This document outlines requirements for the Enhanced Combat Rubber Reconnaissance Craft (E-CRRC). Key details include:
-
The Marine Corps requires a Berry Amendment compliant E-CRRC to improve upon the legacy Combat Rubber Raiding Craft. The E-CRRC must meet detailed functional and performance specifications covering design, supply responsibilities, sustainment, and identification markings.
-
Offerors interested in the pre-solicitation opportunity must be registered in the System for Award Management. The solicitation number is M67854-21-R-1801 and will be issued by the Marine Corps Systems Command Program Manager for Infantry Combat Equipment. The E-CRRC aims to enhance raiding capabilities for Marine Corps reconnaissance personnel.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
E-CRRC-PRF-0001
Aug 2020
DRAFT
PERFORMANCE SPECIFICATION
FOR THE
ENHANCED COMBAT RUBBER
RECONNAISSANCE CRAFT
Version 1.1
Distribution Statement D: Distribution authorized to Department of Defense and U.S. DoD contractors only;
Administrative or Operational Use. Other requests shall be referred to Marine Corps Systems Command, Product Manager Reconnaissance & Amphibious Raids, 2200 Lester Street, Quantico, VA 22134-6050.
UNCLASSIFIED/FOR OFFICIAL USE ONLY DRAFT E-CRRC-PRF-0001V1.1
1 SCOPE
1.1 Scope
This specification describes the functional and performance requirements for the Enhanced
Combat Rubber Reconnaissance Craft (E-CRRC) which is the next generation inflatable raiding craft. Marine Corps reconnaissance personnel are in need of an improved inflatable craft used in conjunction with the fielded 55 hp Non-Gasoline Burning Outboard Engine (NBOE) in order to effectively execute amphibious reconnaissance missions. The E-CRRC will be used for insertion/recovery of personnel and the performance of related amphibious reconnaissance activities in a prospective landing area. It is essential to Marine Corps reconnaissance operations that a clandestine delivery means to enable personnel to cover extended distances across the ocean from the launch/recovery point to the objective area is provided. The newly designed craft must be capable of air drop/delivery in the execution of this primary mission of tactical insertion of small reconnaissance teams
1.2 System Description
The E-CRRC will have increased load carrying capacity as well as improved ride quality, speed, stability and seakeeping in heavy seas over the legacy CRRC. The improved ride quality will deliver Reconnaissance Marines to the objective with reduced fatigue and strain after long distance offshore transits.
1.3 Mission Profiles
The E-CRRC will be used to support Marine Corps reconnaissance missions to conduct amphibious raids. This involves swift incursions into hostile territory, conduct of the raid mission, and a planned withdrawal. Insertion into the mission area will be by ship, helicopter and fixed-wing aircraft. The system will operate across the spectrum of day and night, and in all climates and terrain in which the Marine Air Ground Task Force is employed.
1.4 Use of “Shall” and “Should”
The structure of this specification states requirements using two distinct language provisions: 1)
Binding provisions use the term “shall” to represent the threshold values and is the mandatory requirement, and 2) Non-mandatory provisions use the term “should” to represent the objective values and represents the desired operational performance.
2 APPLICABLE DOCUMENTS
2.1 General
This section provides a list of documents referenced throughout Sections 3 and 4 of this specification. Although this is a comprehensive list, it is not all inclusive; therefore, users of this document are cautioned to communicate with the appropriate technical experts to verify compliance with all additional policies and regulations that may be applicable to a given situation or scenario.
2.2 Government Documents
2.2.1 Specifications, Standards, and Handbooks
MIL-STD-810H, w/Ch 1 Environmental Engineering Considerations and
(31 Jan 2019) Laboratory Tests
10 U.S.C § 2533a Requirement to Buy Certain Articles from American
Sources
FED-STD-191 Textile Test Methods
(Copies of these documents are available online at http://assist.daps.dla.mil/quicksearch/ or from the Standardization Document Order Desk, 700 Robbins Avenue, Building 4D, Philadelphia, PA
19111-5094.)
2.2.2 Other Government Documents, Drawings, and Publications
MCO P5215.17C The Marine Corps Technical Publications System
2.3 Order of Precedence
In the event of a conflict between the text of this document and the references cited herein
(except for associated detail specifications, specification sheets, or Military Specification standards), the text of this specification shall take precedence. Nothing in this document, however, shall supersede applicable laws and regulations unless a specific exemption has been obtained.
3 REQUIREMENTS
3.1 Design
3.1.1 Materials.
3.1.1.1 Berry Amendment. All materials used in construction of the E-CRRC shall be in compliance with the Berry Amendment (10 U.S.C 2533a)
3.1.1.2 Fabric. The coated fabric used in the construction of E-CRRC inflatable buoyancy chambers shall have a base fabric of polyester, nylon or Kevlar with a coating of polyurethane, neoprene, or chlorosulfonated-polyethelene (CSM) rubber.
PVC coated fabrics are not acceptable.
3.1.1.3 Puncture. OSA 1. The E-CRRC shall be constructed of material resistant to the effects of puncture caused by coral and other jagged obstacles. The E-CRRC shall have a puncture resistance of 360 N (81 lbs) when tested per Method 5120 of FED-STD-191, in
Section 4.3.1.2.
3.1.1.4 Environmental. The E-CRRC shall be constructed of material not adversely affected by oil, fungal attack or exposure to sunlight such as may be encountered and applied during its life cycle.
3.1.2 Weight.
3.1.2.1 KSA 5. A fully inflated E-CRRC without equipment, engine, or fuel shall be man portable by six Marines (T), four Marines (O).
3.1.2.2 The E-CRRC shall not exceed 360 (T), 325 (O) pounds empty weight. Weight is exclusive of engine, fuel, equipment, inflation cylinders and supply system responsibility items (SSRI).
3.1.3 Deck.
3.1.3.1. The deck shall be inflatable to minimize injuries to crew and passengers.
3.1.3.2. The deck shall be removable from the craft without special tools for repair and replacement.
3.1.3.3. The deck shall be collapsible and remain within the craft during rolled storage.
3.1.3.4. The deck shall be constructed of a nonskid material or coating on the top layer.
3.1.3.5. The deck shall extend from the transom to the bow of the E-CRRC.
3.1.3.6. The deck shall incorporate a minimum of 10 equipment securing points distributed evenly along the length of the craft deck.
