Attachment 0004b - Relay Acceptance Test Procedures_FINAL.docx

DOCX document 2 MB Posted

Attached to
RFP for Integrated Battle Command System (IBCS) LRIP/FRP Federal contract opportunity
Solicitation number
W31P4Q-20-R-0015
Issued by
Department of the Army Materiel Command Contracting Command Redstone Arsenal

About this file

This document provides acceptance test procedures for the Integrated Fire Control Network Relay hardware and software integration. Key details include testing the relay's hardware initialization, operations, data harvesting and shutdown. Tests will demonstrate functionality of the relay and sensor and launcher interfaces. Additional test equipment used includes two radar interface units, two L2 simulated link boxes, and a government system integration laboratory real-time truth conductor. Pre-test setup includes grounding checks and powering on the relay and auxiliary equipment in sequence. Automated software initialization, air defense functionality with engagements, and software and hardware shutdown are all prescribed test procedures. Supporting documentation will provide instructions for operating test tools used in the relay acceptance testing.

View the file

Other files for this federal contract opportunity

Other files attached to RFP for Integrated Battle Command System (IBCS) LRIP/FRP, newest first.
File Type Posted
EXHIBIT A - CONTRACT DATA ITEM REQUIREMENTS LIST (CDRL) - 24NOV2020.pdf PDF
Exhibit C- IBCS DSL - 24NOV2020.docx DOCX document
Attachment 0002 - AIAMD System of Systems (SoS)(MIS-PRF-56500).pdf PDF
Attachment 0004d - Operator Procedures For IFMC GSIL.docx DOCX document
Attachment 0005 - Software Installation Instructions.docx DOCX document
Attachment 0008 - AIAMD IUID Plan Appendix A - IUID Candidates List Data Items.pdf PDF
Attachment 0009 - R and M Prediction Report.docx DOCX document
Attachment 0010a.3 – R003 KG-250X-FMECA.xlsx XLSX spreadsheet
Attachment 0010a.7 – R007 Relay Network Switch-Parvus Switch-FMECA.xlsx XLSX spreadsheet
Attachment 0010a.9 – R015 PDU Assembly-FMECA.xlsx XLSX spreadsheet
Attachment 0010a.13 – R031 Black Router--FMECA.xlsx XLSX spreadsheet
Attachment 0010c.3 – E048 HRFU-FMECA.xlsx XLSX spreadsheet
Attachment 0010c.8 – E053 Shelter Time Server-FMECA.xlsx XLSX spreadsheet
Attachment 0010c.9 – E059 Shelter Switch – 01-FMECA.xlsx XLSX spreadsheet
Attachment 0010d.7 – E153 RS112 Server -06 Shelter with PT-FMECA.xlsx XLSX spreadsheet
Attachment 0010d.8 – E153 RS112 Server -07 Shelter with PT-FMECA.xlsx XLSX spreadsheet
Attachment 0010e.9 – E147 – Table 3 Assembly-FMECA.xlsx XLSX spreadsheet
Attachment 0012 - Risk Management Plan.pdf PDF
Attachment 0013c - IBCS-A301-003 Vol II Instructor Guide_redacted.pdf PDF
Attachment 0013f - D-IBCS-0428-001_Delta_Software_SG_redacted.pdf PDF
Attachment 0013g - D-IBCS-0471_Delta2_Suppl_PE_redacted.pdf PDF
Attachment 0014 RevC - Technical Library.docx DOCX document
Attachment 0016 - Example Cage Code and Cognizant DCMA DCAA Information.xlsx XLSX spreadsheet
Attachment 0022a - CASS to PDRS.docx DOCX document
Attachment 0022a.1.e - ALH-215333 00 S-280 CASS INSTALLA.pdf PDF
Attachment 0022a.1.h - PL-ALH-211130 00 CABLE ASSEMBLY C.pdf PDF
Attachment 0022a.4 - CASS Task Purpose.v2.pptx PPTX presentation
Attachment 0025 - DD254.pdf PDF
Attachment 0010b.6 – E030 KVM Console-FMECA.xlsx XLSX spreadsheet
Attachment 0010a.5 – R005 SCIM-FMECA.xlsx XLSX spreadsheet
Attachment 0013i - D-IBCS-0473_Adv_NetMgr.pdf PDF
W31P4Q-20-R-0015- LRIP FRP - 25NOV2020.pdf PDF
Exhibit B - LRIP FRP TO 0001 DD1423 CDRLs_24NOV2020.pdf PDF
Attachment 0001 - IBCS LRIP FRP Statement of Work - 24NOV2020.docx DOCX document
Attachment 0010a.1 – R001 HRFU-FMECA.xlsx XLSX spreadsheet
Attachment 0010a.2 – R002 BPU-FMECA.xlsx XLSX spreadsheet
Attachment 0010a.6 – R006 TIMING UNIT-FMECA.xlsx XLSX spreadsheet
Attachment 0010a.12 – R030 PFPU SSHD-1—FMECA.xlsx XLSX spreadsheet
Attachment 0010a.14 – R032 Media Converter Module 11-FMECA.xlsx XLSX spreadsheet
Attachment 0010b.1 – E001 28VDC Pwr Supply Shelter Power-FMECA.xlsx XLSX spreadsheet
Attachment 0010b.10 – E034 R112 Shelter – Server Stack – 04-FMECA.xlsx XLSX spreadsheet
Attachment 0010c.6 – E051 IGRM-FMECA.xlsx XLSX spreadsheet
Attachment 0010c.11 – E061 Isolation Router Red-FMECA.xlsx XLSX spreadsheet
Attachment 0010c.12 – E062 Shelter Router-Red-FMECA.xlsx XLSX spreadsheet
Attachment 0010c.16 – E069 Media Converter 03 - FMECA.xlsx XLSX spreadsheet
Attachment 0010d.1 – E123 TMSS – ECU-FMECA.xlsx XLSX spreadsheet
Attachment 0010d.4 – E151 – Media Converter 04-FMECA.xlsx XLSX spreadsheet
Attachment 0010d.6 – E153 RS112 Server -05 Shelter with PT-FMECA.xlsx XLSX spreadsheet
Attachment 0010e.3 – E092 thru E101 Wkstn Display-FMECA.xlsx XLSX spreadsheet
Attachment 0010e.5 – E122 – EMI Tent PDU-FMECA.xlsx XLSX spreadsheet
Show all 50

