Attachment 01- Specifications-Columbus Construction.pdf

PDF 5 MB Posted

Attached to
Y1PZ--Reconfigure Perimeter Road | Columbus, OH Minor | Construction | 757-204
Solicitation number
36C77625B0005_1
Issued by

About this file

This document is a comprehensive Project Manual for the Columbus VA Healthcare System's Perimeter Road Reconfiguration project (Project #757-204), located at 420 North James Road in Columbus, Ohio. The solicitation is a 100% Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside construction project with a project value between $10-20 million. The project scope includes comprehensive site preparation, demolition, road and utility reconfiguration, building expansion and renovation, and associated infrastructure improvements.

The project manual contains detailed specifications across multiple divisions, including architectural, structural, mechanical, electrical, and site work requirements. Key components include concrete work, masonry, metal fabrications, thermal insulation, exterior closure, and various site improvements. The documentation provides extensive technical details such as material specifications, installation requirements, quality control procedures, and commissioning guidelines. The project involves phased construction with multiple bid alternates that allow the VA to adjust the project scope, such as options to modify sidewalk construction, parking lot striping, site lighting, and interior building improvements.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RECONFIGURE PERIMETER ROAD

Project # 757-204

For the Columbus VA - Chalmers P. Wylie Outpatient Clinic

420 North James Road Columbus, OH 43219

PROJECT MANUAL

BID DOCUMENTS

August 13, 2021

GUIDON DESIGN INC.

PROJECT CONTACTS:

COR / OWNER: Columbus VA Chalmers P. Wylie Outpatient Clinic Attn: Jennifer Miller

420 North James Road Columbus, OH 43219 Phone: 614-388-7332

Email: Jennifer.Miller197e76@va.gov

ARCHITECT, CIVIL GUIDON DESIGN INC.

AND STRUCTURAL Attn: Stacey Paul ENGINEER: 1221 N Pennsylvania St. Suite 200 Indianapolis, Indiana 46202 Phone: (317) 800-6388 x 104 Email: spaul@guidondesign.com

ISSUE DATE: August 13, 2021

Department of Veterans Affairs VA Project No. 757-204 Columbus VA Healthcare System Reconfigure Perimeter Road Columbus, OH Bid Documents: 08/13/21

08-01-20

00 01 10-1

DEPARTMENT OF VETERANS AFFAIRS

VHA MASTER SPECIFICATIONS

TABLE OF CONTENTS

Section 00 01 10

SECTION NO. DIVISION AND SECTION TITLES DATE

DIVISION 00 - SPECIAL SECTIONS

00 01 15 List of Drawing Sheets 05-20

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 03-20 01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 03-20 01 33 23 Shop Drawings, Product Data, and Samples 05-17 01 35 26 Safety Requirements 07-20 01 42 19 Reference Standards 09-19 01 45 00 Quality Control 03-19 01 45 29 Testing Laboratory Services 11-18 01 57 19 Temporary Environmental Controls 01-11 01 58 16 Temporary Interior Signage 07-15 01 74 19 Construction Waste Management 09-13 01 91 00 General Commissioning Requirements 10-15

DIVISION 02 – EXISTING CONDITIONS

02 41 00 Demolition 08-17

DIVISION 03 – CONCRETE

03 30 00 Cast-in-Place Concrete 07-19

DIVISION 04 – MASONRY

04 05 13 Masonry Mortaring 10-17 04 05 16 Masonry Grouting 02-16 04 20 00 Unit Masonry 08-17

DIVISION 05 – METALS

05 12 00 Structural Steel Framing 11-18 05 31 00 Steel Decking 02-16 05 50 00 Metal Fabrications 08-18

DIVISION 06 – WOOD, PLASTICS AND COMPOSITES

06 10 00 Rough Carpentry 10-17 06 20 00 Finish Carpentry 08-16

Columbus, OH Bid Documents: 08/13/21

08-01-20

00 01 10-2

SECTION NO. DIVISION AND SECTION TITLES DATE

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 08 00 Facility Exterior Closure Commissioning 11-16 07 11 13 Bituminous Dampproofing 02-16 07 21 13 Thermal Insulation 10-17 07 22 00 Roof and Deck Insulation 02-16 07 54 23 Thermoplastic Polyolefin (TPO) Roofing 08-16 07 84 00 Firestopping 02-16 07 92 00 Joint Sealants 10-17 07 95 13 Expansion Joint Cover Assemblies 02-16