3.1.3.7. The deck shall be isolated from the E-CRRC main buoyancy chambers in case of puncture.
3.1.3.8. The E-CRRC shall be capable of a minimum speed of 6 knots, at full combat load, in the event of deck puncture and deflation.
3.1.4 Transom
3.1.4.1. The transom shall be sized for use with the USMC 55 HP Non-Gasoline Burning
Outboard Engine (NBOE).
The NBOE is a single long shaft (20”) Evinrude outboard engine with pump jet weighing 270 lbs .
3.1.4.2. The transom shall incorporate a hardened corrosion resistant faceplate and lip.
3.1.4.3. The transom shall have bolts or pins included which the NBOE to be bolted or pinned through the transom to prevent the engine from falling off in the event that the transom clamps loosen.
3.1.4.4. The transom angle shall be approximately -14° for mounting of the NBOE.
3.1.5 Inflation. APA 1.
3.1.5.1 The E-CRRC shall be inflatable via manual foot pumps.
3.1.5.2 The E-CRRC shall be inflatable via standard SCUBA tanks.
3.1.5.2.1 The inflation hose(s) assembly shall attach to the inboard side of the E-
CRRC in the aft of the craft using quick disconnect fittings capable of preventing air loss when the automatic inflation system is not used.
3.1.5.2.2 Yoke style connection valves for a Self-Contained Underwater Breathing
Apparatus (SCUBA) tank shall be provided for inflation of the E-CRRC.
3.1.5.2.3 The craft shall be fully inflated using no more than two 100 ft3 SCUBA bottles at 3000 psi.
3.1.5.3 The E-CRRC inflation chambers shall be fitted with valves capable of transferring the inflation air from one chamber to an adjacent chamber of the same pressure.
3.1.6 Inflation/deflation valves
3.1.6.1 Inflation/deflation valves shall be provided on each inflatable chamber of the E-
CRRC.
3.1.6.2 To prevent entry of sand or debris, the valves shall be equipped with a protective non-corrosive or coated metal cover attached by a lanyard or tether.
3.1.6.3 The valves shall be capable of being locked in an open position to facilitate deflation and shall be marked to indicate instructions for their proper operation.
3.1.6.4 Two (2) additional valves, one each port and starboard on the top side of the main buoyancy tube aft chamber end cones just forward of the end caps shall be provided and designated as dump valves.
3.1.6.5 A single dump valve shall be located near the bow for deflation during cache.
3.1.7 Relief Valves.
3.1.7.1 A system of relief valves shall be installed in the E-CRRC tube chambers to protect from inadvertent overpressure.
3.1.7.2 The relief valves shall be installed and located in a manner which avoids damage by craft personnel or their equipment.
3.1.7.3 The relief valve shall relieve at a craft pressure no greater than 190 percent (%) of the designed working pressure and reseat at 120 percent (±10%) of the designed working pressure.
3.1.7.4 Relief valves shall be capable of being rendered inoperable by design or poppet retainer.
3.1.7.5 All metal parts which can cause damage to the craft fabric shall be protected.
3.1.8 Grab Lines.
3.1.8.1 A minimum of one grab line on the craft interior perimeter shall be included.
3.1.8.2 Interior grab line must be reachable by a Marine seated in the craft.
3.1.8.3 A minimum of one grab line on the craft exterior perimeter shall be included.
3.1.8.4 Exterior grab line must be reachable by a Marine in the water.
3.1.8.5 Grab lines shall be a minimum ½ inch diameter, double braided black nylon rope.
3.1.9 Tie-Down Points.
3.1.9.1 The E-CRRC shall have a minimum of fifteen equipment tie-down points on the interior of the craft.
3.1.9.2 Individual equipment tie-down points shall have a minimum pull strength of 250 lbs.
3.1.9.3 Tie-down points shall accommodate a ¾ inch line.
3.1.10 Towing Points.
3.1.10.1 The E-CRRC shall be equipped with a towing bridle.
3.1.10.2 The E-CRRC shall be equipped with attachment points at the bow allowing the
E-CRRC to be towed.
3.1.10.3 The E-CRRC shall be equipped with attachment points at the stern allowing the
E-CRRC to tow.
3.1.11 Rubbing Strips. Rubbing strips shall be installed on areas subject to abrasion. These areas shall include at a minimum, the keel and perimeter of the main buoyancy tubes.
3.1.12 Multifunctional Lifting Points.
3.1.12.1 The E-CRRC shall have lift points capable of supporting the weight of the craft, motor(s), 36 gallons of fuel and 1000 pounds of gear on a level plane without damage.
3.1.12.2 Lifting points shall be accessible at all times and shall not interfere with the loading/distribution of equipment on the deck.
3.1.13 Carry Handles.
3.1.13.1 The E-CRRC exterior shall have a minimum of eight carry handles (4 on each side) located on the outboard sides of the E-CRRC main buoyancy tubes.
3.1.13.2 Carry handles shall be capable of use with a gloved hand.
3.1.13.3 Carry handles shall be located on the same plane of the craft exterior so that the carry height is the same for all operators.
3.2 Supply System Responsibility Items (SSRI)
3.2.1 Manual Inflation Pumps.
3.2.1.1 Two, foot operated pumps capable of inflation and deflation of all chambers shall be provided with each craft.
3.2.1.2 A hose assembly adaptable to the pump on one end and a fitting compatible with the E-CRRC inflation valve on the other end shall be provided with each pump.
3.2.2 Hoisting Sling.
3.2.2.1 A hoisting sling manufactured from non-metallic rope or flat webbing shall be provided with each craft.
3.2.2.2 One end of the legs of the sling shall be attached to a common link by means of eye splices
3.2.2.3 The craft end of the legs shall be equipped with safety snap hook end fittings on each leg.
3.2.2.4 The legs of the sling shall be of a length to allow hoisting of the craft in a level plane when configured with the NBOE on the transom and 36 gallons of fuel in the bow.
3.2.2.5 The hoisting sling shall be designed with a safety factor of 6 on the hoisting weight of the craft. The hoisting weight is defined as the craft, NBOE, 36 gallons of fuel and 1000 pounds of gear.
3.2.2.6 The legs of the hoisting sling shall be statically tested to twice the rated working load in each leg of the sling.
3.2.3 Paddles. Eight (8) paddles shall be provided with each E-CRRC.
3.2.4 Paddle stowage.
3.2.4.1 The craft shall be provided with a paddle bag(s) capable of accommodating the eight (8) supplied paddles.
3.2.4.2 The paddle bag(s) shall have a method of attaching to the E-CRRC.
3.2.5 Fuel Bladders.
3.2.5.1 The E-CRRC shall be equipped with collapsible fuel bladder(s), the number and capacity of which shall be determined by the OEM in order to meet the range requirement in 3.3.2. All supplied fuel bladders shall be the same capacity, with individual capacity not to exceed not exceed 18 gallons.
3.2.5.2 The fuel bladders shall be secured in the bow of the E-CRRC and designed to maximize deck space.
3.2.5.3 The fuel bladders shall be resistant to JP-5, JP-8 and gasoline.
3.2.5.4 The fuel bladders shall be securable with quick release disconnects and removable within one (1) minute fully loaded.
3.2.5.5 The fuel bladder shall have a connector which mates with the supplied fuel line.
3.2.5.6 The fuel bladders shall have a carry handle(s), rated to the weight of the fuel bladder while fully loaded, for transport on land.
3.2.6 Fuel line.
3.2.6.1 The E-CRRC shall be equipped with a fuel line sized to reach from the fuel bladder(s) in the bow to the NBOE attached on the transom, routed around the perimeter of the E-CRRC.
3.2.6.2 The fuel line shall have connections, with one end of the fuel line connecting to the fuel bladder(s) and the other end to the NBOE.
3.2.6.3 The fuel line shall contain a manual squeeze bulb for priming the NBOE.
3.2.7 Spare Valve Kit. A spare valve kit containing one (1) pressure relief valve, one (1) lock open inflation/deflation valve, two (2) blanking plugs, and two (2) relief valve poppet retainers shall be provided.
3.2.8 Craft Tool Kit. A craft tool kit, containerized in a non-metallic buoyant hard case, containing all tools required to assemble, disassemble, and operate the craft shall be provided.
3.2.9 Onboard Repair Kit.
3.2.9.1 An onboard repair kit, containerized in a non-metallic buoyant hard case, shall include all necessary repair material, adhesive, patches, emergency repair clamps, tools, and instructions necessary to make a minimum of five repairs to the E-CRRC. Patches shall be of sufficient size to repair a 2” sized puncture or laceration.
3.2.9.2 The repair kit shall include at least two field-expedient types of patches in the event the craft is damaged while on a mission or on the water.
3.2.10 Tow Bridle. A double braided black polyester rope towing bridle with 15 foot legs shall be provided for each craft.
3.2.11 Valve Wrench. If required for the maintenance of the E-CRRC valves, a valve wrench shall be provided with each craft.
3.2.12 Pressure Gauge.
3.2.12.1 A minimum of one pressure gauge shall be provided with each craft.
3.2.12.2 Pressure gauge shall be compatible with all manual inflation system valves on the E-CRRC
3.2.12.3 Pressure gauge shall cover the range of working pressures found on the E-
CRRC.
Table 1 summarizes the items required in the Supply System Responsibility Items kit.
Table 1 Supply System Responsibility Items kit
3.3 Performance
3.3.1 Payload. KPP 1. When powered by the Marine Corps Non-Gasoline Burning Outboard
Engine (NBOE), the E-CRRC shall be capable of carrying eight combat loaded Marines and equipment having a total weight of 2400 pounds (T), 2800 (O).
Supply System Responsibility Item QTY
a. Manual foot inflation pump with hose and inflation valve adapter end fitting
b. Hoisting Sling 1
c. Paddles 8 d.
e.
Paddle Bag (s)
Spare valve kit containing, one (1) pressure relief valve, one (1) lock open inflation/deflation valve, two (2) blanking plugs, and two (2) relief valve poppet retainers
As Required
f. Craft tool kit (consisting of all tools required to operate the craft) 1
g. Onboard repair kit 1
h. Tow Bridle 1
i. Valve wrench (if required) 1 j.
k.
l.
Pressure Gauge
Fuel Bladder(s)
Fuel Line
TBD on OEM determined range requirements
The payload is personnel and gear only, and does not include craft, engine, fuel and supply system responsibility items (SSRI).
3.3.2 Range. KPP 3. The E-CRRC, when powered by the NBOE with a full combat load in
Sea State 2, shall be capable of a 50 NM insert (T), 100 NM (O), five hours loiter at idle, and 50 NM extract with a 10% fuel reserve while running on JP-5 or JP-8. (Total range
100 NM insert/extract (T) 200 NM insert/extract (O) w 5 hour loiter at idle + 10% reserve)
Fuel is independent of the defined payload and will be determined by the manufacturer in order to meet the range requirement.
3.3.3 Speed. KPP 4. A combat loaded E-CRRC shall provide a minimum top speed of 18 kts
(T), 24 kts (O) in Sea State 2, when powered by the NBOE.
3.3.4 Shock. The E-CRRC shall have at least a 1/3 reduction in vertical accelerations, when compared to the current USMC CRRC with hard deck, in any sea state and direction at maximum speed. The accelerations shall be measured in units of “g” (acceleration due to gravity), determined as the average of the 1/10 highest peak vertical accelerations.
Accelerations shall be measured just aft of the fuel bladders, which is the most forward position personnel would be located as to record the most severe vertical accelerations that personnel on board would experience.
3.4 Self-Recovery. KSA 9
3.4.1 A combat loaded E-CRRC shall be able to tow another combat loaded E-CRRC in sea state 2 at 4 knots (T), 8 knots (O).
3.4.2 A combat loaded E-CRRC shall be capable of being towed by another combat loaded E-
CRRC in sea state 2 at 4 knots (T), 8 knots (O).
3.5 System Survivability
3.5.1 Surf Passage. KSA 1. A fully combat loaded E-CRRC shall be capable of transit through plunging surf with a six-foot wave height (T), ten-foot significant wave height
(O).
3.5.2 Self-bailing. The E-CRRC shall have the ability to self-bail in the event of being fully flooded by a wave during surf passage in less than two minutes (Threshold), 60 seconds
(O).
3.5.3 Puncture. KSA 4. The combat loaded craft shall provide floatation after puncture by threat weapon systems or environmental hazards (T=O). Puncture assumes that the damage chamber becomes completely deflated.
3.5.3.1 Interconnection valves shall be installed between each chamber of the E-CRRC and be capable of being closed to isolate the chamber in the event of damage or failure of an adjacent chamber (T=O).
3.5.3.2 With one chamber deflated, the E-CRRC shall remain capable of non-planing operation at the maximum payload (T=O).
3.5.3.3 With two chambers deflated, the E-CRRC shall remain capable of maintaining level floatation at the maximum payload (T=O).
3.6 Operation
3.6.1 Broaching. KSA 7. The combat loaded E-CRRC shall be capable of being broached by four Marines (T), three Marines (O).
3.6.2 Operation. KSA 8. The E-CRRC shall be operable by personnel wearing Mission
Essential Protective Posture (MOPP) Level IV equipment (T=O).
3.7 Launch and Recovery KPP 2
3.7.1 The E-CRRC shall be capable of launch and recovery from L-class amphibious shipping equipped with well decks without mechanical aid (T=O).
3.7.2 The E-CRRC shall be capable of launch and recovery from the bow ramp of a Landing
Craft Utility (LCU) without mechanical aid (T=O).
3.7.3 The E-CRRC shall be capable of launch and recovery from a Landing Craft Air Cushion
(LCAC) without mechanical aid (T=O).
3.7.4 The E-CRRC shall be helocast deployable from all U.S.M.C. troop tilt/rotor wing aircraft without mechanical aide. Partial deflation of the craft is acceptable.
3.8 Submarine Deployment. APA 3. The E-CRRC should be capable of deployment and recovery aboard current US Navy submarines (O).
3.9 Parachute Insertion. APA 4. The E-CRRC should be capable of parachute insertion onto a water surface via rotary and fixed wing aircraft, without compromising its structural integrity or mission performance (O).
3.10 Signature
3.10.1 KSA 13. The color of the craft shall be non-reflective when wet to reduce visual detection in the operational environment.
3.10.2 All exposed metallic components shall be non-reflective to reduce visual detection.
3.10.3 The craft shall incorporate methods to mitigate visual signature through the reduction of water spray.
3.11 Inflation/Configuration Time
3.11.1 The E-CRRC shall be capable of being manually inflated, using up to two pumps, to the designed working pressure within 15 minutes.
3.11.2 The E-CRRC shall be capable of being inflated using two 100 ft3 SCUBA cylinders at
3000 psi within 5 minutes.
3.12 Storage
3.12.1 A bag shall be provided when the craft is rolled for storage,
3.12.2 The stored dimensions of the E-CRRC shall not exceed Length 90” X Width 48” X
Height 24” (T), Length 78” X Width 36” X Height 12” (O).
3.12.3 The craft shall not be damaged in storage throughout an air temperature range of -30°C (-
22°F) to + 71°C (160°F). The craft fabric shall not crack or distort in any way when stored in these conditions for a period of five years.
3.13 Sustainment.
3.13.1 Materiel Availability. KPP 5. Materiel availability of the E-CRRC shall be 78% (T), 90% (O).
3.13.2 Mean Time Between Operation Mission Failure. KPP 6. The mean time between operational mission failure shall be at least 170 hours (T), 350 hours (O).
3.13.3 Mean Time to Repair. KPP 6. The mean time to repair should be no more than 2.5 hours (T), one hour (O).
3.13.4 Operational Availability. KPP 6. The operational availability should be at least 80%
(T), 90% (O)
3.14 Maintainability. KSA 10. The E-CRRC shall be field repairable by a single Marine in the event of a puncture or leak, 2” in size or less, in less than 15 minutes (T), ten minutes
(O) with a provided onboard repair kit.
3.15 Interchangeability. KSA 11. All E-CRRC components that are replaceable at the organizational level shall be interchangeable.
3.16 Transportability. KSA 12. The E-CRRC, including the floor, shall be inflatable, and collapsible, and small enough to embark four aboard a single MV-22 (T), small enough to be embarked aboard current US Navy submarines (O).
3.17 Operating and Support Cost. KSA 15. The operations and maintenance cost for the E-
CRRC shall be no more than $6000 per system per year (T), $4000 (O).
3.18 Service life.
3.18.1 The operational service life shall be a minimum of five years (T), seven years (O).
3.18.2 The storage life shall be a minimum of five years in climate-controlled storage.
3.19 Identification
3.19.1 Nameplate. The craft shall have a metal nameplate, attached to the starboard side of the transom. The nameplate shall contain the following information:
Enhanced Combat Rubber Raiding Craft (E-CRRC)
NSN Built for the United States Marine Corps by (Contractor, city, state, Cage code)
Date of Mfg., month, year
Contract No. _
Serial No. _
Operating Inflation Pressure: (TBD) mbar ((TBD) psi)
Bare Weight:
Maximum Horsepower: _
Maximum Capacity:
Item Unique Identification (IUID)
3.19.2 Serial numbers. A unique serial number shall be assigned to each craft by the Contractor.
The craft shall have a unique, systematic serial number regardless of contracts or purchase orders.
3.20 Training and Manuals
3.20.1 Training and maintenance instructions. The Contractor shall provide training material and maintenance instructions in English.
3.20.2 Service manual. The contractor of the E-CRRC will prepare a commercial manual, including instruction for opening, inspecting, testing, repairing, and repacking the craft, in accordance with MCO P5215.17C
4 Verification
4.1 General
The contractor shall provide documentation, procedures and test results that certify the requirements of section 3 have been met with responsible party signatures and in accordance with section 4 verification methods. If unique inspection equipment is required, the contractor shall submit designs of all inspection and test equipment used to perform examinations and tests for Government concurrence of methodology. The Government reserves the right to witness or separately perform any or all tests.
4.1.1 Analysis
Analysis is an element of verification that uses established technical or mathematical models or simulations, algorithms, charts, graphs, circuit diagrams, or other scientific principles and procedures in combination with human analytical thought processes to structure and interpret test data to predict the design compliance and provide evidence that stated requirements in Sections are met.
4.1.2 Demonstration
An element of verification which generally denotes the actual operation, adjustment, or re-configuration of items to provide evidence that the designed functions were accomplished under specific scenarios. The items may be instrumented and quantitative limits of performance monitored.
4.1.3 Examination
An element of verification and inspection consisting of investigation, without the use of special laboratory appliances or procedures, of items to determine conformance to specific requirements.
Examination is generally nondestructive and typically includes the use of sight, hearing, smell, and touch; simple physical manipulation; mechanical and electrical gauging and measurement;
and other forms of investigation.
4.1.4 Test
An element of verification and inspection that generally denotes the determination, by technical means, of the properties or elements of items, including functional operation, and involves the application of established scientific principles and procedures. Test of one or more of the following test types are applicable:
Acceptance Test
Acceptance tests are conducted prior to delivery to verify that the system conforms to the requirements contained in the appropriate engineering drawings and specifications. Acceptance tests are performed on every delivered unit and/or subsystem.
Conformance Test
Conformance tests are contractor-conducted events, which demonstrate compliance with requirements herein. These tests are performed on production representative hardware.
4.2 Pre-Production Qualification Testing.
Submission of Certificate of Conformance (COC). COCs shall contain the following information.
Name of company providing the COC and the date of submittal.
Contract number and DFP paragraph number that the COC applies to.
A brief description of the item for which the COC is being provided.
The test standard used to certify the requirement.
The signature and title of the certifying official.
4.3 Design
4.3.1 Materials.
4.3.1.1 Berry Amendment. Through a certificate of conformance, the manufacturer shall provide verification that the materials used in construction of the E-CRRC are in compliance with the Berry Amendment (10 U.S.C § 2533a).
4.3.1.2 Fabric. Through a certificate of conformance, the manufacturer shall provide verification that the E-CRRC base fabric is constructed of polyester, nylon or Kevlar with a coating of polyurethane, neoprene, or chlorosulfonated-polyethelene (CSM) rubber and that PVC coated fabrics were not used in construction.
4.3.1.3 Puncture. OSA 1. Through a certificate of conformance, the manufacturer shall provide verification that the E-CRRC was tested in accordance with Method 5120 of
FED-STD-191 for puncture resistance. Method 5120 of FED-STD-191 applies except that the ring clamp mechanism shall have an internal diameter of 76 millimeters, and the ball shall be replaced by a piercing instrument shaped like a flared, flat-tip screwdriver, having a width of 7.93 ±.250 millimeters, and a thickness of 0.79 ±.10 millimeters, at the extreme tip. The piercing tip edges shall be rounded to a 0.25 millimeter radius.
The piercing instrument shall be oriented to intercept the warp and fill threads at an angle of approximately 45°. The average of three test specimens shall be reported.
Non-conformance to 3.1.1.3 shall constitute failure of this test.
4.3.1.4 Environmental. Through a certificate of conformance, the manufacturer shall provide verification that the E-CRRC material is not adversely affected by oil, fungal attack or exposure to sunlight such as may be encountered and applied during its life cycle as follows:
4.3.1.4.1 Oil. Through a certificate of conformance, the manufacturer shall provide results of the fabric to oil resistance. Failure to meet the oil resistance standard shall constitute non-conformance. The specimen shall be tested as follows:
a. Disk specimen for testing shall be at least 70 millimeters in diameter. A typical apparatus required is shown in Figure 1. It consists of a base-plate (A) and an open-ended cylindrical chamber (B) which is held tightly against the test specimen (C) by wing nut (D), the wing nuts are mounted on bolts (E). A hole of diameter approximately 30 millimeters shall be made in the base plate for the examination of the surface not in contact with the liquid. During the test the opening in the top of the chamber is closed by a close fitting plug (P).
b. Test specimens in the "As Received" condition shall be conditioned for not less than three hours at 20 ±2°C immediately before testing.
c. The test specimens shall be placed in the apparatus as indicated in figure 5. The chamber of the apparatus is then filled with the test liquid to a depth of approximately
20 millimeters and the plug (P) inserted. The required temperature and the duration shall be 20 ±2°C for 22 hours.
d. At the end of the contact period the test liquid is removed and the test specimen released. Any surplus liquid is removed from the surface of the test specimen by blotting with filter paper or a textile fabric which does not deposit lint.
e. The test specimen shall be folded over so that the surfaces are pressed together to see if there are any signs of residual tackiness.
f. With the test specimen opened out, a single pass of the finger over the exposed surface shall not produce smearing.
g. The liquid to be used as a standard test oil shall be ASTM #1 Oil.
Figure 1. Apparatus for test with liquid on one surface only.
4.3.1.4.2 Fungus. Through a certificate of conformance, the manufacturer shall provide results showing the coated fabric is not adversely affected by fungal attack.
The fabric shall be tested in accordance with MIL-STD-810, Method 508.6, except test specimen shall not be sterilized before being subjected to the fungus. The coated fabric shall maintain a minimum of 50 percent of original breaking strength. Failure to meet
MIL-STD-810, Method 508.6 for resistance to fungal attack shall constitute non-compliance.
4.3.1.4.3 Sunlight. Through a certificate of conformance, the manufacturer shall provide results showing the coated fabric is not adversely affected by long term exposure of sunlight. The fabric shall be tested in accordance with MIL-STD-810, Method 505.7, Procedure II. Failure to meet MIL-STD-810, Method 505.7, Procedure
II for resistance to the effects of long term exposure to sunlight shall constitute non-compliance.
4.3.2 Weight.
4.3.2.1 KSA 5. Demonstrate that a fully inflated E-CRRC without equipment, engine, or fuel is man portable by six Marines (T), four Marines (O). Failure to be man-portable by six Marines shall constitute non-compliance.
4.3.2.2 Using a scale, weigh the empty E-CRRC. A weight which exceeds 360 pounds shall constitute non-compliance.
4.3.3 Deck.
4.3.3.1 Inspect the E-CRRC deck to verify that it is inflatable. A non-inflatable deck shall constitute non-compliance.
4.3.3.2 Demonstrate that the E-CRRC deck is be removable from the craft without special tools. Failure to remove the deck without special tools shall constitute non-compliance.
4.3.3.3 Deflate the E-CRRC and roll the craft for storage. Demonstrate that the deck can remain within the craft during storage and does not require removal. Being unable to roll the E-CRRC for storage with the deck installed shall constitute non-compliance.
Removing the deck for rolled storage shall constitute non-compliance.
4.3.3.4 Inspect the deck for the presence of a non-skid coating. Wet the deck, and while wearing USMC combat boots, demonstrate that the deck is not slippery. Verification of how slippery the deck is shall be subjective. Absence of a non-skid coating or determination that the deck is slippery when wet shall constitute non-compliance.
4.3.3.5 Inspect the E-CRRC to verify that the deck extends from the transom to the bow of the E-CRRC. A deck which does not extend from the transom to the bow of the E-
CRRC shall constitute non-compliance.
4.3.3.6 Inspect the deck to verify there are a minimum of 10 equipment securing points distributed evenly along the length of the E-CRRC deck. Having fewer than 10 equipment securing points on the deck shall constitute non-compliance.
4.3.3.7 Inspect the deck inflation system for a valve or other method of isolating the deck air chamber from the rest of the E-CRRC. Isolate the deck valve and deflate the deck to demonstrate that the rest of the E-CRRC does not deflate when the deck is deflated.
Not having a means to isolate the E-CRRC deck and deflation of the E-CRRC when the deck is deflated shall constitute non-compliance.
4.3.3.8 Deflate the E-CRRC deck and with a full combat load, demonstrate that the E-
CRRC is capable of operating at a minimum ofFailure to operate at a minimum of 6 knots with a deflated deck shall constitute non-compliance.
4.3.4 Transom
4.3.4.1 Inspect the E-CRRC to verify that the attached U.S. Coast Guard capacity plate rates the E-CRRC for a minimum 55 horsepower outboard engine. Demonstrate that the
NBOE can be mounted onto the transom and mounting clamps tightened. Demonstrate that the engine can be turned fully left and right without interference. Demonstrate that the engine can be adjusted through each trim position without interference. Having a horsepower capacity rating of less than 55 horsepower, being unable to attach and tighten the NBOE to the transom, or interference in turning or trim positions shall constitute non-compliance.
4.3.4.2 Inspect the transom for a hardened corrosion resistant faceplate and lip. The absence of a hardened corrosion resistant faceplate shall constitute non-compliance.
4.3.4.3 Inspect the transom to verify that bolts or pins are included for holes for bolting or pinning the NBOE to the E-CRRC transom. Using the included bolts or pins, demonstrate that the NBOE can be bolted or pinned to the E-CRRC transom. Bolts or pins not being included or not being able to secure the NBOE to the transom using the bolts or pins shall constitute non-compliance.
4.3.4.4 Measure the angle of the transom relative to the keel of the E-CRRC. A transom angle that is not between -15° and -13° shall constitute non-compliance.
4.3.5 Inflation.
4.3.5.1 Using the included foot pumps, demonstrate that the E-CRRC can be inflated to the required working pressures. Failure to inflate the E-CRRC to the working pressures shall constitute non-compliance.
4.3.5.2 The E-CRRC shall be inflatable via standard SCUBA tanks.
4.3.5.2.1 The inflation hose(s) assembly shall attach to the inboard side of the E-
CRRC in the aft of the craft using quick disconnect fittings capable of preventing air loss when the automatic inflation system is not used. Inspect the E-CRRC for inflation hose(s) on the inboard side of the craft. Inspect the inflation hoses for the presence of quick disconnect fittings. With the craft inflated, demonstrate that the E-CRRC does not lose air when the automatic inflation system is disconnected. The absence of inflation hoses in the specified locations, quick disconnect fittings, or loss of air when disconnected shall constitute non-compliance.
4.3.5.2.2 Inspect the E-CRRC for yoke style connection valves for connection to a
SCUBA tank. Demonstrate that the yoke style connection valves can be attached to a
SCUBA tank. The absence of yoke connection valves or the inability to connect to a
SCUBA tank shall constitute non-compliance.
4.3.5.2.3 With the E-CRRC completely deflated, demonstrate that the craft can be fully inflated to working pressure using no more than two 100 ft3 SCUBA bottles at
3000 psi. Failure to fully inflate the E-CRRC to working pressure with no more than two 100 ft3 shall constitute non-compliance.
4.3.5.3 Inspect the E-CRRC for interconnection valves between inflation chambers of equal pressure. While inflating the E-CRRC from a single point, demonstrate that air transfers between each of the inflation chambers. Failure for air to transfer between chambers shall constitute non-compliance.
4.3.6 Inflation/deflation valves
4.3.6.1 Inspect the E-CRRC for inflation/deflation valves on each inflatable chamber of the E-CRRC. Absence of inflation/deflation valves on each inflatable chamber shall constitute non-compliance.
4.3.6.2 Inspect the inflation/deflation valves for non-corrosive or coated protective metal covers attached by a lanyard or tether. Absence of a protective metal cover for each valve shall constitute non-compliance.
4.3.6.3 Inspect the inflation/deflation valves for markings indicating operation instructions (i.e. inflate/operate). With the E-CRRC fully inflated, open the valves and deflate the E-CRRC. Failure to lock the valves open and deflate the E-CRRC shall constitute non-compliance.
4.3.6.4 Inspect the top, aft main buoyancy tube end cones on the port and starboard side for two deflation/dump valves. With the E-CRRC fully inflated, demonstrate that the craft can be deflated using the two dump valves. Absence of the two dump valves or failure to deflate the E-CRRC using the dump valves shall constitute non-compliance.
4.3.6.5 Inspect the bow for a dump valve to deflate the E-CRRC. With the E-CRRC fully inflated, demonstrate that the craft can be deflated using the single bow dump valve.
Absence of a bow dump valve or failure to deflate the E-CRRC using the dump valve shall constitute non-compliance.
4.3.7 Relief Valves.
4.3.7.1 Inspect the E-CRRC air chambers for the presence of relief valves. Absence of relief valves in the air chambers shall constitute non-compliance.
4.3.7.2 Inspect the relief valve location and installation. The relief valves should be recessed and in locations that avoid damage or snagging by personnel, equipment or lines. Relief valves that are not recessed, in locations where personnel may sit or lean, have sharp edges or other design features which may cause damage or snagging shall constitute non-compliance.
4.3.7.3 Using a manual pump, SCUBA tank, or air compressor, and a pressure gauge, inflate the E-CRRC until a pressure relief valve relieves pressure. Note the pressure on the gauge when this occurs. Pressures greater than 190% of the designed working pressure shall constitute non-compliance. Note the pressure when the valve re-seats and is no longer relieving pressure. Pressures outside of 120 % (±10%) of the designed working pressure shall constitute non-compliance. Repeat for all air chambers that have different working pressure requirements.
4.3.7.4 Using a poppet retainer or other method for rendering the relief valves inoperable, and a pressure gauge, inflate the E-CRRC to 200% of working pressure. Any relief of pressure by the inoperable relief valve shall constitute non-compliance.
4.3.7.5 Inspect all metal parts in the E-CRRC for sharp edges or other characteristics which can cause damage to the craft fabric. Any metal parts which may cause damage to the E-CRRC shall constitute non-compliance.
4.3.8 Grab Lines.
4.3.8.1 Inspect that a minimum of one grab line on the craft interior perimeter is included with the E-CRRC. The absence of an interior grab line shall constitute non-compliance.
4.3.8.2 Demonstrate that the interior grab line is reachable from any position within the craft by a Marine seated in the craft. Failure to be able to reach the interior grab line when seated in any position of the craft shall constitute non-compliance.
4.3.8.3 Inspect that a minimum of one grab line on the craft exterior perimeter is included with the E-CRRC. The absence of an exterior grab line shall constitute non-compliance.
4.3.8.4 Demonstrate that the exterior grab line is reachable by a Marine in the water.
Failure to be able to reach the exterior grab line by a Marine in the water shall constitute non-compliance.
4.3.8.5 Inspect the interior and exterior grab lines to verify that they are double braided black nylon rope. Measure the interior and exterior E-CRRC grab line diameters. Any grab lines that are not double braided black nylon rope and having a diameter of at least
½” shall constitute non-compliance.
4.3.9 Tie-Down Points.
4.3.9.1 Inspect the interior of the E-CRRC for a minimum of fifteen equipment tie-down points. Tie-down points are independent of the tie-down points located on the E-CRRC deck. Having less than fifteen equipment tie down points shall constitute non-compliance.
4.3.9.2 Through a certificate of conformance, the manufacturer shall provide test results verifying that individual equipment tie-down points have a minimum pull strength of
250 lbs. Equipment tie-down points shall be tested for tensile and shear strength. The direction of the pull in the tensile test shall be perpendicular to the tie down points. The direction of the pull in the shear test shall be parallel to the tie-down points. Each equipment securing line point must be capable of withstanding a minimum pull of 250 lbs. A pull test of less than 250 lbs is shall constitute non-conformance.
4.3.9.3 Demonstrate that a ¾” line can be passed through the equipment tie-down points.
Failure to pass a ¾” line through the equipment tie-down points shall constitute non-compliance.
4.3.10 Towing Points.
4.3.10.1 Inspect the E-CRRC SSRI kit for inclusion of a towing bridle. Failure of a towing bridle to be included in the SSRI kit shall constitute non-compliance.
4.3.10.2 Inspect the bow of the E-CRRC for tow attachment points. Demonstrate that the supplied towing bridle can be attached to the towing points. Absence of towing points or failure to attach the supplied towing bridle to the tow attachment points shall constitute non-compliance.
4.3.10.3 Inspect the stern of the E-CRRC for tow attachment points. Demonstrate that the supplied towing bridle can be attached to the towing points. Absence of towing points or failure to attach the supplied towing bridle to the tow attachment points shall constitute non-compliance.
4.3.11 Rubbing Strips. Inspect the E-CRRC for rubbing strips installed on areas subject to abrasion. These areas shall include at a minimum, the keel and perimeter of the main buoyancy tubes. An absence of rubbing strips in areas subject to abrasion shall constitute non-compliance.
4.3.12 Multifunctional Lifting Points.
4.3.12.1 Configure the E-CRRC with the NBOE, 36 gallons of fuel and 1000 pounds of equipment or other weight, such as sandbags. The 1000 pounds of equipment shall be evenly distributed inside of the E-CRRC. Attach the supplied hoisting sling to the multifunctional lifting points of the E-CRRC. Using an overhead hoist, crane, or other means of lifting, suspend the E-CRRC in the air to demonstrate that the multifunctional lifting points can support the E-CRRC as configured. Inspect the lifting points for damage. Inspect that the E-CRRC is suspended in a level plane without distortion or excessive sagging of the E-CRRC. Failure to lift the E-CRRC, damage to the multifunctional lifting points, excessive distortion or sagging of the E-CRRC while suspended shall constitute non-compliance.
4.3.12.2 With the E-CRRC configured for lifting as discussed in 4.3.12, inspect that the multifunctional lifting points are accessible at all times and not obstructed by the engine, fuel bladders, equipment, or other items. Obstruction of the multifunctional lifting points shall constitute non-compliance.
4.3.13 Carry Handles.
4.3.13.1 Inspect the outboard sides of the main buoyancy tubes for carry handles. Failure to have a minimum of eight carry handles (4 on each side) located on the outboard sides of the main buoyancy tubes shall constitute non-compliance.
4.3.13.2 While wearing 7 mm neoprene dive gloves, demonstrate that the carry handles can be securely gripped for lifting the E-CRRC. Failure to use the carry handles with a gloved hand shall constitute non-compliance.
4.3.13.3 Inspect that the E-CRRC carry handles are located on the same plane of the craft exterior. With the E-CRRC empty and using six Marines, lift the E-CRRC and demonstrate that the carry height is the same for all operators. Repeat for all carry handle locations. Alternatively, use a straight edge or taut string between the most forward and most aft carry handles to verify the carry handles are in the same plane.
Failure of all carry handles to be in the same plane shall constitute non-compliance.
4.4 Supply System Responsibility Items (SSRI)
4.4.1 Manual Inflation Pumps.
4.4.1.1 Inspect the E-CRRC SSRI for the presence of two, foot operated pumps. Using the hose assembly in 4.4.1.1 Demonstrate that the E-CRRC can be inflated and deflated using the foot operated pumps. The absence of two foot operated pumps or the inability to inflate and deflate using the pumps shall constitute non-compliance.
4.4.1.2 Inspect the E-CRRC SSRI for a hose assembly adaptable to the manual foot pump on one end and a fitting compatible with the E-CRRC inflation valves. Demonstrate that the hose assembly can be attached to both the manual foot pump and E-CRRC inflation valves. Failure to attach the hose to either the foot pump or E-CRRC inflation valves shall constitute failure.
4.4.2 Hoisting Sling.
4.4.2.1 Inspect the SSRI kit for the presence of a hoisting sling. Inspect that the hoisting sling is manufactured from non-metallic rope or flat webbing. The absence of a hoisting sling, or a hoisting sling made of materials other than non-metallic rope or flat webbing shall constitute non-compliance.
4.4.2.2 Inspect the hoisting sling for the presence of a common link to which each leg of the hoisting sling is attached by means of eye splices. The absence of a common link, or means of attaching the hoisting sling legs other than eye splices shall constitute non-compliance.
4.4.2.3 Inspect the craft end legs of the hoisting sling for the presence of a safety snap hook end fitting on each leg. Demonstrate that the safety snap hook end fittings can be connected to the lifting points of the craft. The absence of safety snap hook end fittings or the inability to attach the fittings to the craft lifting points shall constitute non-
4.4.2.4 With the NBOE attached to the transom and 36 gallons of fuel in the bow, lift the
E-CRRC using the hoisting sling. Using a level, or other suitable measuring device on the deck of the E-CRRC, inspect that the craft is hoisted in a level plane, +/- 10°.
Failure of the E-CRRC to be hoisted in a level plane, +/- 10° shall constitute failure.
4.4.2.5 Through a certificate of conformance, the manufacturer shall certify that the hoisting sling is designed with a safety factor of 6 times the hoisting weight of the E-
CRRC. The hoisting weight is defined as the craft, NBOE, 36 gallons of fuel and 1000 pounds of gear. Failure to provide verification that the hoisting was tested and certified at 6 times the hoisting weight of the E-CRRC shall constitute non-compliance
4.4.2.6 Through a certificate of conformance, the manufacturer shall certify that each leg of the hoisting sling was statically tested to twice the rated working load of the leg.
Failure to provide verification that the legs of the hoisting sling were tested and certified at twice the rated working load shall constitute non-compliance.
4.4.3 Paddles.
4.4.3.1 Inspect the SSRI kit to verify that eight (8) paddles are provided with each E-
CRRC. The absence of eight (8) paddles shall constitute non-compliance.
4.4.3.2 Using the supplied paddles, demonstrate that the E-CRRC can be paddled with a
Marine seated at any location of the gunnel, and that the paddle length is sufficient to utilize the full length of the blade. Failure for the Marine to utilize the full length of the blade at any position of the gunnel shall constitute non-compliance.
4.4.4 Paddle stowage.
4.4.4.1 Inspect that a paddle bag(s) capable of accommodating the eight (8) supplied paddles is provided with the E-CRRC. Failure to provide a paddle bag(s) with the E-
CRRC shall constitute non-compliance.
4.4.4.2 Demonstrate that the paddle bag(s) can be attached to the E-CRRC. Failure to have a method of attached the paddle bag(s) to the E-CRRC shall constitute non-compliance.
4.4.5 Fuel Bladders.
4.4.5.1 Inspect the SSRI kit for collapsible fuel bladder(s). The absence of collapsible fuel bladders, or individual fuel bladders which exceed 18 gallons shall constitute non-compliance. The number and capacity of the fuel bladders will be verified in 4.5.2.
4.4.5.2 Through a certificate of conformance, the OEM shall provide verification that the fuel bladder is resistant to JP-5, JP-8 and gasoline. Failure to provide data verifying that the fuel bladder is resistant to JP-5, JP-8 and gasoline shall constitute non-compliance.
4.4.5.3 Demonstrate that the fuel bladders can be secured in the bow of the E-CRRC and are shaped to maximize deck space. Failure of the fuel bladders to fit in the bow shall constitute non-compliance.
4.4.5.4 Inspect the fuel bladder for quick release disconnects for securing the bladder to the E-CRRC. Demonstrate that a full fuel bladder may be removed from the E-CRRC in less than one minute. The absence of quick disconnects, or failure to remove a full fuel bladder within one minute shall constitute non-compliance.
4.4.5.5 Demonstrate that the fuel bladder is capable of connecting to the supplied fuel line in 4.4.6. Failure of the fuel bladder to connect to the supplied fuel line shall constitute non-compliance.
4.4.5.6 Inspect the fuel bladder for carry handle(s), capable of carrying the fuel bladder.
Demonstrate that a full fuel bladder can be carried for transport over land. Failure of the fuel bladder to have carry handles, or to be transported using the carry handles, shall constitute non-compliance.
4.4.6 Fuel line.
4.4.6.1 Demonstrate that the E-CRRC fuel line can be connected to the fuel bladder(s) located in the bow, routed around the perimeter of the E-CRRC, and connected to the
NBOE mounted on the transom. Failure to route the fuel line as described shall constitute non-compliance.