Attachment 0003 - Davis Bacon Wage Deteremination.pdf

PDF 95 KB Posted

Attached to
CSS 10967 Install Generator & ATS - Johnstown, PA Federal contract opportunity
Solicitation number
W15QKN-20-Q-5301
Issued by
Department of the Army Materiel Command Contracting Command Picatinny Arsenal

View the file

Other files for this federal contract opportunity

Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

"General Decision Number: PA20200080 07/03/2020

Superseded General Decision Number: PA20190080

State: Pennsylvania

Construction Type: Building

County: Cambria County in Pennsylvania.

BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.80 for calendar year 2020 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January

1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.80 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year

2020. If this contract is covered by the EO and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must pay workers in that classification at least the wage rate determined through the conformance process set forth in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate,if it is higher than the conformed wage rate). The EO minimum wage rate will be adjusted annually. Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the

Davis-Bacon Related Acts, including those set forth at 29 CFR

5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date

0 01/03/2020

1 01/10/2020

2 06/05/2020

3 06/19/2020

4 07/03/2020

* ASBE0023-008 06/29/2020

Rates Fringes

ASBESTOS WORKER/HEAT & FROST

INSULATOR - MECHANICAL (Duct, Pipe & Mechanical System

Insulation)......................$ 34.80 27.96

BOIL0154-003 01/01/2017

BOILERMAKER......................$ 40.90 27.27

BRPA0009-011 12/01/2019

TILE FINISHER....................$ 26.00 15.86

TILE SETTER......................$ 31.91 20.24

BRPA0009-044 06/01/2020

BRICKLAYER (Including

Pointing, Caulking, Cleaning)....$ 31.16 20.18

MASON - STONE....................$ 31.16 20.18

CARP0142-015 06/01/2018

CARPENTER (Scaffold Building and Floor Laying-Hardwood

Only)............................$ 33.75 17.03

CARP0443-004 06/01/2020

MILLWRIGHT.......................$ 41.68 19.97

CARP0900-007 06/01/2018

CARPENTER (Includes

Acoustical Ceiling

Installation, Batt

Insulation, Drywall Hanging, Metal Stud Installation, Floor Laying-Carpet and

Vinyl, Form Work and Gutter

Installation; Excludes

Scaffold Building and Floor

Laying-Hardwood Floors.).........$ 28.51 15.23

ELEC0005-014 12/22/2019

ELECTRICIAN (Includes Alarm

Installation, Installation of

Sound and Communication

System and Low Voltage

Wiring; Excludes HVAC

Temperature Control

Installation)....................$ 42.61 27.19

* ENGI0066-041 07/01/2014

POWER EQUIPMENT OPERATOR

Backhoe/Excavator/Trackhoe, Bulldozer, Crane* Loader, Mechanic....................$ 28.37 15.66

Bobcat/Skid Steer/Skid

Loader, Drill, Gradall, Grader/Blade, Paver

(Asphalt, Aggregate, and

Concrete)...................$ 32.59 18.10

Hoist, Pump.................$ 28.36 18.10

Oiler.......................$ 23.35 15.66

Roller......................$ 25.20 15.66

*Add to Crane rate:

Booms 101-150 jibs- Add $.50

Booms 151-200 jibs- Add $1.00

Booms 201-251 jibs- Add $1.50

IRON0003-022 06/01/2020

IRONWORKER

Ornamental, Reinforcing, Rigger, Structural..........$ 37.29 32.40

LABO0125-005 06/01/2014

LABORER

Mason Tender -

Cement/Concrete.............$ 24.34 9.75

LABO0824-002 01/01/2020

LABORER (Mason Tender-Brick).....$ 21.56 17.05

PAIN0057-035 06/01/2017

PAINTER (Brush, Roller, and

Spray Only)......................$ 26.98 15.65

PAINTER (Drywall

Finishing/Taping Only)...........$ 27.80 18.75

PAIN0751-002 09/01/2019

GLAZIER..........................$ 23.55 20.57

PLAS0526-015 06/01/2019

CEMENT MASON/CONCRETE FINISHER...$ 31.27 19.39

PLAS0526-025 06/01/2019

PLASTERER........................$ 28.29 10.97

PLUM0354-009 06/01/2017

PLUMBER (Industrial).............$ 37.88 22.90

PLUM0520-018 05/01/2020

PIPEFITTER.......................$ 37.52 28.04

* SHEE0012-012 07/01/2020

SHEET METAL WORKER (HVAC Duct

Installation Only)...............$ 37.96 28.05

* UAVG-PA-0019 01/01/2019

SPRINKLER FITTER (Fire

Sprinklers)......................$ 38.16 21.93

SUPA2011-038 08/20/2014

ELECTRICIAN (HVAC/Temperature

Controls Installation Only)......$ 34.86 18.55

LABORER: Common or General......$ 17.53 10.02

OPERATOR: Forklift, All Types....$ 23.69 13.13

PLUMBER (HVAC Pipe

Installation Only)...............$ 30.44 18.73

PLUMBER, Excludes HVAC Pipe

Installation and Work on

Industrial Sites.................$ 30.14 18.83

ROOFER, Excludes Waterproofing...$ 33.50 20.66

ROOFER: Waterproofing Only.......$ 29.50 21.10

SHEET METAL WORKER, Excludes

HVAC Duct Installation...........$ 31.38 19.73

TRUCK DRIVER: Dump Truck........$ 23.36 7.60

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the

Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses

(29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate

(weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or

""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010

08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour

Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the

Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the

Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations

Wage and Hour Division

U.S. Department of Labor

200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator

(See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator

U.S. Department of Labor

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative

Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board

U.S. Department of Labor

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION"