Attachment 01 - Statement of Work.pdf

PDF 265 KB Posted

Attached to
Communication Lines Installation, Tyndall AFB, FL Federal contract opportunity
Solicitation number
FA481922R0026
Issued by
Department of the Air Force Air Combat Command

View the file

Other files for this federal contract opportunity

Other files attached to Communication Lines Installation, Tyndall AFB, FL, newest first.
File Type Posted
Solicitation Amendment - FA481922R00260001.pdf PDF
Attachment 15 R0026 Q and A.xlsx XLSX spreadsheet
Solicitation - FA481922R0026.pdf PDF
Attachment 06 - Wage Determination 20220005.pdf PDF
Attachment 11 - AF Form 3065.pdf PDF
Attachment 07 - AF Form 3064.pdf PDF
Attachment 09 - AF Form 3000.pdf PDF
Attachment 12 - Base Access Request EAL.xlsx XLSX spreadsheet
Attachment 03 - Appendix B.pdf PDF
Attachment 05 - Section L M.pdf PDF
Attachment 10 - Sample RFI.PDF PDF
Attachment 13 - Proof of Financial Responsibility.pdf PDF
Attachment 14 Division Cost Estimate Worksheet.xlsx XLSX spreadsheet
Attachment 02 - Appendix A.pdf PDF
Attachment 04 - Other Contract Requirements.pdf PDF
Attachment 08 - AF Form 66.xls XLS spreadsheet
Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA4819-20-R-XXXX

Appendix - A 26 May 2022

APPENDIX - A

DESCRIPTION OF WORK

For

REQUEST FOR PROPOSAL

Construct (Install) Comm Lines in 1200 Area

TYNDALL AFB FLORIDA

FOR PROJECT XLWU 22-4011

Contents

1.0 SCOPE

1.1 PURPOSE

1.2 GENERAL:

1.3 OTHER REQUIREMENTS:

1.3.1 Inspections

2.0 SUMMARY OF WORK

2.1 TASK 1.0 ...................................................................................................... ERROR! BOOKMARK NOT DEFINED.

2.2 TASK 2.0 ...................................................................................................... ERROR! BOOKMARK NOT DEFINED.

3.0 POINTS OF CONTACT (POCS)

3.1 POCS WILL BE COORDINATED THROUGH THE CO

3.2 CONTRACTING OFFICER AUTHORITY:

3.3 PROJECT MANAGER (PM):

3.4 USER CONTACT ........................................................................................... ERROR! BOOKMARK NOT DEFINED.

3.5 BUILDING CONTACT ................................................................................... ERROR! BOOKMARK NOT DEFINED.

26 May 2022

1.0 SCOPE

1.1 Purpose

A. The purpose of the Tyndall Air Force Base (TAFB) project XLWU 22-4011, Construct (Install) Comm Lines 1200 Area], is to provide base fiber optic communication services to the new Wildland Fire and Natural Resources buildings.

B. The delivery method is Design-Build (D-B). The Contractor shall be responsible for providing all labor, equipment, tools, materials, and services necessary to complete the project within the allotted timeframe.

C. This project has an estimated period of performance from Notification to Proceed (NTP) through completion and turnover of the facility back to the Government for mission operations of 180 calendar days.

D. Implementation of work will not start until an approved 100% Design has been issued. Ordering of long lead items may be coordinated with CO.

1.2 General:

A. Field Changes: The Contractor and the Government may agree to perform a no cost field change. Field changes are made when the change appears to be mutually beneficial to all parties and would not require changing the negotiated items. All field changes must be approved by the CO prior to execution. Only the CO may authorize field changes or deviations from the SOW.

B. Ancillary Task: The tasks in this scope of work do not describe all the ancillary tasks required to complete the task. The contractor is required to complete all ancillary tasks to meet codes and standards that results in a complete and useable facility. Any task omissions by the contractor in their proposal will be the responsibility of the contractor.

C. Quantities and Measurements: All quantities, square footage, linear footage, etc. are estimate to assist contractor in determining scale and scope of this project. Contractor is responsible to verifying and calculating his own quantities for his proposal and estimates do not relieve contractor from providing required quantities and cost to successfully complete project. For example measurements for drywall and painting is a square footage for the room versus the actual wall square footage. Contractor shall provide all calculations, and quantities for government review/approval.

1.3 Other Requirements:

A. Refer to the SOW for other requirements.

1.3.1 Inspections

The Contractor shall advise the Government 48 hours before performing any test operation.

2.0 Summary of Work

This project will provide fiber optic cable and conduit (where required) from the ITN at Building 1210 to points as defined in the following breakdown. This work will provide fiber optic cable where it is currently missing and will provide upgrades where required to meet the base future needs. We will also provide the telecommunication equipment within the new Wildland Fire/Natural Resources compound.

2.1 Breakdown of Tasking involving outside plant conduit and fiber:

2.1.1 Install two new telecommunications hand holes:

NHH1 - West side of Dejarnette Road NHH2 – NW quadrant of intersection of Dejarnette Road and Bambi Trail

2.1.2 Install new 4” diameter conduits:

• Two (2), between HH574-A to NHH1

• One (1), between NHH1 to NHH2

• One (1), between NHH2 to B1259M Telecommunications Room

2.1.3 Bring 144 strand fiber optic line from the ITN within AFNORTH Bldg. to

NHH1. Leave a 50-foot coil at NHH1.

2.1.4 Splice 36 strand of fiber optic onto the 144 strand at NHH1. Bring this 36 strand into the Telecommunications Room of B1259.

Note that there will be 108 strand of fiber optic remaining in NHH1 for future use.

2.2 Provide and install the necessary equipment for full telecommunications requirements within the new Wildland Fire Facility (B1259M). This equipment includes:

• Cabinet

• Patch panel

• Cable management

• Switch

• UPS

Note: Grounding lugs are already in place.

2.3 Install a new 2” diameter conduit from the telecommunications room in B1259 to the multi-purpose room in B1260M (Natural Resources). Run a CATVI telecommunications line within this conduit and terminate it in a wall mount location along the west wall.

2.1.8 Test all new fiber and provide test results to CO.

2.1.9 All telecommunications work shall be done in accordance with UFC 3-580-01 and the Tyndall IFS

3.0 POINTS OF CONTACT (POCs)

3.1 POCs will be coordinated through the CO.

3.2 Contracting Officer Authority:

A. CO, the term used herein, does not include any representative not acting within the scope of his/her authority. Notwithstanding any of the provisions of this contract, the CO shall be the only individual authorized to in any way amend or modify the terms of this contract.

3.3 Project Manager (PM):

Stevan F Jackson 325CES/CENM 850-781-9449

END OF DOCUMENT

1.1 Purpose 3
1.2 General: 3
1.3 Other Requirements: 4
2.1 Task 1.0 Error! Bookmark not defined.
2.2 Task 2.0 Error! Bookmark not defined.
3.1 POCs will be coordinated through the CO. 5
3.2 Contracting Officer Authority: 5
3.3 Project Manager (PM): 5
3.4 User Contact Error! Bookmark not defined.
3.5 Building Contact Error! Bookmark not defined.
1.0 SCOPE
1.1 Purpose
1.2 General:
1.3 Other Requirements:
1.3.1 Inspections
2.0 Summary of Work
3.0 POINTS OF CONTACT (POCs)
3.1 POCs will be coordinated through the CO.
3.2 Contracting Officer Authority:
3.3 Project Manager (PM):