Attachment 02 - SAPR Office Wall and Door Price Breakdown.xlsx
XLSX spreadsheet 58 KB Posted
- Attached to
- B1118 SAPR Office Wall & Door
- Solicitation number
- FA480325R0024
About this file
The file contains a detailed price breakdown spreadsheet for a Small Business set-aside construction project at Shaw Air Force Base. The solicitation (FA480325R0024) is for the B1118 SAPR Office Wall & Door project, with a construction scope under $25,000 and a performance period not exceeding 30 days after Notice to Proceed. The project involves interior renovations including painting, wall base installation, ceiling work, partition walls, electrical conduit and wiring, and glass door installation.
Key procurement details include a mandatory site visit scheduled for 2 June 2025 at 9:30 AM, with base access requiring prior coordination through Contracting Officer Zelda Williams or Contract Specialist Kishauna Goodman. Proposal submission is due by 26 June 2025 at 2:00 PM EST. The work must comply with multiple codes and standards, including UFC, UFGS, IBC, IPC, NEC, NFPA, and Shaw Air Force Base Design and Construction Standards. The project is being executed by the Department of the Air Force Air Combat Command, with strict adherence to specified technical and safety requirements.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| ` | FOR OFFICE USE ONLY | ||||||||||||
| Project: | Proj Name | VLSB -25-2503 | Project Engineer: | Austin Baker | |||||||||
| Location: | 1118 | Department: | 20 CES | ||||||||||
| Contractor: | 6-Mar-25 | ||||||||||||
| Address: | |||||||||||||
| PR No.: | |||||||||||||
| For Official Use Only | |||||||||||||
| Reference | Line No. | Item | Unit of Measure | Quantity | Material Costs | Labor Costs | Direct Cost | Line Total | |||||
| Unit Cost (Means) | Total | Labor Hours per Unit (Means) | Labor Cost per Unit (Means) | Labor-Hours | Avg. Rate ($/hr) | Total | |||||||
| SAPR | |||||||||||||
| 1 | Paints & coatings, walls & ceilings, interior, concrete, drywall or plaster, latex paint, 3 coats, smooth finish, spray | S.F. | |||||||||||
| 2 | Wall base, vinyl, straight or cove, standard colors, 4" high, 1/8" thick | L.F. | |||||||||||
| 3 | Detection system, strobe & horn, excluding wires & conduits | Ea. | |||||||||||
| 4 | Acoustical ceilings, fiberglass boards, film faced, 2' x 2' or 2' x 4' x 5/8" thick | S.F. | |||||||||||
| 5 | Suspended ceiling systems, seismic clips, attached at walls | Ea. | |||||||||||
| 6 | Ceiling suspension system, class A, 15/16" T bar, 2' x 4' grid | S.F. | |||||||||||
| 7 | Ceiling demolition, suspended ceiling, mineral fiber, 2 x 2 or 2 x 4, remove | S.F. | |||||||||||
| 8 | Selective demolition, rubbish handling, dumpster, 6 C.Y., 2 ton capacity, weekly rental, includes one dump per week, cost to be added to demolition cost | Week | |||||||||||
| 9 | Partition wall, interior, standard, taped both sides, installed on & incl. 2" x 4" wood studs, 16" OC, 8' to 12' high, 1/2" gypsum drywall | S.F. | |||||||||||
| 10 | Cellulose fiber board, 1/2" thick | S.F. | |||||||||||
| 11 | Rigid galvanized steel conduit, 3/4" diameter, to 10' H, incl 2 terminations, 2 elbows, 11 beam clamps, and 11 couplings per 100 LF | L.F. | |||||||||||
| 12 | Wire, copper solid, 600 volt, #14, type THW, normal installation conditions in wireway, conduit, cable tray | C.L.F. | |||||||||||
| 13 | Doors, glass, swing, tempered, 1/2" thick, 3' x 7' opening, incl. hardware | Opng. | |||||||||||
| 14 | Field personnel, field engineer, engineer, average | Hours | |||||||||||
| 15 | Wire, copper solid, 600 volt, #12, type THW, normal installation conditions in wireway, conduit, cable tray | C.L.F. | |||||||||||
| 16 | Rigid galvanized steel conduit, 3/4" diameter, to 10' H, incl 2 terminations, 2 elbows, 11 beam clamps, and 11 couplings per 100 LF | L.F. |
Foreman days
Totals: $0.00 $0.00 $0.00 $0.00
| Total Material Cost: | $0.00 |
| Total Labor Cost: | $0.00 |
| Direct Cost: | $0.00 |
| Total Line Item Cost: | $0.00 |
| Overhead: | $0.00 |
| Subtotal: | $0.00 |
| Profit: | $0.00 |
| Subtotal: |
| Bond: |
| Total Contract Price: |
Sheet2
Sheet3
File details come from the government source that posted it. Updated .