This Statement of Work (SOW) details the replacement of an intrusion detection system for the Olympia Lab, a USDA facility experiencing repeated false alarm issues. The project requires installing a new system covering multiple buildings including the main building, maintenance building, pump house, warehouse, enclosed government parking area, and research planting area. Specific technical requirements include monitoring 19 doors across these locations, installing new glass brake sensors, removing in-room motion detection sensors, reusing existing low voltage wire if in good condition, installing six new arm/disarm keypad panels, connecting to existing off-site monitoring service, replacing alarm speakers, and utilizing existing beam sensors in the secured vehicle parking area. The contractor must be registered/licensed with a municipality as an Intrusion Detection installer and ensure all personnel are recognized professionals or supervised by professionals in commercial system installation. The project stems from Thurston County Police serving a violation notice due to frequent false alarms, with the agency indicating they will no longer respond to future alarms from the facility.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Department of Agriculture (USDA)

Statement of Work

Contents Project

General Information

1.0 Scope of Work

2.0 Background

Contractor Requirements

3.0 Technical Requirements / Tasks

4.0 Government Furnished

5.0 Deliverables / Schedule

6.0 Travel

7.0 Contractor’s Key Personnel

8.0 Security Requirements

9.0 Data Rights

10.0 Section 508 – Electronic and Information Technology Standards

Project Olympia Lab Upgrade Intrusion Detection System

General Information

1.0 Scope of Work

Work will consist of: Replacement of the existing intrusion detection system. The existing system covers multiple buildings and locations at the site. Areas to be covered under the new system are the main building, maintenance building, pump house, warehouse, enclosed government parking area and research planting area. Install and program a new intrusion alarm system with updated access keypads.

The intent of this project is for the contractor to replace the existing failing system with a new system that covers the same areas that are currently covered by the existing system.

2.0 Background

Olympia Lab has had repeated false alarms issues, and the alarm access keypads do not function properly. Olympia Lab received faulty alarms multiple times FY 2024, taking away valuable time and resources from the Thurston County Fire and police department. Thurston County PD served Olympia Lab with a violation notice and advised on the facility to get the system fixed and that they will no longer respond to alarms.

Contractor Requirements

3.0 Technical Requirements / Tasks

The new intrusion detection system shall have the following characteristics:

That provide perimeter detect

• Monitor 19 Doors, o 10 on the main building o 3 on the maintenance building o 1 on pump house o 5 on warehouse

• Install new glass brake sensors

• Remove and do not replace in room motion detection sensors

• Existing low voltage wire may be reused if found to be in sound condition

• Locate the Main Alarm panel in the main mechanical room

• Install (6) new arm/disarm keypad panels at the current locations

• Connect the new system to the existing off-site monitoring service

• Replace existing alarm speakers with new speakers

• Design the new intrusion alarm system to use the existing beam sensors in secured vehicle parking area.

4.0 Government Furnished

None

5.0 Deliverables / Schedule

As built drawings showing location of devices and wiring.

6.0 Travel

None

7.0 Contractor’s Key Personnel

The Contractor must be registered/licensed with an Intrusion Detection installer with municipality and ensure all personal are recognized professionals or supervised by recognized professional in commercial installation of that system.

8.0 Security Requirements

N/A

9.0 Data Rights

10.0 Section 508 – Electronic and Information Technology Standards