Attachment 0005 Quality Assurance Survellance Plan (QASP).pdf
PDF 220 KB Posted
- Solicitation number
- W58RGZ26R0017
About this file
This is a Quality Assurance Surveillance Plan (QASP) for Contract W58RGZ-26-R-0017, an AH-64 Apache Sensor Portfolio Field Service Representative (CFSR) support contract managed by the U.S. Army Program Executive Office (PEO) Aviation and Apache Attack Helicopter Project Management Office (PM Apache) at Redstone Arsenal, Alabama. The QASP establishes systematic procedures for monitoring, inspecting, and evaluating contractor compliance with the Performance Work Statement (PWS) requirements for providing Original Equipment Manufacturer-level technical support for the Modernized Target Acquisition Designation Sight/Pilot Night Vision Sensor (M-TADS/PNVS) and Fire Control Radar (FCR) sensor suites on AH-64D/E Apache aircraft. The contract encompasses 9 full-time equivalent (FTE) baseline positions across five CONUS recurring operational stations (Redstone Arsenal, Fort Campbell, Fort Cavazos, Fort Drum, and Morrisville) and four OCONUS forward-stationed locations (Fort Wainwright/JBER Alaska, Camp Humphreys South Korea, Illesheim Germany, and Al Asad/Erbil Iraq), with provisions for overtime maintenance, surge support, and temporary duty (TDY) travel across designated CONUS and OCONUS dispatch locations.
The QASP implements eight performance requirement summary (PRS) metrics subject to surveillance and evaluation: technical inquiry response within one business day (≥95% compliance), AOG issue resolution within 3 business days for critical issues (≥95% compliance), CONUS deployment within 30 calendar days and OCONUS deployment within 60 calendar days (100% compliance), training and mentoring delivery with full documentation (100% compliance), monthly Certificate of Service reporting by the 7th calendar day with complete data elements (zero late submissions), overtime administration restricted to pre-approved emergency AOG and critical maintenance with zero unauthorized billing, and annual Service Contract Reporting to the System for Award Management (SAM) by October 31. Surveillance methodologies include 100% inspection of critical deliverables such as monthly CoS reports, mandatory deliverable timeliness, deployment reporting timelines, overtime invoicing, and security clearances; periodic sampling of training delivery and configuration tracking; validated customer feedback from Combat Aviation Brigades and depot personnel; and financial invoicing reconciliation. The Contracting Officer retains authority over contract interpretation, fee adjustments, modifications, and dispute resolution, while the Contracting Officer's Representative (COR) manages day-to-day technical administration and surveillance. Deficiency documentation procedures distinguish between minor discrepancies (requiring contractor acknowledgment and correction within two business days) and significant deficiencies (requiring formal Contract Discrepancy Reports with five-working-day response deadlines), with government evaluation authority to apply contractual remedies including payment withholding, re-performance at contractor expense, negative CPARS ratings, or cure notices. Performance is formally evaluated annually through the Contractor Performance Assessment Reporting System (CPARS) using ratings of Exceptional, Very Good, Satisfactory, Marginal, or Unsatisfactory based on objective metrics spanning quality of service, schedule timeliness, cost control, and management and regulatory compliance.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QUALITY ASSURANCE SURVEILLANCE PLAN (QASP)
AH-64 APACHE SENSOR PORTFOLIO (M-TADS/PNVS & FCR) CONTRACT
FIELD SERVICE REPRESENTATIVE (CFSR) SUPPORT
DATE: September 2026
SOLICITATION / CONTRACT NUMBER: W58RGZ-26-R-0017
PREPARED BY:
U.S. Army Program Executive Office (PEO) Aviation / Apache Attack Helicopter Project Management Office (PM Apache) Aviation and Missile Command (AMCOM) Logistics Center (ALC) Redstone Arsenal, Alabama 35898-5280
1. INTRODUCTION
This Quality Assurance Surveillance Plan (QASP) has been developed in accordance with Federal Acquisition Regulation (FAR) 46.4, Defense Federal Acquisition Regulation Supplement (DFARS) 246.4, and the requirements of Contract W58RGZ-26- R-0017.
This document establishes the systematic procedures and evaluation guidelines that the U.S. Army Aviation and Missile Command (AMCOM), Program Executive Office (PEO) Aviation, Apache Attack Helicopter Project Management Office (PM Apache), and assigned Contracting Officer’s Representatives (CORs) will employ in monitoring, inspecting, and evaluating Contractor Field Service Representative (CFSR) technical support services.
