Attachment 01- Market Research Barksdale Crisis Action Center.docx
DOCX document 48 KB Posted
- Solicitation number
- Not on record
About this file
This is a Sources Sought Notice and Request for Information (RFI) issued by the U.S. Army Corps of Engineers, Fort Worth District, for market research purposes regarding the Repair Building 5546 Crisis Action Center project at Barksdale Air Force Base, Louisiana. The project involves designing and constructing a 9,000 square foot facility conversion into an ICD-705 compliant secure space to serve as a Crisis Action Center supporting 30 personnel. The facility will include 30 workstations with five distinct networks, six standard offices, three executive offices, two video conference rooms (6-person and 25-person capacity), and interior buildout leveraging existing raised flooring and restrooms. All work must meet DoD standards for security, anti-terrorism, and cybersecurity, with facility alarms and HVAC modifications fully integrated with existing Barksdale AFB standards. The project is located within a cantonment area requiring background checks for all personnel, and involves renovation of an existing facility with potential asbestos and lead-based paint considerations.
The Government has established a Target Price Range (TPR) between $13,555,317.59 and $14,238,842.00 (the Construction Cost Limitation), within a total Programmed Amount of $15,000,000, covering all design services and construction but excluding Government-furnished equipment. The project will be executed under Other Transaction Authority (OTA) pursuant to 10 U.S.C. 2808a using one of three potential delivery methods: Progressive Design-Build (PDB), Design-Build to Budget (DBtB), or Construction Management at Risk (CM@Risk). The FAR does not apply; the OTA Agreement is the sole governing contract. The formal award of Phase 1 (Design and Preconstruction Services) is targeted for July 2027, with Phase 2 Construction following approximately 730 calendar days from Notice to Proceed. The Government currently holds a 100% design but is willing to revert to 35% design maturity to allow collaborative development. Capability statements and the completed Project Delivery & Acquisition Strategy Questionnaire must be submitted by September 30, 2026, at 6:00 P.M. CDT. All technical questions must be submitted via ProjNet (Project ID: 515212, Key: YP7GWK-Y7244Z) by September 27, 2026, at 10:00 A.M. CDT. A virtual Industry Day will be scheduled with details published subsequently on SAM.gov.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 01- Market Research Barksdale Crisis Action Center.pdf | ||
| Attach 01-Sources Sought- Repair Crisis Action Center.pdf | ||
| Attachment 02 -Industy Questionnare.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sources Sought & Other Transaction Authority (OTA) Market Research
DEPARTMENT OF THE ARMY
FORT WORTH DISTRICT, U.S. ARMY CORPS OF ENGINEERS
819 TAYLOR STREET
FORT WORTH, TEXAS 76102-0300
CESWF-CT 10 September 2026
MEMORANDUM FOR ALL PROSPECTIVE OFFERORS AND INTERESTED INDUSTRY PARTNERS
SUBJECT: Sources Sought (RFI) - Repair Building 5546 Crisis Action Center
1. DISCLAIMER. THIS IS A REQUEST FOR INFORMATION (RFI) / SOURCES SOUGHT NOTICE ONLY. This notice is issued solely for market research, information, and planning purposes. It does not constitute a Request for Proposals (RFP), a Request for Qualifications (RFQ), or a commitment by the Government to write, issue, or award an agreement or contract. The Government will not pay for any information or administrative costs incurred in response to this notice. All response costs will be borne solely by the interested party.
2. PURPOSE. The U.S. Army Corps of Engineers (USACE), Fort Worth District, is conducting active public market intelligence to gauge industry interest, capacity, and capability from commercial construction firms, design-builders, and Non-Traditional Defense Contractors (NDCs). The intent is to gather critical feedback regarding advanced commercial construction methodologies, project delivery risks, and acquisition preferences to support our upcoming project delivery selection.
3. ACQUISITION STRATEGY & NON-FAR MODEL.
a. Statutory Authority: This project will potentially be executed as a Progressive Design-Build (PDB), Design-Build to Budget (DBtB) or Construction Management at Risk (CM@Risk) project utilizing Other Transaction Authority (OTA) pursuant to 10 U.S.C. § 2808a.
b. Non-FAR Environment: Prospective partners are advised that the Federal Acquisition Regulation (FAR) does NOT apply to this procurement. The negotiated, bilateral Other Transaction Agreement will serve as the sole governing contract. Standard FAR clauses are inapplicable, though federal statutory constraints (such as federal fiscal law, criminal statutes, and general civil laws) remain fully applicable.
c. Agreement Mechanics:
(1) PBD Procurement Process: Phase 1, Design & Pre-Construction Services, a design-builder will be selected through a qualifications-based selection (QBS) process. The government will then negotiate a fee for Phase 1 services. There is no requirement to submit price proposals or design concepts during the initial selection.
Phase 2, Final Design & Construction, is executed via a bilateral modification to the OT Agreement upon successful negotiation of a Guaranteed Maximum Price (GMP) at approximately 65% design maturity. The Agreement contains an "off-ramp" clause allowing the Government to retain the design and procure construction separately if GMP negotiations fail.
(2) DBtB Procurement Process: Solicitation and evaluation during Phase 1 focuses on the qualifications, past performance, and integrated Design-Build experience of each offeror. The Government is evaluating the team and not necessarily how the offeror will design the structure. The Phase 1 evaluation results in the selection of three of the most highly qualified, competitive teams to proceed to Phase 2.
Phase 2, the Government will issue the final RFP exclusively to the down-selected teams. This RFP includes the validated, performance-based requirements, establishes the firm Construction Cost Limit (CCL), and clearly defines the basic scope.
(3) CM@Risk Procurement Process: Early involvement, separate contracts, guaranteed maximum price and collaborative delivery.
4. PROJECT OVERVIEW & SCOPE.
a. Title: Repair Building 5546 Crisis Action Center
b. Location: Barksdale Air Force Base, Louisiana
c. Scope: Construct a 9,000 square foot facility conversion into a secure space. This renovation of the Crisis Action Center will utilize a double-height space that is currently open to the third floor. It will consist of workstations that must contain 5 distinct networks. This facility must seamlessly support heavy audiovisual and office equipment loads, including Secure Video Teleconference (SVTC) Systems. Finally, all facility alarms and HVAC modifications must be engineered to fully integrate with and adhere to the existing Barksdale AFB standards and requirements.
d. Projected Award Date: The Government targets the formal award of the Agreement Phase 1 (Design and Preconstruction Services) on or before July 2027.
e. Current Design is at 100%. The Government is willing to revert to a 35% design, allowing the awardee and designer the ability to collaborate during an OTA procurement process.
f. Period of Performance (POP): The projected construction timeline is approximately 730 calendar days following the execution of the Phase 2 Construction modification.
g. Product Service Code (PSC): Y1BG (Construction of Electronic and Communications Facilities).
h. NAICS Code: 236220 (Commercial and Institutional Building Construction).
(1) INNOVATIVE METHODOLOGIES & FEEDBACK AREAS. In accordance with Air Force Civil Engineer Center (AFCEC) Design Instruction #3, the Government is seeking commercial industry feedback regarding the feasibility and market capacity for the following innovative methods:
i. Modular and Off-Site Prefabrication: Fabricating large sections of the facility or complex mechanical, electrical, and plumbing (MEP) systems in factory-controlled environments to compress the construction schedule.
ii. 3D Printing: Utilizing large-scale 3D printing for secondary building components, non-load-bearing walls, or perimeter security fencing.
iii. Advanced Materials: Incorporating self-healing concrete to reduce lifecycle maintenance and maximize structural integrity, or utilizing high-performance insulation (e.g., aerogels or vacuum-insulated panels) to meet high-performance building standards.