DIVISION 08 - OPENINGS

08 11 13 Hollow Metal Doors and Frames 08-16 08 14 00 Interior Wood Doors 02-16 08 51 13 Aluminum Windows 04-20 08 71 00 Door Hardware 04-20 08 71 13.11 Low Energy Power Assist Door Operators 08-16 08 80 00 Glazing 10-15 08 90 00 Louvers and Vents 05-15

DIVISION 09 – FINISHES

09 05 16 Subsurface Preparation for Floor Finishes 02-15 09 06 00 Schedule for Finishes 04-15 09 22 16 Non-Structural Metal Framing 06-18 09 29 00 Gypsum Board 04-20 09 51 00 Acoustical Ceilings 12-18 09 68 00 Carpeting 10-15 09 91 00 Painting 01-16

DIVISION 10 – SPECIALTIES

10 26 00 Wall and Door Protection 10-15 10 44 13 Fire Extinguisher Cabinets 08-18

DIVISION 12 – FURNISHINGS

12 24 00 Window Shades 08-17

DIVISION 21- FIRE SUPPRESSION

21 08 00 Commissioning of Fire Suppression System 11-16 21 13 13 Wet-Pipe Sprinkler Systems 06-15

DIVISION 22 – PLUMBING

22 05 11 Common Work Results for Plumbing 07-16 22 05 19 Meters and Gages for Plumbing Piping 09-15 22 05 23 General-Duty Valves for Plumbing Piping 09-15

Columbus, OH Bid Documents: 08/13/21

08-01-20

00 01 10-3

SECTION NO. DIVISION AND SECTION TITLES DATE

22 07 11 Plumbing Insulation 09-19 22 08 00 Commissioning of Plumbing Systems 11-16 22 11 00 Facility Water Distribution 11-19 22 13 00 Facility Sanitary and Vent Piping 09-15 22 40 00 Plumbing Fixtures 09-15

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

23 05 11 Common Work Results for HVAC 02-20 23 05 12 General Motor Requirements for HVAC and Steam

Generation Equipment 02-20

23 05 41 Noise and Vibration Control for HVAC Piping and Equipment

02-20

23 05 93 Testing, Adjusting, and Balancing for HVAC 02-20 23 07 11 HVAC and Boiler Plant Insulation 02-20 23 08 00 Commissioning of HVAC Systems 02-20 23 09 23 Direct-Digital Control System for HVAC 09-11 23 31 00 HVAC Ducts and Casings 02-20 23 34 00 HVAC Fans 02-20 23 36 00 Air Terminal Units 02-20 23 37 00 Air Outlets and Inlets 02-20 23 74 13 Packaged, Outdoor, Central-Station Air-Handling Units 03-20 23 81 00 Decentralized Unitary HVAC Equipment 03-20 23 82 00 Convection Heating and Cooling Units 03-20

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 01-16 26 05 13 Medium-Voltage Cables 01-17 26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17 26 05 26 Grounding and Bonding for Electrical Systems 01-17 26 05 33 Raceway and Boxes for Electrical Systems 01-18 26 05 41 Underground Electrical Construction 01-17 26 05 73 Overcurrent Protective Device Coordination Study 01-18 26 08 00 Commissioning of Electrical Systems 11-16 26 09 23 Lighting Controls 01-18 26 13 13 Medium-Voltage Circuit Breaker Switchgear 01-17 26 22 00 Low-Voltage Transformers 01-18 26 24 16 Panelboards 01-18 26 27 26 Wiring Devices 01-18 26 29 21 Enclosed Switches and Circuit Breakers 01-17 26 41 00 Facility Lightning Protection 01-17 26 43 13 Surge Protective Devices 01-17 26 51 00 Interior Lighting 01-18 26 56 00 Exterior Lighting 01-18

DIVISION 27 – COMMUNICATIONS

27 05 11 Requirements for Communications Installations 09-19

Columbus, OH Bid Documents: 08/13/21

08-01-20

00 01 10-4

SECTION NO. DIVISION AND SECTION TITLES DATE

27 05 33 Raceways and Boxes for Communications Systems 10-18 27 08 00 Commissioning of Communications Systems 11-16 27 10 00 Control, Communication and Signal Wiring 06-15 27 15 00 Communications Structured Cabling 01-16 27 51 16 Public Address and Mass Notification Systems 10-18

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 31 00 Fire Detection and Alarm 10-11