RFP for Integrated Battle Command System (IBCS) LRIP/FRP has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

For Official Use Only Attachment 1 Integrated Battle Command System (IBCS) Integrated Fire Control Network Relay (IFCN) Acceptance Test Procedures – IFCN Relay 14 Jul 2020

For Official Use OnlyW31P4Q-20-R-0015
ATTACHMENT 0004b

For Official Use Only

IBCS-A248-001

18 April 2018

For Official Use Only Printed document is reference document only. Verify document date with on-line system.

Copyright 2020 Northrop Grumman Systems Corporation.

For Official Use Only Table of Contents

1. Scope1
1.1. IBCS IFCN Relay1
1.2. EOC Lite7
1.3. Additional Test Equipment9
2. Test Configurations10
2.1. Test Diagrams10
3. Pretest Setup10
3.1. Grounding10
4. Test Procedures11
4.1. Power On11
4.2. Automatic Software Initialization Checkout14
4.3. Air Defense Acceptance Test16
4.4. Software Shutdown and Data Harvest17
4.5. Hardware Shutdown23
5. Supporting Documentation for Relay ATP Execution24
5.1. Operator Instructions for Test Tools24

List of Figures

Figure 1‑1. IFCN V2 Relay2
Figure 1-2. Power Sub-System (PSS) & Battery3
Figure 1‑3. Network Enclosure Exterior View4
Figure 1‑4. Network Enclosure Interior View5
Figure 1‑5. Network Enclosure Signal & Power Panels6
Figure 1‑6. A-Side Interface Panel7
Figure 1-7. EOC Lite8
Figure 2-8. FT3 via Alt. Media10

List of Tables

Table 1-1. Additional Test Equipment9
Table 3-2. Grounding of Test Articles10
Table 4-3. Hardware Power Up11
Table 4-4. Automatic Software Initialization Check15
Table 4-5. Air Defense Functionality16
Table 4-6. Software Shutdown and Data Harvest17
Table 4-7. Hardware Shutdown23

Table 5-1. Test Tools and Associated Documentation ………………………………………… 24

For Official Use Only Scope The objective of this Acceptance Test Procedure (ATP) is to provide the detailed test steps necessary to demonstrate key functionality of the Integrated Fire Control Network Relay and to confirm conformity of integrated hardware and software end items with the qualified baseline. The qualified baseline is the successful integration of the IFCN Relay’s hardware and software.