The QASP serves as a government-developed instrument ensuring that:
(a) The Contractor executes all tasks in accordance with the Performance Work Statement (PWS).
(b) The Government achieves required sensor readiness and operational availability across fielded AH-64D/E Apache fleets worldwide.
(c) Defective or non-conforming services are promptly identified, documented, and corrected.
(d) The Government pays only for acceptable, conforming services delivered within established contract ceilings.
2. PURPOSE OF THE QASP
The purpose of this QASP is to provide a structured surveillance framework for Government representatives to administer the AH-64 Apache Sensor CFSR PWS.
Specifically, this plan:
(a) Defines the performance objectives and specific work outputs evaluated under the contract.
(b) Establishes explicit Performance Standards and Acceptable Quality Levels (AQLs) aligned with Technical Exhibit A (Performance Requirements Summary) of the PWS.
(c) Details the surveillance methodologies, inspection frequencies, and audit protocols used by the Government.
(d) Outlines procedures for documenting contractor performance, managing customer complaints, issuing Contract Discrepancy Reports (CDRs), and executing Contractor Performance Assessment Reporting System (CPARS) annual evaluations.
3. ROLES AND RESPONSIBILITIES OF GOVERNMENT OFFICIALS
3.1 Contracting Officer (KO)
The KO is the only person authorized to enter into, administer, or terminate contracts, and make related determinations and findings on behalf of the Government. The KO is the sole individual who can legally bind the Government. The KO has ultimate authority over contract interpretation, fee adjustments, contract modifications, and formal dispute resolutions.
3.2 Contracting Officer’s Representative (COR)
The COR is formally designated in writing by the KO pursuant to DFARS 201.602-2.
The COR is responsible for technical administration, day-to-day surveillance, inspection, and verification of contractor work outputs. The COR’s key functions include:
(a) Performing routine inspections and audits in connection with contract performance.
(b) Maintaining detailed surveillance logs and reviewing all technical deliverables (including the Monthly Certificate of Service [CoS] CDRL A001 / DI-MGMT- 81238).
(c) Auditing and validating all Contractor travel requests and overtime billing hours against prior written authorizations and contract funding ceilings.
(d) Serving as the primary conduit for military customer feedback from supported Combat Aviation Brigades (CABs), depots, and aviation activities.
(e) Issuing written notifications of deficiency and recommending issuance of Contract Discrepancy Reports (CDRs) to the KO.
(f) Coordinating site access, Government-Furnished Property (GFP) availability, and Common Access Card (CAC) / Defense Information System for Security (DISS) clearances.
Note: The COR is not authorized to alter, modify, expand, or waive any terms, conditions, specifications, pricing, funding, or delivery schedules of the contract.
3.3 Unit Points of Contact / Functional Inspectors
Designated technical inspectors, military maintenance officers, Division Aviation Support Battalion (DASB) commanders, and aviation unit maintenance officers at supported CONUS and OCONUS operational stations provide supplemental surveillance and direct customer feedback to the COR regarding CFSR on-site responsiveness, diagnostic effectiveness, and over-the-shoulder mentoring quality.
4. SCOPE AND TYPES OF WORK TO BE SURVEILLED
The Contractor provides Original Equipment Manufacturer (OEM)-level CFSR technical support, hands-on troubleshooting, maintenance guidance, formal/informal training, and engineering reach-back for the Modernized Target Acquisition Designation Sight / Pilot Night Vision Sensor (M-TADS/PNVS) and Fire Control Radar (FCR) sensor suites installed on AH-64D/E Apache aircraft.