DIVISION 31 – EARTHWORK

31 20 00 Earthwork 07-16

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 05 23 Cement and Concrete for Exterior Improvements 08-16 32 12 16 Asphalt Paving 09-15 32 14 16 Brick Unit Paving 08-16 32 17 23 Pavement Markings 08-16 32 31 40 High Security Fences and Gates 08-16 32 90 00 Planting 08-16

DIVISION 33 – UTILITIES

33 10 00 Water Utilities 03-17 33 30 00 Sanitary Sewer Utilities 06-13 33 40 00 Storm Sewer Utilities 12-17

DIVISION 34 – TRANSPORTATION

34 71 13 Passive Vehicle Barriers 04-18 34 75 13.13 Active Vehicle Barriers 08-16

Columbus, OH Bid Documents: 08/13/21

05-01-20

00 01 15 - 1

SECTION 00 01 15

LIST OF DRAWING SHEETS

The drawings listed below accompanying this specification form a part of the contract.

GENERAL

GI001 COVER SHEET

GI002 BID ALTERNATE PLAN

GI003 PHASING PLAN (CAMPUS)

GI101 PHASING PLAN - PART I

GI102 PHASING PLAN - PART II

GI004 INFECTION CONTROL/PHASING PLAN - PART III

GI104 PHASING PLAN - PART IV

GI501 MAINTENANCE OF TRAFFIC DETAILS

CIVIL

CI001 GENERAL CIVIL NOTES

CI002 CIVIL LEGEND AND KEYNOTES

CI003 CIVIL AND LANDSCAPE KEY MAP

CD101 DEMOLITION PLAN - PART I

CD102A DEMOLITION PLAN - PART II

CD102B DEMOLITION PLAN - PART II

CD102C DEMOLITION PLAN - PART II

CD103 DEMOLITION PLAN - PART III

CD104A DEMOLITION PLAN - PART IV

CD104B DEMOLITION PLAN - PART IV

CS101 SITE PLAN - PART I

CS102A SITE PLAN - PART II

CS102B SITE PLAN - PART II

CS102C SITE PLAN - PART II

CS103 SITE PLAN - PART III

CS104A SITE PLAN - PART IV

CS104B SITE PLAN - PART IV

CS104C SITE PLAN - PART IV

CS201 JOINTING PLAN

CS501 SITE DETAILS

CS502 SITE DETAILS

CS503 SITE DETAILS

CS504 SITE DETAILS

CS505 SITE DETAILS

CS506 SITE DETAILS

CS507 SITE DETAILS

CG101 GRADING PLAN - PART I

CG103 GRADING PLAN - PART III

CG104A GRADING PLAN - PART IV

CG104B GRADING PLAN - PART IV

CG104C GRADING PLAN - PART IV

CG201 GRADING PLAN - ROAD PROFILE

CU101 UTILITY PLAN - PART I

CU102A UTILITY PLAN - PART II

CU102B UTILITY PLAN - PART II

CU102C UTILITY PLAN - PART II

CU103 UTILITY PLAN - PART III

CU104A UTILITY PLAN - PART IV

Columbus, OH Bid Documents: 08/13/21

05-01-20

00 01 15 - 2

CU104B UTILITY PLAN - PART IV

CU501 UTILITY DETAILS

CU502 UTILITY DETAILS

CU503 UTILITY DETAILS

CJ101 EROSION CONTROL PLAN - PART I

CJ102A EROSION CONTROL PLAN - PART II

CJ102B EROSION CONTROL PLAN - PART II

CJ102C EROSION CONTROL PLAN - PART II

CJ103 EROSION CONTROL PLAN - PART III

CJ104A EROSION CONTROL PLAN - PART IV

CJ104B EROSION CONTROL PLAN - PART IV

CJ104C EROSION CONTROL PLAN - PART IV

CJ501 EROSION CONTROL DETAILS

LP001 LANDSCAPE GENERAL NOTES AND LEGEND

LP101 LANDSCAPE PLAN

STRUCTURAL

SI001 STRUCTURAL ABBREVIATIONS, SYMBOLS AND LOAD MAP - PART III

SI002 STRUCTURAL GENERAL NOTES - PART III

SB103 FOUNDATION PLAN - PART III

SB501 FOUNDATION SECTIONS AND DETAILS - PART III

SF103A ROOF FRAMING PLAN - PART III

SF103B PARAPET SUPPORT FRAMING PLAN - PART III