Satisfaction of the following criteria shall constitute successful completion of the Acceptance Test (AT) process:

1. Hardware components shall exhibit no defects during In-process and Functional Check-Out (FCO).

2. After hardware and software integration, Information Assurance (IA) scans and analysis will be conducted to ensure the system is in compliance with applicable Information Assurance Vulnerability Alert (IAVA) and Security Technical Implementation Guide (STIG) requirements to ensure IA hardening and reduce cyber vulnerabilities.

3. Following IA scans, the IFCN Relay’s hardware initialization, operations, data harvesting, and shutdown shall be completed without functional failure and/or error In Accordance With (IAW) the procedures detailed in this ATP.

IBCS IFCN Relay The IFCN Relay features common hardware and software in a form factor that is intended to impose minimal impact to Air and Missile Defense (AMD) legacy platforms. The Plug and Fight (P&F) “B-Side” application layer interfaces with the appropriate “A-Side” Component Acquisition Program (CAP) adaptation layer for each particular weapon or sensor in the Army Integrated Fires Mission Command (AIFMC) System of Systems (ASoS). The IFCN Relay provides a mobile communications node that extends connectivity to remote launcher and sensor deployments by expanding the range of Line-of-Sight (LOS) communications over the horizon and around intervening terrain features.

The IBCS IFCN provides the framework to distribute fire control quality data, commands, and messages among IBCS Engagement Operations Centers (EOCs) and Plug & Fight enabled weapons and sensors. The IFCN consists of network components within the two Major End Items (MEIs), the EOC and IFCN Relay, and transport media used for voice, data, and video information exchanges between IBCS components.

The IFCN Relay is integrated on the IFCN Relay Platform (IRP) which is an IBCS-modified XM1061E1 Flat Bed Trailer that incorporates Non-Developmental-Items (NDIs), Commercial Off-The-Shelf (COTS), Government Furnished Equipment (GFE), and IBCS-developed Computer Software Configuration Items (CSCIs) within software builds (see Figure 1‑1 for an illustration).

Figure 1‑1. IFCN V2 Relay

The power distribution box on an IFCN relay (see Figure 1-2. Power Sub-System (PSS) & Battery) includes an A/C In circuit breaker that, when off, allows for connecting power to the Relay without putting power into the system. The D/C Out circuit breaker will also keep power from running to the system.

Figure 1-2. Power Sub-System (PSS) & Battery

The IFCN Network enclosure and the Plug & Fight Processing Unit (PFPU) are the heart of the IFCN relay. The network enclosure (see Figure 1-3. Network Enclosure Exterior View and Figure 1-4. Network Enclosure Interior View) contains the network equipment including switches, the Baseband Processing Unit (BPU) radio, the encryption device, and the GPS timing unit that drive the relay.

Figure 1‑3. Network Enclosure Exterior View

Figure 1‑4. Network Enclosure Interior View

During normal operations, the network enclosure remains closed due to environmental concerns. Thus there are signal entry panels for the network enclosure. The BPU radio connects to the Highband RF Unit (HRFU) on the mast of the EOC via an RF cable, a data/control cable, a power cable, and a ground back to the relay trailer (see Figure 1-5). Network Enclosure & Signal Entry Panel). These panels also house the PFPU connections.

Figure 1‑5. Network Enclosure Signal & Power Panels

The A-Side interface panel (see Figure 1-6. A-Side Interface Panel) contains the connections from the network enclosure to the different A-Sides that talk to IBCS. There is one sensor and eight launcher ports along with the black side Alt. Media Ports.

Figure 1‑6. A-Side Interface Panel

EOC Lite An EOC Lite (see Figure 1-7. EOC Lite) will be used as the C2 to test A-Side to A-Side communications during the Acceptance Test. An EOC Lite is operationally equivalent to an IBCS EOC but does not include tactical radios. Therefore, it cannot be used to test radio to radio communications nor does it check functionality of all the hardware components.

