This document contains run-in test sheets for military vehicles and equipment to be refurbished under a two-year requirements contract. The Army Contracting Command-Detroit Arsenal intends to award a contract to Caterpillar Inc. to perform Service Life Extension Program work on approximately 243 government-furnished vibratory rollers, compactors, dual steel wheel rollers, and deployable universal combat earthmovers. Caterpillar will return the vehicles and equipment to like-new condition. The effort includes core tasks common to all vehicles, and additional unique repair work. The contract also includes estimated additional work to maintain previously refurbished training assets and annual warehousing costs. The contract is a combination of firm fixed price and cost-plus-fixed-fee terms for the period of 30 June 2020 to 29 June 2022. The point of contact is Elaine O. Nelson.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 0007 Compaction Vehicle Core Lists.xlsx | XLSX spreadsheet | |
| Attachment 0008 Geographic Labor Category Breakdown.xls | XLS spreadsheet | |
| Attachment 0006 DEUCE MRPL.XLSX | XLSX spreadsheet | |
| RFP W56HZV20R0030.pdf | ||
| Attachment 0009 IUID Marked Items.xlsx | XLSX spreadsheet | |
| Attachment 0001 DEUCE ATPD-2184.pdf | ||
| Attachment 0002 Vibe Roller I II III PD3895 2190.pdf | ||
| Attachment 0004 DSWR PD3895 0103.pdf | ||
| Attachment 0010 GFP List.xlsx | XLSX spreadsheet | |
| Attachment 0003 HSC MIL PRF 53024C AT.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MILITARY DEUCE RUN-IN TEST
Contract No. _______________________ Serial No. 7RR_____________
QAR
Initials _____ Backup Alarm audible in reverse ………………………………….. YES or NO
(with switches in proper position) _____ All gauges operational………………………………………………..
YES or NO
Specifications:
_____ Engine test correct:
1. High Idle
2590 +/- 50 rpm
2. Low Idle
850 +/- 50 rpm
3. Stall Speed
1970 +/- 30 rpm
(2nd Reverse)
_____ Drive train test correct:
1. Torque Converter Outlet
60 +/- 15 psi (stall speed)
2. Speed clutch (PI) Pressure (neutral) 85 +/- 5 psi Low (low idle)
3. Speed Clutch (PI) Pressure
450 psi max (low idle) 3A ________Gauge (6th -gear self-deployed mode)
4. Directional Clutch (P2) Gauge
4A________ Gauge
5. Directional Clutch (P2) 55 +/- 8 psi (less PI) 5A________ Difference
(5A = 3A minus 4A)
6. Priority Valve Pressure
320 psi min (low idle)
7. Lubrication System Pressure
15 +/- 7 psi
______Steering System Pressures
1. High Pressure Cutoff (Gauge)
1A________ Gauge
2. Charge Oil Pressure
350 +/- 50 psi (high idle) 2A________ Gauge
3. High-Pressure Cutoff:
6000 +/- 100 psi above Charge Oil Pressure
3A________ Difference
(3A = 1A minus 2A)
4. Flushing Relief Valve
35 +/- 10 psi (press. Diff)
______Brake System Pressures
1. Parking Brake Pressure Limiter 800 +/- 30 psi
2. Brake System (high idle)
2950 +/- 100 psi 2A ________
3. Brake System (low idle)
2200 +/- 200 psi (min) ________ (max same as 2A) ______Hydraulic System Pressures
1. Low Pressure Standby (Gauge)
1A________ Gauge
2. Margin Pressure
300 +/- 50 psi 2A________ Gauge
3. Low-Pressure Standby (1A) 50 +/- 10 psi above Margin Pressure
3A________ Difference
(3A = 1A minus 2A)
4. High Pressure Stall
2950 +/- 100
Updated 30 Oct 14 continued…
QAR
Initials _____ Implement System Test correct:
1. Lift Cylinder Rod Drift
Oil Temp Range:
100F to 120F
120F to 150F
150F + Spec:
Max Drift
1.26 inches
1.26 inches
1.26 inches Spec: Time Interval
5 minutes
2.7 minutes
1.7 minutes Actual Drift in Time Interval:
_______inches ________inches _______inches
2. Tilt Cylinder Speed Specification:
Actual Fully retracted to fully extended
2 seconds
________seconds Fully extended to fully retracted
2 seconds
________seconds Machine has ability to use blade, lift machine and hold for 15 seconds minimum.
Winch is able to pull machine 50 feet to dead-man while in neutral.
Date E-mailed / sent to D&FP
Dealer Representative
Machine identified by serial number received in good condition
Date Inspected
Signature of Government Inspector
Printed Name of Government Inspector
Stamp of Government Inspector Updated 30 Oct 14
815F RUN-IN TEST
Contract No. _______________________
Serial No. ___________________
Completed
In lieu of a field test or demonstration, the Government representative shall receive certification that the machine conforms to the following specifications:
_____ Parking brake operational _____ Backup alarm audible in reverse _____ All gauges operational
4. High idle
2395 +/- 60 rpm
5. Low idle
985 +/- 30 rpm
_____ Drive train test correct:
5. Torque converter outlet
70+/-10 psi
6. Speed clutch (PI) (Initial pressure) 80+/-5 psi
Speed clutch (PI) pressure (High idle) 380+/-20
3. Directional clutch (P2) (High idle) 55+/-8 psi
4. Oil Pump (High idle)
400+/-17 psi
5. Steering relief pressure
2500 +/- 50 psi
6. Lubrication system pressure (high idle) 10 psi min
_____ Implement system test correct:
1. Pilot system pressure
350 +/- 20 psi
2. Pressure Relief valve
2250 +/- 50 psi
3. Pressure control/selector relief
350 +/- 50 psi
Date E-mailed / faxed to D&FP
MILITARY CB-534B RUN-IN TEST
Contract No. _______________________
Serial No. ___________________
Completed
In lieu of a field test or demonstration, the Government representative shall receive certification that the tractor conforms to the following specifications:
_____ Parking brake operational _____ Backup alarm audible in reverse
6. High idle
2310 +/- 60 rpm
7. Low idle
750 +/- 10 rpm
_____ Propel test correct:
7. Propel Pump charge relief valve
360 +/- 20 psi
8. Reverse Main Relief Valve
6670 +/-200 psi
9. Forward Main Relief Valve
6670 +- 200psi
10. POR relief pressure
6090+/- 200psi
_____ Steering test:
1. Steering system pressure
2050 +/- 100 psi
_____ Vibratory system
1. POR relief pressure
4830+/- 100 psi
2. GP Relief Valve
3350+/- 100 psi
3. Charge pump relief pressure
360 +/- 20 psi
4. High Pressure relief
5300+/-100 psi
MILITARY CS-433C RUN-IN TEST
Serial No. ___________________
Completed
In lieu of a field test or demonstration, the Government representative shall receive certification that the tractor conforms to the following specifications:
_____ Parking brake operational _____ Backup alarm audible in reverse
8. High idle
2350 +/- 50 rpm
9. Low idle
1000 +/- 30 rpm
_____ Propel test correct:
11. Propel Pump charge relief valve
250 +/- 10 psi
12. Main relief valve
4600 to 5100 psi Drum
Axle ________
MILITARY CS-563D RUN-IN TEST
Serial No. ___________________
Completed
In lieu of a field test or demonstration, the Government representative shall receive certification that the tractor conforms to the following specifications:
_____ Parking brake operational _____ Backup alarm audible in reverse
10. High idle
2340 +/- 60 rpm
11. Low idle
800 +/- 10 rpm
_____ Propel test correct:
13. Propel Pump charge relief valve
335 +/- 15 psi
14. Relief Valve Piston Pump
6960 +/-250 psi
15. Relief Valve (Pressure Override)
6525 +- 200psi
_____ Steering test:
2. Steering system pressure
2750 +/- 45 psi
_____ Vibratory system
1. Main relief valve (High Amplitude) 5076+/- 435 psi
2. Main relief valve (Low Amplitude) 5076+/- 435 psi
3. Charge relief pressure (vibe off)
428 +/- 22 psi
4. Charge relief pressure (vibe on)
19+/-10 lower than vibe off
R:\MACHINE REPAIR WORKING DIR\TOOL BOX MACHINE REPAIR\DEUCE Run-In Test Updated 30OCT14.doc 9/23/2016
File details come from the government source that posted it. Updated .