Surveillance encompasses performance across three distinct operational segments:
4.1 Primary Recurring Support Hubs (9 FTE Baseline)
(a) CONUS Recurring Operational Stations (5 FTEs):
1. Redstone Arsenal, AL (Baseline Hub / Engineering Reach-Back /
Programmatic Coordination) (1 FTE)
2. Fort Campbell, KY (101st Airborne Division / 160th SOAR) (1 FTE)
3. Fort Cavazos (Hood), TX (1st Cavalry Division) (1 FTE)
4. Fort Drum, NY (10th Mountain Division) (1 FTE)
5. Morrisville, NC (Army National Guard Aviation Facility) (1 FTE)
(b) OCONUS Forward-Stationed Hubs (4 FTEs):
1. Fort Wainwright / Joint Base Elmendorf-Richardson (JBER), AK (1 FTE)
2. Camp Humphreys / USAG Daegu, Republic of Korea (1 FTE)
3. Illesheim (Storck Barracks) / Katterbach Kaserne, Germany (1 FTE)
4. Al Asad Air Base / Erbil Air Base, Iraq (CENTCOM Area of Operations) (1
FTE)
4.2 Overtime Maintenance and Surge Support
Surveillance verifies that overtime labor is strictly confined to emergency Aircraft on Ground (AOG) restoration and critical maintenance surge missions pre-authorized in writing by the KO or COR, within the established 90-hour-per-technician planning threshold and contract funding limits.
4.3 Surge TDY Travel Execution
Surveillance monitors contractor compliance with Joint Travel Regulations (JTR), FAR 31.205-46, and approved Travel Authorization Requests (TARs) across designated CONUS dispatches (Bliss, Liberty/Bragg, Carson, Riley, Novosel/Rucker, Savannah, Eastover, Houston, West Jordan, CCAD, NTC) and forward OCONUS dispatches (Alaska, Hawaii, Korea, Germany, Kuwait, and CENTCOM operational sites).
5. SURVEILLANCE METHODOLOGIES
The Government will employ the following surveillance methods to evaluate Contractor compliance with PWS requirements:
5.1 100% Inspection
Used for critical outputs where non-conformance immediately impairs readiness, contract legality, or financial controls:
(a) Monthly Certificate of Service (CoS) Reports (CDRL A001): 100% review of all technical assistance entries, Field Data Reports (FDRs), prevented premature component removals, AvMC-approved Maintenance Engineering Calls (MECs), and publications discrepancy submittals (DA Form 2028).
(b) Mandatory Deliverables Timeliness: 100% verification of deliverable due dates against Technical Exhibit B (Deliverables Schedule).
(c) Deployment Reporting Timelines: 100% audit of reporting dates for CONUS (≤30 calendar days) and OCONUS (≤60 calendar days) personnel.
(d) Overtime Invoicing Audits: 100% audit of billed overtime hours against advance written authorizations and monthly CoS logs.
(e) Security & Clearances: 100% verification that all performing CFSRs maintain active SECRET clearances in DISS and mandatory security training certifications (AT Level I, Level I OPSEC, Cyber Awareness, PII, ATCTS).
5.2 Periodic Surveillance / Sampling
(a) Training and Mentoring Delivery: Periodic inspection of documented Theory of Operation training classes, attendee metrics, and over-the-shoulder mentoring sessions at supported flight and maintenance units.
(b) Configuration Tracking: Periodic verification that CFSR-maintained aircraft sensor configuration records match physical aircraft hardware and software baselines.
(c) Property Management Audits: Semi-annual inspections of Government Furnished Property (GFP), computer terminals, toolkits, and TMDE assigned to CFSR personnel.
5.3 Validated Customer Feedback
(a) Customer Feedback Channels: The COR will collect and log feedback from supported Combat Aviation Brigade (CAB) maintenance officers, Quality Assurance Representatives (QARs), and unit commanders regarding CFSR technical proficiency, diagnostic timeliness, and support availability.
(b) Customer Complaint Investigation: Any complaint received by the COR will be formally investigated. If substantiated, the COR will notify the Contractor in writing within one (1) working day and initiate corrective action protocols.
5.4 Financial and Manpower Invoicing Surveillance
(a) Invoice Auditing: Monthly reconciliation of submitted invoices against hours logged in the CoS, authorized travel expense claims under JTR, and pre-approved overtime logs.
(b) Service Contract Reporting: Verification of annual completion of labor hour entries in the System for Award Management (SAM SCR) by October 31.
6. PERFORMANCE REQUIREMENTS SUMMARY (PRS) SURVEILLANCE
MATRIX
Attachment 1 provides the complete surveillance matrix detailing the Performance Objectives, Standards, Acceptable Quality Levels (AQLs), Surveillance Methods, and Performance Evaluation Impacts.
