storage/placement of furnishings while work in each individual room is being accomplished.
2. Remove existing asbestos floor tiling and asbestos containing mastic from:
Base Rooms (Approx. 2100 SF): Rooms 117,128, 206, 208, 211, 215, 216, 301, 304, 306, 310, 311.
Additive Rooms (Approx. 2400 SF): Rooms 118, 123, 124, 125, 126, 129, 202, 203, 207, 302, 303, 305.
See drawings for exact location of work areas.
3. Install new government furnished commercial grade Vinyl Composition Tile (VCT) as new floor covering in all areas where asbestos tile was removed. Provide and install new rubber cove base around new VCT flooring.
1.02 RELATED WORK
A. The work shall be in accordance with the following subsidiary specifications. The subsidiary specifications are referred to in the text by the Section designation only.
2. PART II - PRODUCTS
2.01 N/A
3. PART III - EXECUTION
3.01 UTILITIES
A. Utilities, (electricity and water) will be available for contractor's use, limited to reasonable use for construction. It shall be the contractor's responsibility to maintain water and electrical needed to maintain safe conditions.
3.02 BUILDING ENVIRONMENT
A. Contractor shall maintain a clean, dust free office environment throughout the progress of work.
3.03 WORK NOT INCLUDED
A. N/A.
3.04 ALL OTHER PRODUCTS AND EXECUTION
A. Work shall be in accordance with the drawings and the project specifications.
END OF SECTION 00 00 50
5/14/2020 PNW – Olympia Asbestos Abatement 3 OF 23
SECTION 00 01 00
MEASUREMENT AND PAYMENT
4. PART I - GENERAL
4.01 MEASUREMENT AND PAYMENT
A. Measurement and payment for contract work will be made only for and under those pay items included in the SCHEDULE OF ITEMS. All other work and materials will be considered as included in the payment for items shown.
B. When more than one class, size, or thickness is specified in the SCHEDULE OF ITEMS for any pay item, suffixes will be added to the item number to differentiate between items to be bid.
4.02 DETERMINATION OF QUANTITIES
A. The following methods of measurement are used to determine contract quantities for payment.
1. For individual construction items, longitudinal and lateral measurements for area computations will be made horizontally or corrected to horizontal measurement unless otherwise specified. Measurements for seeding, mulching, geotextiles, netting, erosion control blankets, and sodding will be along slope lines.
2. Structures will be measured according to neat lines SHOWN ON THE DRAWINGS or as altered by the Engineer in writing to fit field conditions.
3. For items that are measured by the linear foot, measurements will be made parallel to the base or foundation upon which the structures are placed
4. For standard manufactured items, such as fence, wire, plates, rolled shapes, pipe conduits, etc., identified by gauge, weight, section dimensions, etc., such identification shall be considered the nominal weights or dimensions. Unless controlled by tolerances in cited specifications, manufacturer's tolerances will be accepted.
4.03 UNITS OF MEASUREMENT
A. Payment will be by units defined and determined according to U.S. Standard measure as follows:
1. Acre – Make longitudinal and transverse measurements for area computations horizontally.
2. Cubic Yard - A measurement computed by one of the following methods:
a. Material in the Delivery Vehicle - The measurement computed using measurements of material in the hauling vehicles at the point of delivery.
Vehicles shall be loaded to at least their water level capacity. Leveling of the loads may be required when vehicles arrive at the delivery point.
3. Cubic Yard Mile - A combination of linear and volumetric measurement meaning the movement of a cubic yard of material 1 mile.
4. Each - One complete unit, which may consist of one or more parts.
5. Gallon – The quantity may be measured by any of the following methods:
a. Measured volume container.
b. Metered volume. Use an approved metering system.
c. Commercially packaged volumes.
5/14/2020 PNW – Olympia Asbestos Abatement 4 OF 23
6. Hour – Measurement will be for the actual number of hours ordered and performed by the Contractor.
7. Linear Foot – Measure from end to end, parallel to the base or foundation being measured, or horizontal.
8. Mile – Measure horizontal along the centerline of each roadway, approach road, or ramp.
9. Pound – If sacked or packaged material is furnished, the net weight as packed by the manufacturer may be used.
10. Square Foot - Measure on a plane parallel to the surface being measured or horizontal.
11. Square Yard – Measure on a plane parallel to the surface being measured or horizontal.
12. Ton - Short ton consisting of 2,000 pounds.
13. Ton Mile - A combination of linear and weight measurement meaning the movement of
1 ton of material 1 mile.
14. Lump Sum – One complete unit.
4.04 METHODS OF MEASUREMENT
A. One of the following methods of measurement for determining final payment is
DESIGNATED on the SCHEDULE OF ITEMS for each pay item:
1. Designed Quantities (DQ) - These quantities denote the final number of units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units SHOWN in the SCHEDULE OF ITEMS may be authorized under any of the following conditions:
a. As a result of changes in the work authorized by the Contracting Officer.
b. As a result of the Contracting Officer determining that errors exist in the original design data used to determine designed quantities that cause a pay item to change by 15 percent or more.
c. As a result of the Contractor submitting to the Contracting Officer a written request showing evidence of errors in the original design data used to determine design quantities that cause a pay item total to change by 15 percent or more.
The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.
2. Staked Quantities (SQ) - These quantities are determined from staked measurements prior to construction.
3. Actual Quantities (AQ) - These quantities are determined from measurements of completed work.
4. Vehicle Quantities (VQ) - These quantities are measured or weighed in hauling vehicles.
5. Lump Sum Quantities (LSQ) - These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They will not be measured.
5/14/2020 PNW – Olympia Asbestos Abatement 5 OF 23
5.