SF203 BRACE FRAME ELEVATIONS AND DETAILS - PART III

SF501 FRAMING SECTIONS AND DETAILS - PART III

ARCHITECTURAL

AE001 ARCHITECTURAL SYMBOLS AND ABBREVIATIONS - PART III

AE002 WALL TYPES - PART III

AD103 ARCHITECTURAL DEMOLITION PLAN - PART III

AD104 DEMOLITION ROOF PLAN - PART III

AE101 LIFE SAFETY PLAN - PART III

AE103A ARCHITECTURAL FLOOR PLAN - PART III

AE103B ROOF PLAN - PART III

AE113 REFLECTED CEILING PLAN - PART III

AE203 BUILDING ELEVATIONS - PART III

AE303 BUILDING SECTIONS - PART III

AE503 WALL SECTION AND BUILDING DETAILS - PART III

AE603 OPENINGS SCHEDULES AND DETAILS - PART III

AI103 FINISH TREATMENT PLAN - PART III

QHE103 FURNITURE PLAN - PART III

ELECTRICAL

EE000 ELECTRICAL LEGENDS

EE010 EXISTING PLANT& NEW MEDIUM VOLTAGE SINGLE LINE DIAGRAM

EE020 PARTIAL ELECTRICAL SINGLE LINE - GARAGE/END. BLDG

ED101 ELECTRICAL DEMOLITION SITE PLAN - PART I

ED103 ELECTRICAL DEMOLITION PLAN - PART III

EL103 ELECTRICAL LIGHTING PLAN - PART III

EP103 ELECTRICAL POWER PLAN - PART III

ES101 ELECTRICAL SITE PLAN - PART I

ES102A ELECTRICAL SITE PLAN VA - PART II

ES102B ELECTRICAL SITE PLAN DSCC - PART II

ES104A ELECTRICAL SITE PLAN - PART IV

ES104B LIGHTING SITE PLAN - PART IV

EE500 ELECTRICAL DETAILS

Columbus, OH Bid Documents: 08/13/21

05-01-20

00 01 15 - 3

EE501 POLE DETAILS

EE502 POLE DETAILS

FIRE PROTECTION

FP003 FIRE PROTECTION LEGENDS

FD103 FIRE PROTECTION DEMOLITION PLAN - PART III

FP101 FIRE PROTECTION PLAN - PART III

MECHANICAL

HH003 HVAC LEGENDS

HD103 HVAC DEMOLITION PLAN - PART III

HH103 HVAC PLAN - PART III

HH113 HVAC ROOF PLAN - PART III

HH503 HVAC DETAILS

HH603 HVAC SCHEDULES

HH703A HVAC CONTROLS - NETWORK

HH703B HVAC CONTROLS - RTU-1

HH703C HVAC CONTROLS - RTU-2

PLUMBING

PP003 PLUMBING LEGENDS

PD103 PLUMBING DEMOLITION PLAN - PART III

PP103 PLUMBING PLAN - PART III

PP603 PLUMBING SCHEDULES & DETAILS

PP903 WASTE & VENT RISER DIAGRAMS

TECHNOLOGY

TT003 TECHNOLOGY LEGENDS

TT013 TECHNOLOGY FACEPLATE DETAILS

TT103 TECHNOLOGY PLAN - PART III

TT501 TECHNOLOGY DETAILS

- - - END - - -

Columbus, OH Bid Documents: 08/13/21

12-01-18

01 00 00 -1

SECTION 01 00 00

GENERAL REQUIREMENTS

TABLE OF CONTENTS

1.1 Safety Requirements

1.2 GENERAL INTENTION

1.3 STATEMENT OF BID ITEM(S)

1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

1.5 CONSTRUCTION SECURITY REQUIREMENTS

1.6 OPERATIONS AND STORAGE AREAS

1.7 ALTERATIONS

1.8 DISPOSAL AND RETENTION

1.9 RESTORATION

1.10 PHYSICAL DATA

1.11 PROFESSIONAL SURVEYING SERVICES

1.12 LAYOUT OF WORK

1.13 AS-BUILT DRAWINGS

1.14 WARRANTY MANAGEMENT

1.15 USE OF ROADWAYS

1.16 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT

1.17 TEMPORARY TOILETS

1.18 AVAILABILITY AND USE OF UTILITY SERVICES

1.19 NEW TELEPHONE EQUIPMENT

1.20 TESTS

1.21 INSTRUCTIONS

1.22 GOVERNMENT-FURNISHED PROPERTY

1.23 RELOCATED EQUIPMENT or ITEMS

1.24 STORAGE SPACE FOR DEPARTMENT OF VETERANS AFFAIRS EQUIPMENT........ Error!

Bookmark not defined.