Figure 1-7. EOC Lite

Additional Test Equipment In addition to the EOC Lite, the following items are needed in order to meet the AT requirements as identified in the document.

Table 1-1. Additional Test Equipment

Item Description
Purpose
Part Number
2x Real Time Digital Radar Interface Unit (RIU) RTDRIU and Virtual Engagement Simulation Tool (VEST)
To track and act as an uplinking sensor and missile fly out model.
Launcher on the Net (LOTN)
To act as the Enhanced Launcher Electronics System (ELES) and tell the missile fly out model to fly the missile.
2x L2
A simulated LINK box that is hosted on a VM that connects the launcher to the B-Side.
Network, System Integration, and Test Environment (NSITE)
A test asset that shows the Distributed Interactive Simulation (DIS) on a map in order to verify that the targets are being displayed properly on Common Warfighter Machine Interface (CWMI).
Government System Integration Laboratory (GSIL) Real Time Truth Conductor (GRTTC)
A DIS player that outputs a scenario to the sensor models and destroys targets depending on the kill Protocol Data Units received.
10x TFOCA-II Cables
These cables will be used to connect the launchers and sensor from the test tool rack to the Unit Under Test (UUT).

Test Configurations Test Diagrams

Figure 2-8. FT3 via Alt. Media

Pretest Setup Grounding The following steps should be taken prior to powering up any equipment to ensure proper a common ground is established to prevent any harm to equipment damage.

Table 3-2. Grounding of Test Articles

Step #
Operator Actions
Expected Results
Actual Results
Comments/TIR #

Verify Test Articles Grounding

****CAUTION****

Prior to connecting commercial shore power or applying power to the EOC systems, verify by visual inspection that all equipment has been properly grounded and thresholds are IAW MIL-STD-464A, dated, 19 December 2002, to ensure proper operation and prevent an electrical hazard for the equipment or operator. The thresholds are 10 mOhms or less for inside the shelter and 20 mOhms or less for outside the shelter.

Relay HW is ground to a common facility ground

1.
Verify Main circuit breaker on UUT Relay is OFF
Relay main circuit breaker is OFF.
2.
Verify UUT Relay ground is connected to earth ground via cable (ALH-213925-0180)

Relay is grounded to common ground

Test Procedures Power On

Table 4-3. Hardware Power Up

Step #
Operator Actions
Expected Results
Actual Results
Comments/TIR #

Verify UUT per Hardware Connections for Test Configuration (See Error! Reference source not found.)

****CAUTION****

Verify by visual inspection that all equipment has been properly grounded to ensure proper operation and prevent an electrical hazard for the equipment or operator. See grounding steps below.

Relay HW is ground to a common facility ground

1.
Verify Battery Main circuit breaker is OFF (see Figure 1‑1. IFCN V2 Relay & Figure 1-2. Power Sub-System & Battery)
PSS Battery is OFF
QA witness
2.
Verify AC input circuit breaker on the PSS is OFF (see Figure 1‑1. IFCN V2 Relay & Figure 1-2. Power Sub-System & Battery)
PSS AC input is OFF
QA witness
3.
Verify output switch on the PSS is OFF (see Figure 1‑1. IFCN V2 Relay & Figure 1-2. Power Sub-System & Battery)
PSS DC output is OFF
QA witness
4.
Verify circuit breakers 1-5 on the UUT Relay Network Enclosure are in the OFF position (see Figure 1‑3. Network Enclosure Exterior View)
CB1 through CB5 in the OFF position
QA witness
5.
Verify PFPU on/off switch is in the OFF position
PFPU ON/OFF switch is in the OFF position
QA witness
6.
Verify SSD1 and SSD2 are installed in the PFPU. If not, install them at this time using ESD procedures.

NOTE: ESD procedures require the operator to wear a wrist strap with the clip end connected to a ground point. HDD / SDD are to be stored in anti-static bags when not installed. Drives should never have direct contact with a metal safe drawer, even if in an anti-static bag.