6. PART II - PRODUCTS (NOT APPLICABLE)
7.
8. PART III - EXECUTION (NOT APPLICABLE)
END OF SECTION 00 01 00
5/14/2020 PNW – Olympia Asbestos Abatement 6 OF 23
SECTION 00 19 00
MOBILIZATION
9. PART I - GENERAL
9.01 MOBILIZATION
A. This item is intended to compensate the Contractor for operations including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; for payment of premiums for bonds and insurance for the project; and for any other work and operations which must be performed or costs that must be incurred incident to the initiation of meaningful work at the site and for which payment is not otherwise provided for under the contract.
9.02 METHOD OF MEASUREMENT
A. The measurement shall be lump sum for mobilization.
9.03 BASIS OF PAYMENT
A. The lump sum price shall include full compensation for mobilization. Progress payments for mobilization will be made as follows:
1. Bond premiums will be reimbursed after receipt of the evidence of payment.
2. 50% of the lump sum, not to exceed 5% of the original contract amount, will be paid following completion of 5% of the original contract amount not including mobilization and bond premiums.
3. Payment of the remaining portion of the lump sum, up to 10% of the original contract amount, will be paid following completion of 10% of the original contract amount not including mobilization and bond premiums.
B. Any portion of the lump sum in excess of 10% of the original contract amount will be paid after final acceptance.
C. Progress payments for mobilization and preparatory work shall be subject to retainage.
10. PART II - PRODUCTS (NOT APPLICABLE)
11. PART III - EXECUTION (NOT APPLICABLE)
END OF SECTION 00 19 00
5/14/2020 PNW – Olympia Asbestos Abatement 7 OF 23
SECTION 01 40 00
QUALITY REQUIREMENTS
12. PART I - GENERAL
12.01 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 01 Specification Sections, apply to this Section.
12.02 SUMMARY
A. This Section includes administrative and procedural requirements for quality assurance and quality control.
B. Testing and inspecting services are required to verify compliance with requirements specified or indicated. These services do not relieve Contractor of responsibility for compliance with the Contract Document requirements.
1. Specific quality-assurance and -control requirements for individual construction activities are specified in the Sections that specify those activities. Requirements in those Sections may also cover production of standard products.
2. Specified tests, inspections, and related actions do not limit Contractor's other quality-assurance and -control procedures that facilitate compliance with the Contract
Document requirements.
3. Requirements for Contractor to provide quality-assurance and -control services required by Design Professional, Owner, CO, or authorities having jurisdiction are not limited by provisions of this Section.
C. Related Sections include the following:
1. Division 01 Section "Cutting and Patching" for repair and restoration of construction disturbed by testing and inspecting activities.
2. Divisions 02 through 49 Sections for specific test and inspection requirements.
12.03 DEFINITIONS
A. Quality-Assurance Services: Activities, actions, and procedures performed before and during execution of the Work to guard against defects and deficiencies and substantiate that proposed construction will comply with requirements.
B. Quality-Control Services: Tests, inspections, procedures, and related actions during and after execution of the Work to evaluate that actual products incorporated into the Work and completed construction comply with requirements. Services do not include contract enforcement activities performed by Construction Project Manager.
C. Preconstruction Testing: Tests and inspections that are performed specifically for the Project before products and materials are incorporated into the Work to verify performance or compliance with specified criteria.
D. Product Testing: Tests and inspections that are performed by an NRTL, an NVLAP, or a testing agency qualified to conduct product testing and acceptable to authorities having jurisdiction, to establish product performance and compliance with industry standards.
E. Source Quality-Control Testing: Tests and inspections that are performed at the source, i.e., plant, mill, factory, or shop.
5/14/2020 PNW – Olympia Asbestos Abatement 8 OF 23
F. Field Quality-Control Testing: Tests and inspections that are performed on-site for installation of the Work and for completed Work.
G. Testing Agency: An entity engaged to perform specific tests, inspections, or both. Testing laboratory shall mean the same as testing agency.
H. Installer/Applicator/Erector: Contractor or another entity engaged by Contractor as an employee, Subcontractor, or Sub-subcontractor, to perform a particular construction operation, including installation, erection, application, and similar operations.
1. Using a term such as "carpentry" does not imply that certain construction activities must be performed by accredited or unionized individuals of a corresponding generic name, such as "carpenter." It also does not imply that requirements specified apply exclusively to tradespeople of the corresponding generic name.
I. Experienced: When used with an entity, "experienced" means having successfully completed a minimum of five previous projects similar in size and scope to this Project; being familiar with special requirements indicated; and having complied with requirements of authorities having jurisdiction.
12.04 CONFLICTING REQUIREMENTS
A. General: If compliance with two or more standards is specified and the standards establish different or conflicting requirements for minimum quantities or quality levels, comply with the most stringent requirement. Refer uncertainties and requirements that are different, but apparently equal, to Construction Project Manager for a decision before proceeding.
B. Minimum Quantity or Quality Levels: The quantity or quality level shown or specified shall be the minimum provided or performed. The actual installation may comply exactly with the minimum quantity or quality specified, or it may exceed the minimum within reasonable limits. To comply with these requirements, indicated numeric values are minimum or maximum, as appropriate, for the context of requirements. Refer uncertainties to Architect for a decision before proceeding.