1.25 CONSTRUCTION SIGN

1.26 SAFETY SIGN

1.27 PHOTOGRAPHIC DOCUMENTATION

Columbus, OH Bid Documents: 08/13/21

12-01-18

01 00 00 -2

1.28 FINAL ELEVATION Digital Images

1.29 HISTORIC PRESERVATION

Columbus, OH Bid Documents: 08/13/21

12-01-18

01 00 00 -3

SECTION 01 00 00

GENERAL REQUIREMENTS

1.1 SAFETY REQUIREMENTS

A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.

1.2 GENERAL INTENTION

A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for the reconfiguration of the perimeter roadway, extension of a medium voltage electrical system, expansion and renovation of the

Engineering Building, closure and renovation of Washington

Street, additional paving and striping as required by drawings and specifications.

B. Visits to the site by Bidders may be made only by appointment with the Medical Center Engineering Officer.

C. Offices of Guidon Design, Inc., as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.

D. Before placement and installation of work subject to tests by testing laboratory retained by the contractor, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three workdays unless otherwise designated by the COR.

E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.

Columbus, OH Bid Documents: 08/13/21

12-01-18

01 00 00 -4

1.3 STATEMENT OF BID ITEM(S)

A. ITEM I, GENERAL CONSTRUCTION: Work includes general construction of Parts I, II, III, and IV with regards to alterations, roads, walks, grading, drainage, utilities, fences, gates, building expansion and renovation and all necessary removal of existing structures and construction and certain other items.

BID ALTERNATE A: WEST CAMPUS SIDEWALK

BID ALTERNATE A CONSISTS OF ALL WORK IN THE BASE BID EXCEPT DO NOT

CONSTRUCT THE WEST SIDEWALK AS SHOWN ON SHEETS: CS104C, CG104C,

CJ104C, AND CS501 (CONCRETE SIDEWALK DETAIL) SEE SHEETS CS104C,

CG104C, CJ104C AND CS501(CONCRETE SIDEWALK DETAIL).

BID ALTERNATE B: NORTH PARKING LOT STRIPING

BID ALTERNATE B CONSISTS OF ALL WORK IN THE BASE BID, BID ALTERNATE A,

AND DO NOT REMOVE AND REPLACE PAVEMENT MARKINGS IN THE NORTH PARKING

LOT. SEE SHEETS CD104A AND CS104A.

BID ALTERNATE C: SITE LIGHTING

BID ALTERNATE C CONSISTS OF ALL WORK IN THE BASE BID, BID ALTERNATE B,

AND DO NOT CONSTRUCT SITE LIGHTING IMPROVEMENTS AS SHOWN ON SHEET

ES104B. SEE SHEET ES104B

BID ALTERNATE D: TRAILER UTILITIES

BID ALTERNATE D CONSISTS OF ALL WORK IN THE BASE BID, BID ALTERNATE C

AND DO NOT CONSTRUCT ELECTRICAL POWER FOR MOBILE TRAILERS. SEE SHEETS

EE020, ES104A.

BID ALTERNATE E: ENGINEERING BUILDING INTERIOR IMPROVEMENTS

BID ALTERNATE E CONSISTS OF ALL WORK IN THE BASE BID, BID ALTERNATE D

AND DO NOT PERFORM WORK ON ENGINEERING BUILDING INTERIOR. SEE SHEETS

SI002, SB103, SF103, SB501, AE001, AE002, AE003M AE101, AD103, AE103A,

AE103B, AE113, AE203, AE303, AE503, AE603, AI103, EL103, EP103, FP103,

FP103A, FP103B, HH003, HD103, HH103, HH113, HH503, HH603, PP03, PD103,

PP103, PP603, PP903, TT003, TT013, TT103.

BID ALTERNATE F: ENGINEERING BUILDING ADDITION

BID ALTERNATE F CONSISTS OF ALL WORK IN THE BASE BID, BID ALTERNATE E

AND DO NOT CONSTRUCT ENGINEERING BUILDING ADDITION. SEE SHEETS CD103.

CS103, CG103, CU103, CJ103 SI001, SI002, SB103, SF103, SB501, AE001,

AE002, AE003M AE101, AD103, AE103A, AE103B, AE113, AE203, AE303,

AE503, AE603, AI103, EL103, EP103, FP103, FP103A, FP103B, HH003,

HD103, HH103, HH113, HH503, HH603, PP03, PD103, PP103, PP603, PP903,

TT003, TT013, TT103, EE020.

Columbus, OH Bid Documents: 08/13/21

12-01-18

01 00 00 -5

1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at

Contractor's expense.