APPENDIX B
1. Project Overview & Mission Goal
· Project Name/Number: Repair Building 5546 Crisis Action Center
· Location: Barksdale Air Force Base, Louisiana
· Mission Statement: The US Army Corps of Engineers, Fort Worth District, has a requirement from the U.S. Air Force to provide a Design-Bid-Build, Firm Fixed-Price contract to renovate and convert a 9,000 sq. ft. space to a new Crisis Action Center.
· The Government currently has a 100% design through an existing contract for the subject project and prefers to keep the existing A-E Designer involved in the project. This will mean the awardee for the subject project would partner with the existing A-E Designer, instead of choosing their own. The Government is willing to revert to a lesser design phase, no less than 35%, allowing the awardee and designer the ability to collaborate during an OTA procurement process (i.e., PDB, DBtB or CM@Risk).
2. Functional Requirements (The "What")
· Facility Type: 30 personnel - Crisis Action Center
· Estimated Scale: 9,000 sq. ft.
· Primary Functional Spaces:
· Space A: 30 Workstation including 5 distinct networks, 6 Standard Offices, and 3 Executive Offices
· Space B: Video Conference Rooms; 2 each, 6 person and 25 person
· Space C: Interior buildout to leverage existing raised flooring system designated areas and existing restrooms.
· Key Performance Targets: All work will meet DoD standards for security, anti-terrorism, and cybersecurity.
3. Known Project Constraints
· Site Conditions: Renovation of existing facility, potential for asbestos and lead-based paints.
· Security/Access: Project is located inside the cantonment area; all personnel must undergo background checks for site access.
· Utilities: Utilities are existing, work is limited to interior work and incorporation and update of existing restrooms.
4. The Construction Cost Limitation (CCL)
· The Fixed Budget: The Target Price Range (TPR) is estimated is between $13,500,00 and $14,238,842 (the strict CCL/CWE limit), with a total Programmed Amount (PA) of $15,000,000.
· What it Includes: This amount covers all design services and construction. It excludes Government-furnished equipment (GFE).
· The DBB Challenge: USACE is seeking a design-build team that can provide the highest level of technical merit, quality, and mission-capability.
5. Proposed Project Schedule
· Period of Performance: 730 Calendar Days from Notice to Proceed.
· Critical Milestones:
· Solicitation Release – JAN 2027
· Proposals Received – MAR 2027
· Proposal Revisions Submitted – APR 2027
· Contact Award – JULY 2027
6. OTA vs FAR Based Acquisition
· The purpose of this market research is to assist the Government in determining if OTA or a FAR-based acquisition is appropriate. The next page provides information for two OTA procurement methods and one FAR based procurement method (i.e., Highest Technically Rated).
· Stipends: A stipend is not authorized.
· Incentives: Not mentioned in the source selection plan.
Progressive Design-Build –
Progressive Design-Build is a collaborative project delivery method where the owner selects a design-builder based on their qualifications and experience, rather than on a detailed bid. Success hinges on proactive, early integration of construction expertise, a commitment to transparent "open-book" estimating, and a culture of collaborative decision-making.
The defining characteristics of PDB:
· One integrated team: The Government selects a design-builder—designer and constructor working as one team—at the beginning of project development, before a meaningful amount of design is complete.
· Qualifications led selection: Selection focuses heavily, and often exclusively in the initial stage, on relevant experience, past performance, technical capability, proposed personnel, and ability to collaborate—not a low construction bid.
· Construction not priced at award: The initial agreement award Phase 1 services. A price for construction, such as a guaranteed maximum price (GMP) is set only once the design, scope, schedule, and risks have been sufficiently developed.
Design-Build to Budget –
Design-Build to Budget is a project delivery method where the project's budget is established as a firm, fixed design constraint from the beginning. Its ultimate outcome is a fixed-price contract with a single, integrated design-build team.
The defining characteristics of DBtB are:
· Budget as a Primary Driver: Unlike other methods where the design determines the final cost, DBtB challenges the industry to innovate and provide the best possible technical solution within a pre-established, maximum budget.
· Performance-Based Requirements: The owner defines what the facility must achieve (performance, operational needs, quality) but does not provide a prescriptive design. This leaves the how entirely up to the competing design-build teams.
· Collaborative Refinement: The procurement process involves confidential, proprietary meetings with shortlisted teams. In these meetings, the owner provides feedback on preliminary concepts, allowing teams to refine their solutions to best align with the project's goals before submitting a final proposal.
Construction Management at Risk (CM@Risk) – Construction Management at Risk is a delivery method in which the owner hires a construction manager during design to provide preconstruction support and later serve as the general contractor. The CM@Risk firm commonly delivers the project under a Guaranteed Maximum Price (GMP).
The defining characteristics of CM@Risk are:
• Early Involvement: The CM@Risk provides cost estimating, scheduling, constructability reviews, and procurement advice during design.
• Separate Contracts: The owner contracts separately with the architect/engineer and the CM@Risk firm, which typically manages the trade subcontractors.
• Guaranteed Maximum Price: The CM@Risk develops a GMP and accepts defined cost and construction-performance risk within that agreement.
• Collaborative Delivery: The owner, designer, and CM@Risk coordinate throughout the project; phased construction may begin before design is fully complete.
Market Intelligence Report: Industry Day/First Look Questionnaire General Feasibility & Model Selection (DBtB vs. PDB vs. CM@Risk)
1. Agreement Preference: The Government is exploring the use of an Other Transaction (OT) Agreement for this construction project to potentially increase collaboration, speed, and innovation. For this specific project, do you believe an OT agreement is the most appropriate vehicle, or would your firm prefer a traditional FAR-based contract? Please explain your reasoning.
Your Answer:
[Please type your detailed reasoning here]
2. OT Risk & Barriers: If the Government chooses to proceed with an OT framework rather than a traditional FAR Part 15 procurement, does your firm foresee any barriers, risks, or hesitations in proposing on or executing this project?
[ ] No [ ] Yes
[If yes, please explain the barriers, risks, or hesitations here]
3. Model Viability: Based on the parameters provided in the Project Information Packet (Appendix B), does your firm believe it is feasible to propose a reliable, fixed price (including incentives) for this project after a 2–3 month collaborative design refinement period?
☐ Yes, a reliable price is likely achievable.
☐ No, there is too much risk/uncertainty to provide a reliable price this early.
4. Risk Justification: Please explain your reasoning for the answer above. What are the top 1-3 factors (e.g., project complexity, site conditions, clarity of functional requirements) that influenced your choice?
Your Answer:
| Factor 1 |
| Type Factor here |
| [Please type your Factor 1 justification here] |
| Factor 2 |
| Type Factor here |
| [Please type your Factor 2 justification here] |
| Factor 3 |
| Type Factor here |
| [Please type your Factor 3 justification here] |
5. PDB Threshold: If you answered "No" to Question 1, at what level of design maturity (e.g., 35%, 60%, 90%) would your firm feel confident in providing a reliable, fixed price or Guaranteed Maximum Price (GMP) through a Progressive Design-Build process?
☐ 35% ☐ 60% ☐ 90% [Please type your detailed reasoning here]
I. Budget & Financial Realism
1. Budget Alignment: Based on your firm's recent experience with similar projects, does the proposed Construction Cost Limitation (CCL) of $13.5M - $14.2M for approximately 9,000 square feet complex facility appear realistic in the current local market?
[Please provide your assessment here]
2. Major Cost Drivers: From a high-level view of our functional requirements, do you see any specific mission needs (e.g., specialized security, unique structural loads) that you anticipate will be the primary drivers of cost?
[Identify potential primary cost drivers here]
3. Market Precedents: Are there specific benchmarks or recent industry projects we should look at to ensure our expectations for quality and performance align with this budget?
[Identify potential projects and locations here]
II. Flexibility & Innovation (The "How")
1. Prescriptive "Showstoppers": Are there any requirements in our functional description that appear overly prescriptive or "locked-in" that might prevent you from offering a more innovative or cost-effective solution to meet the mission?
[Identify any restrictive requirements here]
2. Innovation Opportunities: In this building type, where do you typically see the most opportunity for an integrated design-build team to provide "more for the money" (e.g., modular systems, envelope efficiency, MEP coordination)?
[List innovation opportunities here]
III. Market & Supply Chain (External Risks)
1. Long-Lead Warning: Even without a full design, are there specific systems common to this facility type (e.g., generators, custom AHUs, specialized lab equipment) that are currently experiencing lead times that would threaten the proposed project schedule?
[List any long-lead items of concern here]
2. Local Labor Constraints: Are there specific trades in the project area that are currently over-extended or in short supply that could impact the project's risk profile?
[List any trades currently over extended or in short supply]
IV. Defining Value (The Betterment Search)
1. The Value Gap: If your team discovers or recommends any in design efficiencies during the proprietary meetings, which "betterments/enhancements" (e.g., enhanced durability, lower life-cycle costs, better technology) should we prioritize in our evaluation criteria as the most valuable for this facility type? (List 3-5 options for industry to rank).
| Government “betterments/enhancements” |
| Industry’s Ranking |
| Estimated Dollar Amount |
| Enhanced Durability |
| [1-5] |
| $ |
| Lower Lift-Cycle Cost |
| [1-5] |
| $ |
| Better Technology |
| [1-5] |
| $ |
2. Sustainability Targets: Is the proposed level of sustainability (e.g., Specific energy goals, etc.) a standard "reach" for industry, or will it require significant premium pricing in this market?
[Provide your assessment on sustainability targets here]
V. Proposal Effort & Contract Incentives
1. Stipend Necessity: Given the requirement to participate in five proprietary meetings and develop a conceptual design for Phase 2 evaluation, is a stipend necessary for your firm to justify the pursuit costs of this procurement? Yes or no, and why?
☐ Yes ☐ No [Your answer here]
2. Stipend Alignment: If a stipend is offered, what amount (or percentage of the CCL) does the market currently consider sufficient to offset the level of effort required for a Phase 2 proposal of this complexity?
[Indicate the sufficient stipend amount or percentage here]
3. Effective Incentives: In a fixed-budget environment, what types of post-award contract incentives (e.g., award fee for exceptional quality, schedule acceleration, shared savings) are most effective at motivating your team to exceed minimum performance requirements?
[Describe the most effective incentives here]
Technical Question and Cutoff for This Sources Sought Notice:
Please submit all questions and concerns regarding this Sources Sought Notice via ProjNet ONLY The absolute cutoff for all inquiries is Thursday, September 27, 2026, NLT 10:00 A.M. Central Daylight Time (CDT).
Please use ProjNet for all questions regarding this project.
VI. Additional Inquiries or Comments
We have established a ProjNet, http://www.projnet.org/projnet, for additional inquires and questions. To self-register go to web page, click Quick Add link, select agency USACE, enter Key for this solicitation listed below, and your e-mail address, click Continue. Fill in all required information and click Add User. Verify that information on next screen is correct and click continue. From this page you may view all bidder inquiries or add inquiry. Bidders will receive an acknowledgement of their question via email, followed by an answer to their question after it has been processed by our technical team.
Project ID Number: 515212 Bidder Inquiry Key Number: YP7GWK-Y7244Z
Capability Statement Response and Complete Package Submission Deadline:
Thursday, September 30, 2026, NLT 06:00 P.M. CDT.
FUTURE INDUSTRY DAY: A virtual Industry Day is being scheduled; however, a specific date and time have not yet been established. This scheduling information, along with registration details and access links, will be published in a subsequent Special Notice on SAM.gov.
We ask all interested parties to closely monitor SAM.gov for these upcoming details.
During the session, the USACE Project Delivery Team (PDT) and AFCEC representatives will discuss the collaborative mechanics of the potential PDB/OTA model.
File details come from the government source that posted it. Updated .