12.05 SUBMITTALS
A. Qualification Data: For testing agencies specified in "Quality Assurance" Article to demonstrate their capabilities and experience. Include proof of qualifications in the form of a recent report on the inspection of the testing agency by a recognized authority.
B. Permits, Licenses, and Certificates: For Owner's records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents, established for compliance with standards and regulations bearing on performance of the Work.
12.06 QUALITY ASSURANCE
A. General: Qualifications paragraphs in this Article establish the minimum qualification levels required; individual Specification Sections specify additional requirements.
B. Installer Qualifications: A firm or individual experienced in installing, erecting, or assembling work similar in material, design, and extent to that indicated for this Project, whose work has resulted in construction with a record of successful in-service performance.
C. Manufacturer Qualifications: A firm experienced in manufacturing products or systems similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units.
5/14/2020 PNW – Olympia Asbestos Abatement 9 OF 23
D. Fabricator Qualifications: A firm experienced in producing products similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units.
E. Professional Engineer Qualifications: A professional engineer who is legally qualified to practice in jurisdiction where Project is located and who is experienced in providing engineering services of the kind indicated. Engineering services are defined as those performed for installations of the system, assembly, or product that are similar to those indicated for this Project in material, design, and extent.
F. Specialists: Certain sections of the Specifications require that specific construction activities shall be performed by entities who are recognized experts in those operations. Specialists shall satisfy qualification requirements indicated and shall be engaged for the activities indicated.
1. Requirement for specialists shall not supersede building codes and regulations governing the Work.
12.07 QUALITY CONTROL
A. Owner Responsibilities: All quality-control services are indicated as Contractor’s responsibility.
B. Contractor to provide quality-control services specified and those required by authorities having jurisdiction. Perform quality-control services required of Contractor by authorities having jurisdiction, whether specified or not.
1. Contractor shall engage a qualified testing agency to perform these quality-control services.
a. Contractor shall not employ same entity engaged by Owner, unless agreed to in writing by Owner.
b. It is the Contractor's responsibility to submit a certified written report, in duplicate, of each quality-control service.
c. Notify testing agencies at least 24 hours in advance of time when Work that requires testing or inspecting will be performed.
2. Testing and inspecting requested by Contractor and not required by the Contract
Documents are Contractor's responsibility.
3. Submit additional copies of each written report directly to authorities having jurisdiction, when they so direct.
C. Manufacturer's Field Services: Where indicated, engage a factory-authorized service representative to inspect field-assembled components and equipment installation, including service connections. Report results in writing as specified in Division 01 Section "Submittal
Procedures."
D. Coordination: Coordinate sequence of activities to accommodate required quality-assurance and -control services with a minimum of delay and to avoid necessity of removing and replacing construction to accommodate testing and inspecting.
1. Schedule times for tests, inspections, obtaining samples, and similar activities.
5/14/2020 PNW – Olympia Asbestos Abatement 10 OF 23
13. PART II - PRODUCTS (NOT USED)
14. PART III - EXECUTION
14.01 TEST AND INSPECTION LOG
A. Prepare a record of tests and inspections. Include the following:
1. Date test or inspection was conducted.
2. Description of the Work tested or inspected.
3. Date test or inspection results were transmitted to Architect.
4. Identification of testing agency or special inspector conducting test or inspection.
B. Maintain log at Project site. Post changes and modifications as they occur. Provide access to test and inspection log for Construction Project Manager's reference during normal working hours.
14.02 REPAIR AND PROTECTION
A. General: On completion of testing, inspecting, sample taking, and similar services, repair damaged construction and restore substrates and finishes.
1. Provide materials and comply with installation requirements specified in other
Specification Sections. Restore patched areas and extend restoration into adjoining areas with durable seams that are as invisible as possible.
2. Comply with the Contract Document requirements for Division 01 Section "Cutting and Patching."
B. Protect construction exposed by or for quality-control service activities.
C. Repair and protection are Contractor's responsibility, regardless of the assignment of responsibility for quality-control services.
END OF SECTION 01 40 00
5/14/2020 PNW – Olympia Asbestos Abatement 11 OF 23
SECTION 02 82 13
ASBESTOS ABATEMENT
PART 1 GENERAL
1.01 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other
Division 01 Specification Sections, apply to this Section.
1.02 DESCRIPTION OF WORK
A. The work requires the disturbance, repair, removal, and disposal of the following asbestos-containing material
(ACM) and associated non-asbestos containing materials for the accomplishment of the work as shown on the drawings and as specified herein:
1. Refer to the "Asbestos Survey Report for Maintenance and Renovation, January 2012 Report" (an update to the 1993 Good Faith Asbestos Inspection).
2. The Scope of Work consists of the proper removal and disposal of only the asbestos containing material indicated and as required for the completion of the project.
3. Asbestos debris in the work areas are to be removed and the areas cleaned in accordance with the contract and the contractor's approved work plan.
4. The certified lab results report provided by the Contracting Officer indicate the presence of asbestos containing materials (ACM) and will require the use of an accredited asbestos abatement contractor for the disturbance and removal of all affected ACM prior to and during renovation.
B. Schedule:
1. The abatement contractor is required to coordinate with the General Contractor and all trades for requirements to meet the project schedule.
1.03 ASBESTOS-CONTAINING MATERIALS
A. It is the responsibility of the Contractor to verify actual quantities of asbestos-containing materials to be removed and to obtain the Contracting Officer's concurrence in writing, prior to removal.
1.04 DEFINITIONS AND ABBREVIATIONS
A. Definitions and abbreviations pertaining to asbestos removal and disposal are provided in the regulations, codes, and standards listed below.
B. General Requirements: All work shall be done in compliance with the publications listed in this section as well as all
Occupational Safety and Health Standards, the Uniform Building Code, Uniform Plumbing Code, Uniform Fire
Code, the National Electrical Code, and as specified herein:
C. Title 29 CFR Part 1910
General Occupational Safety and Health Standards
Subpart E. Means of Egress
Subpart I. Personal Protective Equipment
Subpart Z. Toxic and Hazardous Substances
D. Title 29 CFR Part 1926
Safety and Health Regulations for Construction
Subpart C. General Safety and Health Provisions
Subpart D. Occupational Health and Environmental Controls
Subpart F. Fire Protection and Prevention
Subpart Z. Toxic and Hazardous Substances
5/14/2020 PNW – Olympia Asbestos Abatement 12 OF 23
Section 1926.1101 Asbestos
E. Title 40 CFR Part 61
Environmental Protection Agency Hazardous Air Pollution
Subpart A. General Conditions
Subpart M. National Emission Standard for Asbestos
F. Title 40 CFR Part 763
Environmental Protection Agency
Subpart E. Asbestos-Containing Materials in Schools
Subpart F. Friable Asbestos-Containing Materials in Schools
Subpart G. Asbestos Abatement Projects
G. 49 CFR 100-180 and 382
Department of Transportation
H. Public Law 101-637
Asbestos School Hazard Abatement Reauthorization Act
I. Federal Standard 313B
Material Safety Data Sheets
J. American National Standard Institute (ANSI)
Z9.2-79 Local Exhaust Systems
Z87.1-89 Eye and Face Protection
Z88.2-80 Practices for Respiratory Protection
K. International Fire Code Institute
Uniform Fire Code (UFC) 1994 UFC Standards
L. National Fire Protection Association (NFPA)
NFPA 701 (1989) Fire Tests for Flame-Resistant Textiles and Films
1.05 QUALITY ASSURANCE
A. On-site Observation:
1. During all and or any asbestos abatement there shall be a Competent Person present, having the qualifications and authorities for ensuring worker safety and health required by Subpart C, General
Safety and Health Provisions for Construction (29 CFR 1926.1020 through 1926.32
2. The safety and protection of the Contractor's employees, sub-contractor's employees, Government's employees, other occupants, the facility, and the public is the sole responsibility of the Contractor.
B. Air Monitoring:
1. The Contractor shall be responsible for monitoring its employees for potential exposure to asbestos fibers as required by 29 CFR 1926.1101(f)(1-6).
2. The Contractor shall be responsible for work area monitoring and environmental monitoring outside the work area as required by, 29 CFR 1926.1101(f)(1-6).
5/14/2020 PNW – Olympia Asbestos Abatement 13 OF 23
3. The Contractor shall conduct personnel monitoring continuously during asbestos removal operations to determine the 8-hour time weighted exposure and 30-minute short term excursion limit exposure of workers to airborne fibers, as described in 29 CFR 1926.1101 (f)(1)(iii).
4. The Contractor shall collect and have a certified laboratory analyze by phase contrast microscopy
(PCM), using the NIOSH Analytical Procedure 7400, pre-abatement and pre-clearance samples in accordance with 29 CFR 1926.110 Appendix A and 40 CFR 762 Subpart M.
5. The Contractor shall deliver all air samples to its designated laboratory for analysis within one working day of collection. The Contractor shall direct its laboratory, in writing, to forward by facsimile all employees and work site air monitoring data, and all other pertinent data and records, to the Contracting
Officer's Representative within one working day of sample receipt.
6. The Contractor shall have its laboratory archive all air samples until the successful completion of the project.
C. The Contractor shall perform initial exposure assessments (Air Monitoring) as required by 29 CFR
1926.1101(f)(2)(iii).
1.06 PROTECTION OF EXISTING WORK
A. Perform asbestos removal in the project work areas without contamination of adjacent work.
1.07 MEDICAL REQUIREMENTS
A. Institute a medical surveillance program for employees in accordance with 29 CFR 1926.1101 Appendix D.
B. Provide random drug testing, as required by 49 CFR 382, for all drivers of vehicles transporting asbestos or hazardous materials.
1.08 PERMITS AND NOTIFICATIONS
A. Make all required notifications for asbestos removal, hauling, and disposal as required by federal, state, and local authorities.
1.09 SAFETY COMPLIANCE
A. Comply with laws, ordinances, rules, and regulations of federal, state, and local authorities regarding handling, storing, transporting, and disposing of hazardous materials and all other construction activities.
1.10 RESPIRATOR PROGRAM
A. Establish a respirator program as required by 29 CFR 1910.134(b) through (d)
1.11 INITIAL SUBMITTAL
A. The Contractor shall submit three (3) bound, indexed copies with the following documentation to the Contracting
Officer for review, approval, or rejection, at least ten working days prior to scheduled commencement of work. The
Contractor is responsible for delays caused by late submittals. Submittal packages shall be organized and indexed in the order provided in the checklist 1.11.A.1 through 1.11.A.12. See Sub-sections1.11.B through 1.11.M for detailed descriptions of individual submittal requirements.
B. Submittals not properly organized and indexed will be rejected.
1. Contractor's work and compliance plan including type, location and quantities of ACM to be abated.
2. Contractor's asbestos liability insurance policy.
3. Contractor's schedule.
4. Contractor's testing laboratory.
5. Disposal site designations.
6. Waste transporter designation.
7. Manufacturer's product data sheets and material safety data sheets (MSDS).
5/14/2020 PNW – Olympia Asbestos Abatement 14 OF 23
8. Contractor's representations.
9. Contractor's notifications.
10. Contractor's Asbestos Certifications.
11. Contractor's request for substitutions.
12. Contractor's AHERA Project Designer review.
13.
C. The Work Plan shall include procedures for:
1. The Work Plan shall specifically address asbestos removal and disposal procedures as required for asbestos abatement as required in 29 CFR 1926.1101 (g)(4) through (7) and 40 CFR 61.
2. The Work Plan shall be reviewed and certified as meeting Federal State, and local regulatory requirements and the requirements stated herein by an EPA-Certified Project Designer, prior to submittal. The Project Designer shall indicate his approval and certification by a signed cover letter attached to the work plan.
D. Insurance Policy: Submit copies of the Contractor's asbestos liability insurance policy, in accordance with specifications.
E. Schedule: Submit construction schedule by work area that meets the requirements of Sub-section 3.03 of this section.
F. Testing Laboratory: Submit the name, location, and phone number of proposed certified testing laboratory.
G. Disposal Site: Submit the name and location of the proposed EPA permitted disposal site.
H. Waste Transporter: Submit the name and address of the proposed waste transporter.
I. Manufacturer's product data sheets and MSDS: Submit legible copies of manufacturer's product data sheets that describe product usage and restrictions, application procedures, and safety precautions. Submit copies of all MSDS for tape, plastic sheeting, solvents, encapsulants, adhesives, and lock-down chemicals.
J. Representations: Submit statement signed by a Principal of the Contractor that records of employees' work assignments, certifications, respirator fit tests, and medical examinations are accurate, up-to-date, and available for inspection.
K. Notifications:
1. Submit appropriate asbestos abatement Notification to the following agencies per applicable regulations: Washington State’s Department of Ecology
L. Submit legible, current copies of the following asbestos certifications:
1. Certified Asbestos Supervisor/competent person: Submit the name of the proposed Certified Asbestos
Supervisor/competent person, a legible copy of his/her current Asbestos Supervisor Certificate, and a list of his/her previous projects.
2. Submit a legible copy of the current Certified Asbestos Worker (or Supervisor) Certificate for each employee who will be working on the project. If non-certified asbestos workers are used to remove the non-friable asphaltic roofing material, submit names and training rosters or training certificates showing each worker has completed the required minimum 8-hour training.
3. Submit a legible copy of Contractor's AHERA Project Designer who reviewed and certified the Work
Plan.
M. Substitutions: Submit proposals for substitutions of materials, equipment and methods to the Contracting Officer at least ten (10) working days prior to implementing the change.
1.12 PERIODIC SUBMITTALS
A. Submit the following information obtained during the course of the work to the Contracting Officer:
5/14/2020 PNW – Olympia Asbestos Abatement 15 OF 23
1. Initial Exposure Monitoring: Submit the results of the Contractor's initial exposure monitoring within two working days of sample collection.
2. Daily Air Monitoring: Have the Contractor's laboratory submit by facsimile daily, to the Contracting
Officer, all results of Contractor's daily air monitoring. Submittal shall consist of field data sheets and the analytical laboratory's results. Daily air monitoring submittals shall be furnished to the Contracting
Officer within two working days of collection of samples.
3. Project Daily Logs: Submit the previous day's Daily Logs.
4. Updated Project Information: Submit changes in project schedule or personnel at least 48 hours prior to the effective time of change for the following:
a. Updated schedules for asbestos removal.
b. Change in Certified Asbestos Supervisor, including, medical and fit test certificate.
c. Copies of the, medical, and fit test certificate for additional workers.
d. Copies of amended notifications.
e. Copies of amended disposal - waste manifest forms.
B. Negative pressure enclosures, if required, and work area barrier tape or demarcation shall not be removed until successful, final visual inspection has been accomplished by the Contracting Officer's Asbestos Consultant.
1.13 CLOSE-OUT SUBMITTAL
A. The Contractor shall within thirty (30) days of completion of the last scheduled abatement, submit three copies of the following documents with the application for final payment.
1. Employees' daily sign-in sheets.
2. Contractor's actual "Start and Finish" Project Dates.
3. Waste Shipment Records (40 CFR 61, Figure 4).
4. Disposal Site Receipts.
5. Revised Notification showing actual disposal amounts.
6. Statement of completion of asbestos abatement work as required by these specifications and drawings.
1.14 SANITARY FACILITIES
A. The Contractor shall provide adequate toilet facilities.
1.15 MATERIAL STORAGE
A. Store all materials subject to damage off the ground and secure from damage by weather or vandalism.
1.16 ON-SITE DOCUMENTATION
A. The Contractor shall maintain, on the job site, copies of the following data for safety, equipment, and supplies used for the work.
1. Equipment: Show the model, style, capacity, and the operation and maintenance procedures for the following, as applicable:
a. HEPA Vacuum cleaners.
b. HEPA air filtration units, if required.
2. Material Safety Data Sheets: The Contractor shall maintain a Material Safety Data Sheet for each tape, plastic sheeting, solvent, encapsulant, adhesive, and lock-down chemical proposed to be used as required by 29 CFR 1926.1101
3. Respiratory Protection Plan: The Contractor shall maintain on-site their written respirator program. The
Contractor's written and approved respirator program shall meet all requirements of 29 CFR
1910.134(b) through (d). Any deficiencies identified in the Contracting Officer's review of the respiratory protection plan shall be corrected prior to commencement of work.
1.17 METHOD OF MEASUREMENT
The measurement shall be actual quantity removed of tile. For miscellaneous items lump sum quantity will be used.
5/14/2020 PNW – Olympia Asbestos Abatement 16 OF 23
PART 2 PRODUCTS
2.01 RESPIRATORS
A. Provide personally issued and marked respirators approved by NIOSH and MSHA, and provide sufficient replacement canisters for respirators with disposable filters.
B. Provided respirators with the protection factors required by 29 CFR 1910.134 and 29 CFR 1926.1101(h)
C. Respirators shall be suitable for dual (“stacked”) cartridge use whenever both asbestos hazards and other respiratory hazards exist in the work area.
D. Respirators used for all work inside negative pressure enclosures shall offer sufficient protection for the expected potential exposure identified in the Initial Exposure Assessment required by 29 CFR 1926.1101(f)(2)(i)-(iii)
2.02 PROTECTIVE CLOTHING
A. Provide approved protective outer clothing, consisting of disposable fire retardant, full body coveralls and hoods fabricated from non-woven fabric. Personal protective equipment shall be provided and utilized to meet applicable safety regulations.
B. Cloth work clothes may be worn under disposable protective coveralls, boots and gloves for comfort as permitted by regulation, however if worn in a negative pressure enclosure, the cloth clothing must be removed and left in the equipment room as personnel exit the enclosure and must be laundered by the employer per the applicable instructions.
2.03 SEALANTS AND ENCAPSULANTS
A. Penetrating and bridging encapsulants for asbestos applications. "Lock-Down" encapsulants used in non-finished areas shall be tinted for identification in a color, which will not obscure residual asbestos. Encapsulants shall be compatible with replacement materials and shall not contain hazardous materials listed in 29 CFR 1910, Subpart Z.
2.04 SURFACTANT
A. A surfactant consisting of 50% polyoxyethylene ether and 50% polyoxyethylene ester (or an approved alternate) shall be used, and shall be mixed with water at the rate of one ounce of surfactant to 5 gallons of water or as recommended by the manufacturer.
2.05 MASTIC REMOVAL SOLVENTS
A. Mastic removal solvents, if used, shall be non-flammable and shall not contain halogenated compounds. Solvents shall be compatible with replacement materials. Solvents must be of the “low odor” or “no odor” variety and so indicate on the MSDS. Citrus based solvents do not meet these criteria.
2.06 PLASTIC SHEET
A. A minimum 6-mil thick flame resistant polyethylene (in accordance with NFPA 701) shall be used unless otherwise specified. The poly shall be sized in length and width to minimize the frequency of joints.
2.07 TAPE
A. Tape shall be capable of sealing joints of adjacent sheets of polyethylene, for attachment of polyethylene sheets to finished or unfinished surfaces and of adhering under both dry and wet conditions, including during use of amended water.
2.08 ADHESIVES
A. Adhesives shall be capable of sealing joints of adjacent sheets of polyethylene to finished or unfinished surfaces and of adhering under both dry and wet conditions.
5/14/2020 PNW – Olympia Asbestos Abatement 17 OF 23
2.09 DISPOSAL CONTAINERS
A. Disposal containers shall be suitable to receive, retain, and dispose of asbestos-containing or contaminated materials.
Containers shall be labeled in accordance with the applicable regulations and must be both airtight and watertight.
Plastic bags shall be a minimum 6-mil polyethylene, pre-printed with approved warning labels. Plastic wrap shall be
6 mil polyethylene sheets, securely wrapped and taped.
2.10 GLOVE BAGS
A. Shall be a minimum of 6 mil polyethylene and specially designed for removal of asbestos-bearing insulation.
2.11 EYE PROTECTION
A. The Contractor shall provide goggles to personnel engaged in asbestos operations, unless worker is required to wear a full-face piece respirator.
2.12 DANGER SIGNS AND LABELS
A. Danger signs and labels shall be affixed to all products or containers containing asbestos. The required signs shall be used to demarcate areas where asbestos waste is temporarily stored; and areas, not accessible to the public where asbestos-containing materials are left in place. Signs and labels shall be in accordance with applicable regulations and codes. The signs posted at work area entrance, exists, decontamination areas, and waste disposal areas shall comply with all applicable requirements.
2.13 OTHER MATERIALS
A. The Contractor shall provide standard commercial quality of all other materials that are required to prepare and complete the work.
2.14 TOOLS AND EQUIPMENT
A. Sprayers for amended water and encapsulant application shall be airless.
B. Vacuum cleaning equipment shall be manufactured for asbestos use and shall use HEPA filters on the discharge.
C. Scaffolding, hoists, and protective equipment shall meet all applicable safety regulations.
D. Transportation equipment shall be suitable for loading, temporary storage, transit, and unloading of contaminated waste without exposure to persons or property. All trucks or vans used to transport asbestos shall be enclosed and sealed watertight. The driver of the truck shall have a commercial driver's license with hazardous material endorsement.