1.5 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.

2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.

B. Security Procedures:

1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.

2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.

3. No photography of VA premises is allowed without written permission of the Contracting Officer.

4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the

Contracting Officer.

C. Key Control:

1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR) for the purpose of security inspections of every area of

Columbus, OH Bid Documents: 08/13/21

12-01-18

01 00 00 -6 project including toolboxes and parked machines and take any emergency action.

2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation. See

Section 08 71 00, DOOR HARDWARE and coordinate.

D. Document Control:

1. Before starting any work, the General Contractor/Sub

Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”.

2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.

3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or

“Sensitive Unclassified”. Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting

Officer upon request.

4. These security documents shall not be removed or transmitted from the project site without the written approval of

Contracting Officer.

5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the

VA.

6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.

7. All electronic information shall be stored in specified location following VA standards and procedures using an

Engineering Document Management Software (EDMS).

Columbus, OH Bid Documents: 08/13/21

12-01-18

01 00 00 -7

a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.

b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.

E. Motor Vehicle Restrictions

1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted

24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.

2. A limited number of (5) permits shall be issued for General

Contractor and its employees for parking in designated areas only.

1.6 OPERATIONS AND STORAGE AREAS

A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the

Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the

Contractor at its expense upon completion of the work. With the written consent of the Contracting Officer, the buildings and utilities may be abandoned and need not be removed.

C. The Contractor shall, under regulations prescribed by the

Contracting Officer, use only established roadways, or use

Columbus, OH Bid Documents: 08/13/21

12-01-18

01 00 00 -8 temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the

Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.

(FAR 52.236-10)

D. Working space and space available for storing materials shall be as shown on the drawings.

E. Workers are subject to rules of the Medical Center applicable to their conduct.

F. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.

G. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.

1. Do not store materials and equipment in other than assigned areas.

2. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.

Columbus, OH Bid Documents: 08/13/21

12-01-18

01 00 00 -9

H. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.

All such actions shall be coordinated with the COR or Utility

Company involved:

1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.

I. Phasing:

1. The Medical Center must maintain its operation 24 hours a day

7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:

2. To ensure such executions, Contractor shall furnish the COR with a schedule of approximate phasing dates on which the

Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing dates to ensure accomplishment of this work in successive phases mutually agreeable to Medical Center Director, COR and Contractor, as follows:

Columbus, OH Bid Documents: 08/13/21

12-01-18

01 00 00 -10

Columbus, OH Bid Documents: 08/13/21

01 00 00 -11

Columbus, OH Bid Documents: 08/13/21

01 00 00 -12

Columbus, OH Bid Documents: 08/13/21

12-01-18

01 00 00 -13

Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical

Centers operations will not be hindered. Contractor shall permit access to Department of Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc to facilitate patient and staff access.

Coordinate alteration work in areas occupied by Department of

Veterans Affairs so that Medical Center operations will continue during the construction period.

J. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, (seven feet) minimum height, around the construction area indicated on the drawings. Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and

Columbus, OH Bid Documents: 08/13/21

12-01-18

01 00 00 -14 bottom rails with tie wires spaced at maximum (15 inches). Bottom of fences shall extend to (one inch) above grade. Remove the fence when directed by COR.

K. When a building and/or construction site is turned over to

Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:

1. Contractor shall maintain a minimum temperature of (40 degrees

F) at all times, except as otherwise specified.

2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company

(Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from Contractor's employee or watchman.

L. Utilities Services: Maintain existing utility services for

Medical Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.

1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR.

Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the

Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, Columbus, OH Bid Documents: 08/13/21

12-01-18

01 00 00 -15

REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, 27 05 11

REQUIREMENTS FOR COMMUNICATIONS INSTALLATIONS and 28 05 00, COMMON WORK RESULTS FOR ELECTRONIC SAFETY AND SECURITY for additional requirements.

2. Contractor shall submit a request to interrupt any such services to COR, in writing, 7 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.

3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical

Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.

4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.

5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.

6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.

M. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.

Columbus, OH Bid Documents: 08/13/21

12-01-18

01 00 00 -16

N. To minimize interference of construction activities with flow of

Medical Center traffic, comply with the following:

1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.

Wherever excavation for new utility lines cross existing roads, at least one lane must be open to traffic at all times with approval.

2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.

O. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF

ROADWAYS.

1.7 ALTERATIONS

A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the Contracting

Officer. This report shall list by rooms and spaces:

1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of building.

2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.