SSDs are installed in the PFPU
QA witness
7.
On Relay visually verify facility (building) ground to trailer ground point
Ground connected
QA witness
8.
On Relay visually verify PFPU ground to trailer ground point (see Figure 1‑1. IFCN V2 Relay)
Ground connected
QA witness
9.
On Relay visually verify HRFU ground to Network Enclosure (see Figure 1‑1. IFCN V2 Relay)
Ground connected
QA witness
10.
On Relay visually verify Network Enclosure ground to trailer ground point
Ground connected
QA witness
11.
On Relay visually verify power generation to trailer ground point (see Figure 1‑1. IFCN V2 Relay)

· Two grounds from PSS to trailer ground point

· One ground from Generator to trailer ground point

Grounds connected
QA witness
12.
Verify External GPS antenna is connected to Network Enclosure J12 (GPS) (see Figure 1‑5. Network Enclosure Signal & Power Panels)
GPS antenna connected
QA witness
13.
Verify on Network Enclosure J9 (HRFU ANT) connected to HRFU J2 using HRFU RF cable (see Figure 1‑5. Network Enclosure Signal & Power Panels)
Cables secure
QA witness
14.
Verify on Network Enclosure J8 (HRFU CTRL) connected to HRFU J3 using HRFU CTRL cable (see Figure 1‑5. Network Enclosure Signal & Power Panels)
Cables secure
QA witness
15.
Verify on Network Enclosure J14 (HRFU PWR) connected to HRFU J1 (see Figure 1‑5. Network Enclosure Signal & Power Panels)
Cables secure
QA witness
16.
Verify on Network Enclosure J15 (J15 PFPU Power) connected to PFPU J1 (PFPU PWR / J1) (see Figure 1‑5. Network Enclosure Signal & Power Panels)
Cables secure
QA witness
17.
Verify on Network Enclosure J13 (PFPU LAN) connected to PFPU J2 using PFPU J2 / PFPU LAN J13 cable (see Figure 1‑5. Network Enclosure Signal & Power Panels)
Cables secure
QA witness
18.
Verify on Network Enclosure J10 connected to A-side interface panel J1 Sensor (see Figure 1‑5. Network Enclosure Signal & Power Panels)
Cables secure
QA witness
19.
Verify on Network Enclosure J11 connected to A-side interface panel J2-6 Launchers (see Figure 1‑5. Network Enclosure Signal & Power Panels)
Cables secure
QA witness
20.
Verify on Network Enclosure J16 connected to A-side interface panel J7-8 Alt Media 1 and 2 (see Figure 1‑5. Network Enclosure Signal & Power Panels)
Cables secure
QA witness
21.
On Relay verify Power Sub-System (PSS) connected to commercial / external power source via PSS J1 AC Input (see Figure 1‑1. IFCN V2 Relay and Figure 1-2. Power Sub-System & Battery).
External power connected and available to IFCN Relay
QA witness
22.
Switch battery output to ON (see Figure 1‑1. IFCN V2 Relay & Figure 1-2. Power Sub-System & Battery)
Battery is providing power to PSS and DC volt meter reads 28 VDC
QA witness
23.
On Relay PSS do the following (see Figure 1‑1. IFCN V2 Relay & Figure 1-2. Power Sub-System & Battery):

· Switch AC INPUT to ON

· Switch OUTPUT switch to ON

Relay PSS is providing power to sub-components
QA witness

Configure KG-250

****WARNING****

Ensure KG-250X has been loaded with appropriate test keys prior to performing test. Check the latest configuration documentation to verify that the KG-250X has been loaded with the correct keys.

1.
Verify serial number of its associated Relay key and KG-250X match.

CIK must be provisioned SECRET before use

KG-250X and key match
QA witness
2.
If CIK key is not inserted in the UUT

Insert the correct Crypto Ignition Key (CIK) into the KG-250X and press KG-250X POWER button Wait until the ALARM LED extinguishes and the PWR/READY LED turns green.