7. DEFICIENCY DOCUMENTATION AND CORRECTIVE ACTION PROCEDURES
7.1 Identification of Deficiencies
When contractor performance deviates from the standards established in the PWS and QASP, the COR will determine whether the deficiency is minor or significant:
(a) Minor Discrepancy: A technical or administrative deviation that does not directly degrade mission readiness or weapon system availability (e.g., administrative error in a report, minor delay in a routine deliverable).
(b) Significant Deficiency: A condition that adversely affects fleet operational readiness, aircraft safety, security compliance, deployment schedules, or involves unauthorized financial billing / overtime expenditures.
7.2 Resolution of Minor Discrepancies
For minor discrepancies, the COR will contact the Contractor’s Program/Contract Manager verbally or via email. The Contractor shall acknowledge the discrepancy within twenty-four (24) hours and take immediate corrective action. If the minor discrepancy is corrected satisfactorily within two (2) business days, no formal negative rating is issued, but the incident is documented in the COR surveillance files.
7.3 Issuance of Contract Discrepancy Report (CDR)
For recurring minor deficiencies, any uncorrected deficiency, or any significant deficiency, the COR will issue a formal Contract Discrepancy Report (CDR) (DA Form 5479-R or agency equivalent) through the Contracting Officer:
(a) Government Issuance: The COR/KO issues Part A of the CDR detailing the specific PWS violation, objective standard failed, operational impact, and required response suspense date.
(b) Contractor Response: The Contractor shall provide a written response (Part B) within five (5) working days (or sooner if directed for critical AOG failures). The response must identify:
1. The root cause of the non-conforming performance.
2. Corrective action taken for the specific instance.
3. Preventative actions implemented to preclude recurrence.
4. Updated Quality Control Plan (QCP) procedures if systemic failure occurred.
(c) Government Evaluation: The KO and COR will evaluate the Contractor's response. The KO will accept or reject the corrective action plan and determine whether contractual remedies (e.g., invoice withholding, re-performance at contractor expense, negative CPARS rating, or cure notice) are warranted.
8. PERFORMANCE EVALUATION AND CPARS REPORTING
The Contractor's overall performance will be formally recorded at least annually in the Contractor Performance Assessment Reporting System (CPARS) IAW FAR 42.15. The evaluation ratings (Exceptional, Very Good, Satisfactory, Marginal, Unsatisfactory) will be directly supported by objective metrics collected under this QASP:
(a) Quality of Service: Evaluated against Technical Inquiry Response (PRS #1), Issue Resolution / AOG Support (PRS #2), Training Mentoring Delivery (PRS #5), Technical Data / DA Form 2028 Accuracy, and Prevented Premature Removals documentation.
(b) Schedule / Timeliness: Evaluated against CONUS/OCONUS Reporting Timelines (PRS #3 & #4), Timely Submission of Monthly CoS CDRL A001 (PRS #6), and adherence to Technical Exhibit B deliverable deadlines.
(c) Cost Control: Evaluated against compliance with Overtime Controls (PRS #7), containment of TDY travel expenses within JTR benchmarks, and zero unapproved labor billings.
(d) Management & Regulatory Compliance: Evaluated against active security clearances, DOCPER compliance in Germany, host-nation legal authorizations, property accountability, and annual SAM SCR reporting (PRS #8).
9. SIGNATURES AND APPROVALS
Submitted by:
Contracting Officer’s Representative (COR)
PEO Aviation / PM Apache
Date: ________________________
Approved by:
Contracting Officer (KO)
Army Contracting Command – Redstone (ACC-RSA)
Date: ________________________
ATTACHMENT 1: PERFORMANCE REQUIREMENTS SUMMARY (PRS)
SURVEILLANCE MATRIX
PRS Item /
PWS
Reference
Performance Objective
Performance Standard
Acceptable Quality Level
(AQL)
Method of Surveillanc e
Performance Impact /
CPARS
Incentive
PRS #1:
Technical Inquiry Response (PWS Para 5.2.1.2)
Deliver initial verbal/writte n response to operational unit and depot technical inquiries.
Provide initial response to unit technical inquiries within one (1) business day of receipt.
≥95% compliance;
no more than 1 discrepancy per month.
100% Review of Inquiry Logs / Monthly CoS / Unit Feedback
Exceptional:
≥99% timely response.
Satisfactory:
≥95% compliant.
Marginal/Uns at: <95% compliant;
results in
CDR.
PRS #2:
Issue Resolution
& AOG
Support (PWS Para 5.2.1.2)
Resolve field-level sensor system anomalies and critical AOG status.
Resolve critical AOG sensor issues within 3 business days;
resolve routine issues within 10 business days (or document formal escalation to
COR).
≥95% compliance across all handled technical cases.
Periodic Inspection / Customer Feedback / 100% Review of CoS AOG entries
Exceptional:
Zero aircraft grounded >3 days due to CFSR delay.
Satisfactory:
≥95% resolution within standards.
Unsat: <90% resolution;
CDR issued.
PRS #3:
Deployment Lead Times
(CONUS)
(PWS Para 5.2.1.3)
Provide rapid on-site
CFSR
reporting for
CONUS
operational locations.
Personnel must achieve on-site reporting within thirty
(30) calendar days of Task Order award or formal relocation
100% Compliance ; zero deviation from standard.
100% Inspection of Check-in Reports / Unit In- Processing Records
Exceptional:
On-site ≤20 days.
Satisfactory:
100% compliant at ≤30 days.
Marginal/Uns at: >30 days without KO waiver;
directive. invoice adjustment.
PRS #4:
Deployment Lead Times
(OCONUS)
(PWS Para 5.2.1.3)
Provide theater-cleared
CFSR
reporting for forward-stationed
OCONUS
locations.
Cleared, DOCPER/SP
OT-approved personnel must achieve on-site reporting within sixty
(60) calendar days of Task Order award.
100% Compliance ; zero deviation from standard.
100% Inspection of SPOT LOAs, APACS clearances, and arrival logs
Exceptional:
On-site ≤45 days.
Satisfactory:
100% compliant at ≤60 days.
Marginal/Uns at: >60 days;
immediate CDR issued.
PRS #5:
Training & Over-the- Shoulder Mentoring (PWS Para 5.2.2.1)
Conduct structured Theory of Operation and step-by-step fault isolation mentoring for military maintainers and aircrew.
Deliver mentoring starting with system MOCs; fully document all training sessions, attendee counts, MOS/roles, and instructional hours.
100% Compliance ; zero unverified or undocument ed training events.
Periodic Inspection / Review of CoS Training Entries / Customer Surveys
Exceptional:
Documented increase in unit organic maintenance self-sufficiency.
Satisfactory:
100% compliant documentatio n.
Marginal:
<95% compliance.
PRS #6:
Monthly Reporting (CoS CDRL A001) (PWS Para 5.2.3.1)
Submit comprehensi ve Certificate of Service (CoS) reports covering all
PWS
reporting elements.
Submit Monthly CoS report (DI-
MGMT-
81238) containing all 8 required data items no later than the 7th calendar day of each following month.
Zero unexcused late submissions ; 100% completenes s of mandatory data elements.
100% Inspection of monthly
CDRL
submittals
Exceptional:
Reports consistently early with flawless technical depth.
Satisfactory:
Submitted by 7th calendar day.
Marginal/Uns at: Late or missing data;
CDR.
PRS #7:
Overtime Administrati on & Controls (PWS Para 1.5.4.3)
Manage overtime labor hours strictly for authorized emergency AOG and critical surge maintenance
Overtime must be pre-approved in writing (≥7 days prior, or within 4 hrs for emergency
AOG);
restricted strictly to direct maintenance;
must not exceed authorized funding limits.
Zero unapproved overtime billings;
zero billing in excess of established funding ceilings.
100% Invoice Audit against advance
COR/KO
authorizatio ns and CoS logs
Satisfactory:
100% pre-authorized;
within budget.
Unsat: Any unauthorized or unapproved overtime billed;
rejected invoices.
PRS #8:
Service Contract Reporting
(SAM SCR)
(PWS Para 5.3.1)
Report all direct labor hours executed under the contract into the System for Award Managemen t (SAM).
Completely fill in all required labor hour and cost fields at www.sam.gov no later than October 31 of each year (or within 30 days of contract expiration).
100% Compliance ; zero unexcused missed reporting deadlines.
100% Verificatio n of SAM system confirmatio n report
Satisfactory:
Completed by October 31.
Unsat:
Failure to report by suspense date;
negative rating in
CPARS.
http://www.sam.gov/
ATTACHMENT 2: DELIVERABLE SURVEILLANCE & VERIFICATION
TRACKER
Deliverable Ref
Title / Requirement
PWS Para Standard Delivery Due Date
Surveillance Method
Responsible Evaluator
A.001 Quality Control Plan
(QCP)
1.5.1 Within 10 days
of contract award; changes 15 days prior
100% Review for completeness
KO and
COR
A.001A QCP Option Period Analysis
1.5.1.1 Within 30 days
of option / TO completion
100% Inspection of quality trends
COR
A.001B Performance Issues Report
1.5.1.2 Verbal: 4
hours; Written follow-up: 2 days
100% Inspection of response
COR
A.002 Contractor Work Plan
1.5.4.3.1 Within 10 days
of award;
changes 30 days prior
100% Technical Review
KO via
COR
A.003 / A.003A
Installation Pass Logs (Initial / Updated)
1.7.3.1 Initial: 3 days
post-award;
Updates:
within 5 days
100% Audit against personnel list
KO via
COR
A.003B / A.003C
Pass Retrieval (Departures / Termination)
1.7.3.2 / 3 Departures: 3 days; Contract end: 5 days
100% Accountability Verification
Issuing Office /
COR
A.004 / A.004A
Consolidated
CAC PII
Form & Log
1.7.3.4 PII: 10 days
post-award;
Log: 30 days post-award
100% Security Verification
COR
A.004B / A.004C
Background Check
1.7.4.1 Favorable: 5
days;
100% Audit against DISS
KO, COR,
Activity
Verifications Unfavorable:
within 24 hours
Mgr
A.004D Host-Nation Security Backgrounds
1.7.4.2 Within 5 days
of award / post-award conference
100% Inspection of permits
KO via
COR
A.005 Key Personnel CVs
1.11 Within 5
calendar days after contract award
100% Qualification Assessment
KO via
COR
A.006 Proposed Workspace Sign
1.13.1 Within 10
calendar days after contract award
100% Inspection
KO via
COR
A.007 Issued ID Badges Listing
1.13.2 Prior to
performance start; updated as changes occur
100% Physical Audit
KO via
COR
A.008 Signed Non- Disclosure Statements
1.19 No later than 5
days prior to work commencement
100% Verification of all staff
COR
A.009 OCI
Mitigation Plan
1.20 Within 5
calendar days of OCI identification
100% Legal & KO Review
KO via
COR
A.010 / A.010A
Accident Prevention Plan & Safety Proof
1.22.1 / 2 Prior to site start; local notices within 10 days
100% Safety Compliance Audit
KO via
COR
A.011– A.015
Mandatory Training Certifications
(AT,
1.24 Within 30 days
of onboarding (ATCTS within 10 days);
100% Verification against training
COR
OPSEC,
iWATCH, Cyber, PII, ATCTS) annual refreshers database
A.016 Property Management Plan
1.28 Within 30
calendar days of contract award
100% Property Audit
KO, COR,
Prop Admin
A.017 Monthly Certificate of Service (CoS)
5.2.3.1 Monthly, by
7th calendar day of following month
100% Technical Audit
KO and
COR
A.018 SAM Service Contract Report
5.3.1 Annually by
Oct 31; or 30 days after contract end
100% Verification on SAM.gov
KO via System
ATTACHMENT 3 – CONTRACT DISCREPANCY REPORT (CDR) WORKFLOW
1. DISCREPANCY IDENTIFIED
COR detects non-conformance exceeding established AQL via 100% inspection, periodic sampling, invoice audit, or validated unit complaint.
2. CLASSIFICATION & NOTIFICATION
* Minor Discrepancy: COR notifies Contractor verbally/email. Immediate re-performance or correction within 2 working days.
* Significant/Recurring Failure: COR drafts formal CDR and forwards to KO.
3. FORMAL CDR ISSUANCE (KO / COR)
Contracting Officer issues CDR Part A to Contractor specifying PWS / QASP| violation, operational impact, and response suspense date (≤5 working days).
4. CONTRACTOR ROOT CAUSE & CORRECTIVE ACTION (PART B)
Contractor submits written response detailing root cause analysis, specific resolution, and systemic preventative measures incorporated into QCP
5. EVALUATION & CONTRACTUAL DETERMINATION (KO / COR)
Government evaluates response adequacy. If acceptable, closure is tracked. If rejected or uncorrected, KO determines remedies (e.g., payment withhold, |re-performance at contractor cost, negative CPARS rating, or Cure Notice)
File details come from the government source that posted it. Updated .