3. Shall note any discrepancies between drawings and existing conditions at site.

4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.

Columbus, OH Bid Documents: 08/13/21

12-01-18

01 00 00 -17

B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by

Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled

"DIFFERING SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR

52.243-4).

C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:

1. Re-survey report shall also list any damage caused by

Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of Contractor to restore damage caused by Contractor's workers in executing work of this contract.

D. Protection: Provide the following protective measures:

1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.

2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.

E. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately

Columbus, OH Bid Documents: 08/13/21

12-01-18

01 00 00 -18 protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.

1.8 DISPOSAL AND RETENTION

A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:

1. Reserved items which are to remain property of the Government are noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by

COR.

2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.

3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.

4. PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,

UTILITIES, AND IMPROVEMENTS

a. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so and shall avoid damaging vegetation that will remain in place.

If any limbs or branches of trees are broken during

Columbus, OH Bid Documents: 08/13/21

12-01-18

01 00 00 -19 contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting

Officer.

b. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The

Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

(FAR 52.236-9)

c. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL

CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and "Operations and Storage

Areas" for additional instructions concerning repair of damage to structures and site improvements.

d. Refer to FAR clause 52.236-7, "Permits and

Responsibilities," which is included in General Conditions.

A National Pollutant Discharge Elimination System (NPDES) permit is required for this project. The Contractor is considered an "operator" under the permit and has extensive responsibility for compliance with permit requirements. VA will make the permit application available at the

(appropriate medical center) office. The apparent low bidder, contractor and affected subcontractors shall

Columbus, OH Bid Documents: 08/13/21

12-01-18

01 00 00 -20 furnish all information and certifications that are required to comply with the permit process and permit requirements. Many of the permit requirements will be satisfied by completing construction as shown and specified. Some requirements involve the Contractor's method of operations and operations planning and the

Contractor is responsible for employing best management practices. The affected activities often include, but are not limited to the following:

1) Designating areas for equipment maintenance and repair;

2) Providing waste receptacles at convenient locations and provide regular collection of wastes;

3) Locating equipment wash down areas on site, and provide appropriate control of wash-waters;

4) Providing protected storage areas for chemicals, paints, solvents, fertilizers, and other potentially toxic materials; and

5) Providing adequately maintained sanitary facilities.

1.9 RESTORATION

A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.

B. Upon completion of contract, deliver work complete and undamaged.

Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be

Columbus, OH Bid Documents: 08/13/21

12-01-18

01 00 00 -21 patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.

C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems

(including telephone) which are not scheduled for discontinuance or abandonment.

D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES" (FAR 52.243-4) and "DIFFERING SITE CONDITIONS"

(FAR 52.236-2).

1.10 PHYSICAL DATA

A. Data and information furnished or referred to below is for the

Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.

1. The indications of physical conditions on the drawings and in the specifications are the result of site investigations by the surveyor and A/E design team.

(FAR 52.236-4)

2. Subsurface conditions have been developed by core borings and test pits. Logs of subsurface exploration are shown diagrammatically in the Geotechnical Report.

3. A copy of the soil report will be made available for inspection by bidders upon request to the Engineering Officer at the VA Medical Center and shall be considered part of the contract documents.

4. Government does not guarantee that other materials will not be encountered, nor that proportions, conditions or character of several materials will not vary from those indicated by

Columbus, OH Bid Documents: 08/13/21

12-01-18

01 00 00 -22 explorations. Bidders are expected to examine site of work and logs of borings; and, after investigation, decide for themselves character of materials and make their bids accordingly. Upon proper application to Department of Veterans

Affairs, bidders will be permitted to make subsurface explorations of their own at site.

1.11 PROFESSIONAL SURVEYING SERVICES

A. A registered professional land surveyor or registered civil engineer whose services are retained and paid for by the

Contractor shall perform services specified herein and in other specification sections. The Contractor shall certify that the land surveyor or civil engineer is not one who is a regular employee of the Contractor, and that the land surveyor or civil engineer has no financial interest in this contract.

1.12 LAYOUT OF WORK

A. The Contractor shall lay out the work from Government established base lines and benchmarks, indicated on the drawings, and shall be responsible for all measurements in connection with the layout. The Contractor shall furnish, at Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work.

The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the

Contracting Officer. The Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the Contracting Officer until authorized to remove them. If such marks are destroyed by the Contractor or through

Contractor's negligence before their removal is authorized, the

Contracting Officer may replace them and deduct the expense of the replacement from any amounts due or to become due to the

Contractor.