KG-250X is ON and PWR/READY LED illuminates green
QA witness
3.
If KG-250 READY LED does not turn green in 5 minutes press RESET on KG-250
KG-250 resets, TC see red side, Green light will appear on KG-250
QA witness

Turn PFPU On

4.
Turn PFPU on/off switch to the ON position
PFPU ON/OFF switch is in the ON position
QA witness

Automatic Software Initialization Checkout

Table 4-4. Automatic Software Initialization Check

Step #
Operator Actions
Expected Results
Actual Results
Comments/TIR #

Test Configuration:

Figure 2-3. FT3 via Alt Media

Check OpenSAF Status on IFCN Relay

1.
If Relay is not powered on perform steps in Table 4-3. Hardware Power Up. (Steps 1 – 20 can be skipped if already performed on this UUT.)
Relay is powered on.
QA witness
2.
From an EOC Lite Operator Workstation remote into Relay UUT by doing the following:

· Right click on desktop

· Click on Open Terminal

· Type ssh localadmin@<IPv6 address of relay>

· Enter password

NOTE: UUT IPv6 addresses and passwords are unique and will be provided separately prior to testing.

Operator is remotely logged in to the relay.
QA witness
3.
Change directory to the location of the startup scripts by doing the following:

· Type cd /opt/integ/tools

Current directory is changed to the necessary location for scripts.
QA witness
4.
Verify IBCS software is running on IFCN Relay by doing the following:

· Type ./statusIBCS All services show INSTANTIATED / IN-SERVICE / ENABLED

IBCS software is running. Record initial IBCS status.

IBCS Status

QA witness

5.
If IBCS software is not running do the following to stop IBCS:

· Type ./stopIBCS

· Type watch ./statusIBCS

· Type ctrl + c after services have stopped

All services show UNINSTANTIATED / OUT-OF-SERVICE / DISABLED
QA witness
6.
If previous step was performed then do the following to start IBCS software:

· Type ./startIBCS

· Type watch ./statusIBCS

· Type ctrl + c after services have started All services show INSTANTIATED / IN-SERVICE / ENABLED

OpenSAF is now running QA witness

Air Defense Acceptance Test

Table 4-5. Air Defense Functionality

Step #
Operator Actions
Expected Results
Actual Results
Comments/TIR #

Test Configuration: Figure 2-8 FT3 via Alt Media

Start FT3 Test

NOTE: IBCS software must be installed to complete this test.

NOTE: Operator Procedures needed for Test Tools are listed in Reference Section

1.
Verify all test tools are started.
2.
Verify connectivity between UUT and EOC Lite by pinging between the two units.
3.
Start EOC Lite and UUT software.
4.
Log in to roles on CWMI on EOC Lite.
5.
Edit and activate the FT3 ATP Defense plan.
6.
Start 2 RIUs and 8 launchers.
7.
Bring 2 RIUs to radiate.
8.
Emplace all launchers.
9.
Bring PAC2 launchers to remote active.
10.
Verify IES is forwarding to ADSI.
11.
Start GRTTC Scenario 1207-11
12.
EOC operator on EOC Lite CWMI commit on ABT and TBM.
13.
Verify shots against ABT and TBM and kills.

QA witness

14.
After scenario finishes, take PAC2’s to remote standby. Take PAC3’s to remote active.
15.
Start GRTTC Scenario 1207-11
16.
EOC operator on EOC Lite CWMI commit on ABT and TBM.
17.
Verify shots against ABT and TBM and kills.

QA witness

18.
After scenario finishes, take PAC3’s to remote standby. Take MSE’s to remote active.
19.
Start GRTTC Scenario 1207-11
20.
EOC operator on EOC Lite CWMI commit on ABT and TBM.
21.
Verify shots against ABT and TBM and kills.

QA witness

22.
After scenario completes, harvest EOC data.
23.
Execute end of test procedures.

Software Shutdown and Data Harvest Table 4-6. Software Shutdown and Data Harvest

Step #
Operator Actions
Expected Results
Actual Results
Comments/TIR #

SHUTDOWN – Shutdown IBCS Software on IFCN Relay

1.
Remotely log on to the Relay by doing the following:

· Right click on desktop

· Click on Open Terminal

· Type ssh –X –o ‘ServerAliveInterval=60’ localadmin@<IPv6 address of relay>

· Enter password

Operator is remotely logged into the IFCN Relay
QA witness
2.
Verify IBCS software is shut down by doing the following in the terminal window:

· Type cd /opt/integ/tools

· Type ./stopIBCS

· Type watch ./statusIBCS

· Type ctrl + c after services have stopped

All CIs should show status as being UNINSTANTIATED and OUT-OF-SERVICE.
QA witness

Harvest Logs on Relay

3.
Harvest data by doing the following on the test operator workstation terminal window:

· Type ssh –X –o ‘ServerAliveInterval=60’ localadmin@<RelayIPv6Address>

· Enter password

· Type cd /opt/integ/tools

· Type ./runHarvester –A –d <relay_harvest_archive_name>

· Type cd /data_local/logs

· Type ls –al

· Type cd <relay harvest archive directory name>

· Type ls –al

· Type md5sum <relay_harvest_archive_name.tar> > <relay_harvest_archive_name.tar.md5>

NOTE: Replace <relay_harvest_archive_name> with “MEI#_ Relay_[yyyymmdd]_ATP#”

UUT data is harvested and md5 checksum created

Message “Harvest has completed successfully and is stored at, <archive_name>” received QA witness

Archive Relay Test Results

4.
Transfer files from Relay to bs1 by doing the following in the terminal window:

· Type ssh –X –o ‘ServerAliveInterval=60’ bs1

· Type cd /data_local/logs/

· Type scp -r localadmin@[<relay IP address>]:/data_local/logs/<MEI Archive Name> .

IFCN Relay harvest archive is transferred to the data directory of the EOC Lite
QA witness
5.
Transfer files from bs1 to storage by doing the following in the terminal window:

· Type ssh –X –o ‘ServerAliveInterval=60’ security

· Type cd /mnt/DataTransfer/Data/<MEInumber> (add “/dryRun” if harvest is from a dry run)

· Type scp -r username@bs1:/data_local/logs/<MEI#_Acceptance_Test Relay_[yyyymmdd]_Run#> .

IFCN Relay harvest archive is transferred to the data directory of the EOC Lite
QA witness
6.
Check the integrity of the data harvest check sum by doing the following in the terminal window in security:

· Type cd /mnt/DataTransfer/Data/<MEInumber> (add “/dryRun” if harvest is from a dry run)

· Type cd <relay_harvest_archive_name>

· Type sudo chmod 775 *

· Type md5sum –c <relay_harvest_archive_name>.md5

Command returns Ok
QA witness

Clean Logs on Relay

7.
Clean the IFCN Relay logs by doing the following in the terminal window:

· Type ssh –X –o ‘ServerAliveInterval=60’ localadmin@<RelayIPv6Address>

· Enter password

· Type cd /opt/integ/tools

· Type ./cleanLogs –b

· Close terminal window

NOTE: At the completion of the harvest, the script will indicate if the harvest was successful and the clean may be performed, or if errors occurred that require attention.

IFCN Relay log directories are cleaned
QA witness

Shutdown IBCS Software on EOC Lite

8.
Stop IBCS software on the EOC LITE by doing the following in the terminal window:

· Type ssh bs1

· Type cd /opt/integ/tools

· Type ./stopIBCS

· Type watch ./statusIBCS

· Type ctrl + c after services have stopped

All CIs should show status as being UNINSTANTIATED and OUT-OF-SERVICE.
QA witness
9.
Stop IBCS B-side software on the EOC LITE by doing the following in the terminal window:

· Type ssh bs1

· Type cd /opt/integ/tools

· Type ./stopBside

· Type watch ./statusBside

· Type ctrl + c after services have stopped

All CIs should show status as being UNINSTANTIATED and OUT-OF-SERVICE.
QA witness

Harvest Logs on EOC LITE

10.
Change the permissions on all print screens shots by doing the following on the test operator workstation ST2:

· Right click on desktop

· Click on Open Terminal

· Type cd /data_local/logs/ibcs/ui/iuicli

· Type sudo chmod 775 *.png

· Type sudo chown root:ibcs *.png

· Type ls –al

Screen shots are in the correct directory and have the correct permissions
QA witness
11.
Harvest data by doing the following on the test operator workstation:

· Type ssh –X –o ‘ServerAliveInterval=60’ bs1

· Type cd /opt/integ/tools

· Type ./runHarvester –d <EOC LITE_harvest archive name>

· Type ./runHarvester –A –d <EOC LITE_harvest archive name>

NOTE: Replace <EOC LITE_harvest archive name> with “MEI#_EOC LITE_[yyyymmdd]_ATP#

NOTE: At the completion of the harvest, the script will indicate if the harvest was successful and the clean may be performed, or if errors occurred that require attention.