E. Provide all other tools and equipment for removal, enclosure, encapsulation, patching, and disposal activities.
F. Electrical tools and equipment shall meet all applicable codes and regulations.
G. HEPA Filtration Units (if required) shall conform to ANSI Z9.2, and HEPA filters shall be UL-586 labeled.
H. Water Filtration Units shall be provided with filters of adequate capacity to treat decontamination washing and shower flows. Water filtration unit effluent shall contain less than 7,000,000 asbestos fibers per gallon.
5/14/2020 PNW – Olympia Asbestos Abatement 18 OF 23
PART 3 EXECUTION
3.01 WORK AREAS
A. Regulated Work Areas: Establish regulated work areas in compliance with 29 CFR 1926.1101 (b)-(e)
B. Decontamination Area: Install decontamination areas in compliance with 29 CFR 1926.1101, if required.
C. Negative Pressure Enclosure System: If required, construct Negative Pressure Enclosure Systems as required by 29
FR 1926.1101 (g)(5)(i)(A), these specifications, and approved work plan.
D. Notify Fire Marshal at least 24-hours before establishing a regulated area.
3.02 PERSONNEL PROTECTION PROCEDURES
A. Post the decontamination, safety, and work procedures to be followed by workers.
B. Provide continuous on-site supervision by the approved Certified Asbestos Supervisor.
C. Follow all worker protection procedures as described in the approved work plan.
D. Provide the highest level of respiratory protection unless approved and documented exposure assessments establish that a lower level of protection is adequate, as determined by the Certified Asbestos Supervisor, with the written concurrence of the Contracting Officer. For asbestos removal inside a negative pressure enclosure, respiratory protection shall be in accordance with the requirements of 29 CFR 1910.134, regardless of the exposure assessment.
E. Maintain a daily log of all workers and visitors entering regulated work areas. The log shall contain the name of each individual, his or her organization, accurate time of entering and leaving, and purpose of visit.
F. Monitor worker exposure to airborne asbestos fibers as required by 29 CFR 1926.1101 (f)(1-6).
G. Provide approved filters for other airborne contaminants (solvents, etc.) that may be present. These filters shall be used in combination with approved asbestos filters. At no time shall the permissible exposure limit (PEL) for any airborne contaminant exceed the PEL listed in 29 CFR 1910, Subpart Z
3.03 ASBESTOS REMOVAL PROCEDURES
A. Asbestos removal shall be in accordance with the Contractor's Approved Work Plan, applicable regulations, and this specification.
B. Fire exits and fire lanes shall not be blocked without prior written consent of the Contracting Officer and the fire marshal.
C. The Contracting Officer must concur in writing with the proposed Work Plan, prior to commencement of work.
3.04 AIR MONITORING
A. Airborne concentrations of asbestos fibers shall be monitored in accordance with 29 CFR 1926.1101 current EPA and OSHA guidance, and as specified herein. The Contracting Officer may perform independent monitoring of the work area and Contractor's employees. All monitoring shall be performed by trained industrial hygiene technicians or equivalent. All sampling pumps shall be calibrated in the field with a secondary calibration device before and after each sample. Built-in rotometers on pumps are not acceptable.
B. The minimum number of daily samples per work area without a negative exposure assessment are as follows:
1. One (1) air sample within the regulated work area.
2. One (1) air sample at least every other day, located outside the entrance to the work area.
3. Personnel samples (excluding excursion samples) shall be taken at least twice per eight-hour work shift at the rate of one sample for every six people performing that task in the same work area. Persons performing separate tasks or in separate work areas shall be sampled separately.
4. Excursion samples as required by 29 CFR 1926.1101(f)(1)(iii)
5/14/2020 PNW – Olympia Asbestos Abatement 19 OF 23
5. Two (2) waste load-out samples for the full duration of the operation, one taken inside the wash-down station and one taken on the clean side of the wash-down station. (No samples are necessary if no load-out operation is performed.)
6. All workers disturbing asbestos outside of a Negative- Pressure Enclosure System shall be monitored continuously.
7. In addition to the samples listed in paragraphs 1 through 6 above, when employing a negative pressure enclosure, take one (1) air sample every other day located at the entrance to the decontamination chamber and one (1) air sample located at the exhaust(s) of the HEPA filtration unit(s) (if more than one unit is used, the sampling may be rotated between units, however, each unit must be sampled at least once every other day). Decontamination chamber entrance and HEPA exhaust samples are not required if negative pressure enclosures are not used.
C. Daily monitoring may be discontinued only after the Contractor's Certified Asbestos Supervisor certifies in writing that a Negative Exposure Assessment, in accordance with 29 CFR 1926.1101(f)(2)(iii) has been obtained. Written concurrence must be obtained from the Contracting Officer prior to discontinuing daily monitoring.
3.05 DISPOSAL
A. Dispose of asbestos wastes in an EPA permitted asbestos landfill.
B. Comply with current waste handling, storage, transportation, and disposal requirements of the waste disposal facility, U.S. Department of Transportation, and EPA regulations.
C. Label waste containers and vehicles in accordance with 40 CFR Part 61 and 49 CFR 100-180. Affix warning labels having waterproof print and permanent adhesive to all waste containers. Affix a Class 9 label with ID number 2212 on all four sides of the waste transport vehicle.
D. Waste transport vehicles shall be lined with polyethylene and be fully enclosed.
E. Waste shipping papers shall identify waste as "Asbestos 9, NA 2212 III, RQ" and list the total quantity being transported in addition to the requirements of 40 CFR 61.