(FAR 52.236-17)

Columbus, OH Bid Documents: 08/13/21

12-01-18

01 00 00 -23

B. Establish and plainly mark center lines for each building and corner of column lines and/or addition to each existing building, and such other lines and grades that are reasonably necessary to properly assure that location, orientation, and elevations established for each such structure and/or addition, roads, parking lots, are in accordance with lines and elevations shown on contract drawings.

C. Following completion of general mass excavation and before any other permanent work is performed, establish and plainly mark

(through use of appropriate batter boards or other means) sufficient additional survey control points or system of points as may be necessary to assure proper alignment, orientation, and grade of all major features of work. Survey shall include, but not be limited to, location of lines and grades of footings, exterior walls, center lines of columns in both directions, major utilities and elevations of floor slabs:

1. Such additional survey control points or system of points thus established shall be checked and certified by a registered land surveyor or registered civil engineer. Furnish such certification to the COR before any work (such as footings, floor slabs, columns, walls, utilities and other major controlling features) is placed.

D. During progress of work, Contractor shall have line grades and plumbness of all major form work checked and certified by a registered land surveyor or registered civil engineer as meeting requirements of contract drawings. Furnish such certification to the COR before any major items of concrete work are placed. In addition, Contractor shall also furnish to the COR certificates from a registered land surveyor or registered civil engineer that the following work is complete in every respect as required by contract drawings.

1. Lines of each building and/or addition.

Columbus, OH Bid Documents: 08/13/21

12-01-18

01 00 00 -24

2. Elevations of bottoms of footings and tops of floors of each building and/or addition.

3. Lines and elevations of sewers and of all outside distribution systems.

4. Lines of elevations of all swales and interment areas.

5. Lines and elevations of roads, streets and parking lots.

E. Whenever changes from contract drawings are made in line or grading requiring certificates, record such changes on a reproducible drawing bearing the registered land surveyor or registered civil engineer seal, and forward these drawings upon completion of work to COR.

F. The Contractor shall perform the surveying and layout work of this and other articles and specifications in accordance with the provisions of Article "Professional Surveying Services".

1.13 AS-BUILT DRAWINGS

A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.

B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR’s review, as often as requested.

C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.

D. Paragraphs A, B, & C shall also apply to all shop drawings.

1.14 WARRANTY MANAGEMENT

A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of

Construction in at least 30 days before the planned pre-warranty conference, submit two sets of the warranty management plan.

Columbus, OH Bid Documents: 08/13/21

12-01-18

01 00 00 -25

Include within the warranty management plan all required actions and documents to assure that the Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract. The term “status” as indicated below must include due date and whether item has been submitted or was approved.

Warranty information made available during the construction phase must be submitted to the Contracting Officer for approval prior to each monthly invoice for payment. Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period will begin on the date of the project acceptance and continue for the product warranty period. A joint 4 month and 9 month warranty inspection will be conducted, measured from time of acceptance, by the Contactor and the Contracting Officer. Include in the warranty management plan, but not limited to, the following:

1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the Contractor, subcontractors, manufacturers or suppliers involved.

2. Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest project location.

3. Listing and status of delivery of all Certificates of Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.

4. A list for each warranted equipment item, feature of construction or system indicating:

a. Name of item.

Columbus, OH Bid Documents: 08/13/21

12-01-18

01 00 00 -26

b. Model and serial numbers.

c. Location where installed.

d. Name and phone numbers of manufacturers and suppliers.

e. Name and phone numbers of manufacturers or suppliers.

f. Names, addresses and phone numbers of sources of spare parts.

5. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties must be indicated with separate warranty expiration dates.

6. Starting point and duration of warranty period.

7. Summary of maintenance procedures required to continue the warranty in force.

8. Cross-reference to specific pertinent Operation and

Maintenance manuals.

9. Organizations, names and phone numbers of persons to call for warranty service.

10. Typical response time and repair time expected for various warranted equipment.

11. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.

12. Procedure and status of tagging of all equipment covered by extended warranties.

13. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.

B. Performance Bond: The Performance Bond must remain effective throughout the construction period.

1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the

Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the

Columbus, OH Bid Documents: 08/13/21

12-01-18

01 00 00 -27

Government while performing the work, including, but not limited to administrative expenses.

2. In the event sufficient funds are not available to cover the construction warranty work performed by the Government at the contractor’s expenses, the Contracting Officer will have the right to recoup expenses from the bonding company.

3. Following oral or written notification of required construction warranty repair work, the Contractor shall respond in a timely…