EOC LITE data is harvested
QA witness
12.
Check the integrity of the data harvest check sum by doing the following:

· Type cd /data_local/logs/<EOC LITE_harvest archive name>

· Type md5sum –c <EOC LITE_harvest archive name>.tar.md5

Command returns OK
QA witness

Archive EOC LITE Test Results

13.
Copy test result file and md5 checksum files to the data archive by doing the following on an operator workstation:

· Right click on desktop

· Click on Open Terminal

· Type ssh –X –o ‘ServerAliveInterval=60’ security

· Type cd /mnt/DataTransfer/Data/(MEI Number)

· If this is a test dry run then type ls -al

· If a dryRun subdirectory does not exist then type mkdir dryRun

· Type cd dryRun

· Type scp –r username@bs1/data_local/logs/<EOC LITE_harvest archive name> .

Test data copied to archive location
QA witness
14.
Check the integrity of the data harvest check sum of the EOC LITE harvest by doing the following:

· Type ssh security

· Type cd /mnt/DataTransfer/Data/(MEI Number)

· If this is a test dry run then type cd dryRun

· Type cd <EOC LITE_harvest archive name>

· Type md5sum <EOC LITE_harvest archive name>.tar> > <EOC LITE_harvest archive name>.tar.new.md5

· Type diff <EOC LITE_harvest archive name>.tar.md5 <EOC LITE_harvest archive name>.tar.new.md5

New and original md5 sum files have identical values.
QA witness

Clean Logs on EOC LITE

15.
Clean the EOC LITE logs by doing the following in the BS1 Terminal Window:

· Type cd /opt/integ/tools

· Type ./cleanLogs –b

EOC LITE log directories are cleaned
QA witness

Hardware Shutdown

Table 4-7. Hardware Shutdown

Step #
Operator Actions
Expected Results
Actual Results
Comments/TIR #

SHUTDOWN

1.
Turn ON/OFF switch on PFPU to the OFF position
PFPU OFF
QA witness
2.
Turn KG-250 OFF by pressing the Power button
KG-250 OFF
QA witness
3.
Turn BPU to Standby
BPU in Standby mode
QA witness
4.
On the front panel of the IFCN Relay place the 5 breakers in the OFF position (down) according to the following sequence: (see Figure 1‑3. Network Enclosure Exterior View for breaker location)

1- PFPU (CB2)

2- HRFU (CB3)

3- Power Distribution Unit (PDU)(CB1)

4- MAIN (CB5)

UUT is powered OFF

QA witness

5.
Turn OFF Output switch
PSS DC Output OFF
QA witness
6.
Turn OFF AC Input
PSS AC Input OFF
QA witness
7.
Turn OFF Battery Main
PSS Battery OFF
QA witness
8.
Record PFPU Run Time Meter
PFPU Run Time Meter recorded
QA witness
9.
Secure UUT by doing the following:

· Remove SSD hard drives from the PFPU

· CIK from KG-250X in Network Enclosure

· Secure material in safe

NOTE: ESD procedures require the operator to wear a wrist strap with the clip end connected to a ground point. HDD / SDD are to be stored in anti-static bags when not installed. Drives should never have direct contact with a metal safe drawer, even if in an anti-static bag.

CIK & SSD hard drives are removed and secured
QA witness

Supporting Documentation for Relay ATP Execution Operator Instructions for Test Tools The IFCN Relay ATP uses test tools during its execution. The test tools simulate components (e.g., radars and sensors) that are in the IFMC architecture. The document that explains how to set up and operate these test tools is named Operator Procedures For the Integrated Fires Mission Command (IFMC) Government System Integration Laboratory (GSIL) and will be provided as an attachment named “Operator Procedures For IFMC GSIL”.

image2.png image3.png image4.png image5.png image6.png image7.emf image8.PNG image9.PNG image1.wmf

File details come from the government source that posted it. Updated .