F. Workers loading waste shall wear protective clothing and canister type respirators.
3.06 CLEANING OF WORK AREA
A. Upon completion of asbestos repair or removal within a work area, remove visible accumulations of asbestos material and debris. Wet clean and HEPA vacuum all work area surfaces.
B. Ensure that all asbestos-containing materials have been removed from concave corners and textured surfaces
(i.e., concrete floors).
C. Notify the Contracting Officer that asbestos work has been completed, and that the work area is ready for final visual.
Include a statement that all asbestos in the work area has been removed, repaired, and/or encapsulated as required by the contract, and that all debris has been removed.
3.07 CLEARANCE AIR MONITORING
A. The Contractor will conduct final inspection and final third party air clearance monitoring. Final clearance air monitoring shall be conducted in accordance with 40 CFR 763 Subpart E. Phase Contrast Microscopy (PCM) or
Transmission Electron Microscopy (TEM) final air clearance samples, dependent on quantity of ACM removed, shall be collected using aggressive sampling. Final clearance levels shall be in accordance with 40 CFR 763 (e.g., 0.01 fibers per cubic centimeter for PCM clearance, or 70 structures per square millimeter for TEM). The Contractor will use twenty-four hour laboratory turn-around for all final clearance samples. PCM samples will be analyzed locally.
TEM samples will be shipped by next day delivery to the analytical laboratory.
B. Prior to admitting non-certified workers into areas regulated, the Contractor shall conduct a visual inspection to verify the completion of removal and clean-up and will conduct clearance air monitoring using phase contract microscopy (PCM). Airborne concentrations of asbestos fibers from the pre-clearance samples must be less than 0.01 fibers per cubic centimeter using PCM. Upon receipt of satisfactory air clearance results the Contractor will notify
5/14/2020 PNW – Olympia Asbestos Abatement 20 OF 23 the Contracting Officer's Representative that the work area is ready for final inspection and final air clearance sampling.
C. Final clearance air monitoring tests will not be performed until all areas and materials within the work area are fully clean, encapsulated and dry.
D. If the final clearance air monitoring results show that the work area has failed to meet the clearance criteria, the
Contracting Officer shall notify the Contractor. The Contractor shall re-clean the work area and collect and analyze an additional set of PCM clearance air monitoring samples whose asbestos concentration must be less than 0.01 fibers per cubic centimeter prior to requesting the Contracting Officer collect another set of final clearance air monitoring samples. All work specified in this paragraph shall be done at no additional expense to the Government, including all labor and laboratory fees of the Government.
E. Once the final clearance air monitoring results meet the clearance criteria of 40 CFR 763 Subpart E for the work, then the HEPA filtration units may be deactivated (if applicable) and all seals, barriers, barricades, and decontamination areas shall be dismantled and removed except for visqueen to remain in place to separate “clean” areas from “unclean” areas. The work area will then be released to unprotected workers.
F. Work area containment's and/or critical barriers shall not be removed until final clearance results are reviewed and accepted by the Contracting Officer.
3.08 SUBSTANTIAL COMPLETION
A. After the work area barriers have been removed, the Contractor shall conduct an additional inspection to verify that there was no asbestos debris, contaminated water, or other residue, concealed by the work area protection installations. Any such residue shall be cleaned up using HEPA vacuum cleaners and wet wiping methods.
B. After the Contractor certifies that the work area has been cleaned of all asbestos in compliance with the contract, the
Contractor shall conduct a final inspection to verify that there is no un-repaired damage to walls, ceilings, doors or surfaces or finishes other than that called for by the scope of work. Costs of restoration of damaged finishes shall be borne by the Contractor.
END OF SECTION
5/14/2020 PNW – Olympia Asbestos Abatement 21 OF 23
SECTION 09 65 00
RESILIENT FLOORING
PART 1 GENERAL
1. A. DRAWINGS AND GENERAL PROVISIONS OF THE CONTRACT, INCLUDING GENERAL
AND SUPPLEMENTARY CONDITIONS AND OTHER DIVISION 01 SPECIFICATION SECTIONS,
APPLY TO THIS SECTION.
2. SECTION INCLUDE
A. Resilient tile flooring (VCT)
B. Resilient base
C. Ceramic Tile
D. Installation accessories
3. REFERENCE STANDARDS
A. ASTM F 710-Standard Practices Concrete Floors to Receive Resilient Flooring
B. ASTM F 1066 1066 – Standard Specifications for Vinyl Composition Flooring Tile
C. ASTM F 1861- Standard Specification for Resilient Wall Base
4. SUBMITTALS
A. Product Data: Provide data on specified products, describing physical and performance characteristic; including size patterns and colors available; and installation instructions.
B. Selection Samples: Submit manufacturer’s complete set of color samples for Contracting
Officer’s initial selection.
C. Certification: Prior to installation of flooring, submit written certification by flooring manufacturer and adhesive manufacturer that condition of sub-flooring acceptable.
D. Maintenance Data: Include maintenance procedures, recommended maintenance materials, and suggested schedule for clearing, stripping and re-waxing.
5. DELIVERY, STORAGE, AND HANDLING
A. Protect rolls material from damage by storing on end.
6. METHOD OF MEASUREMENT
A. The measurement shall be actual quantity for resilient flooring and cove base.
PART 2 PRODUCTS
1. FIELD CONDITIONS
A. Maintain temperature in storage area between 55 degrees Fahrenheit and 90 degrees
Fahrenheit.
B. Store materials…
This is the start of the file's text. The full file is on GovTribe.