This is a Contractor Price Breakdown Form that serves as the primary cost submission template for a firm-fixed-price construction solicitation. Offerors must complete this form to submit their pricing for CLIN 0001 associated with the renovation of common areas in Building 209 at Fort Hamilton, NY. The form is structured in five sections requiring detailed cost buildup: Section 1 captures direct labor costs broken down by trade category (HVAC Mechanic/Pipefitter, Painter/Surface Prep, Plumber, General Laborer, and Site Superintendent) with estimated hours and fully burdened hourly rates that must meet or exceed Davis-Bacon Act wage determination minimums; Section 2 itemizes direct materials including HVAC equipment, water source heat pumps, paint and primer materials, cove base, blackout shades, urinals, and shower curtains; Section 3 addresses equipment and rental costs for items such as scaffolding, lifts, and specialized HVAC handling equipment; Section 4 accounts for any subcontractor costs with required detailed buildup upon Government request; and Section 5 summarizes total direct costs and applies overhead, general and administrative (G&A), profit, and bonds and insurance to arrive at the grand total fixed price.

Offerors must certify that all proposed labor rates comply with mandatory Davis-Bacon Act wage determination minimums. The solicitation is a 100% small business set-aside with an estimated project value between $100,000 and $250,000, utilizing a firm-fixed-price purchase order contract type with a performance period of 120 calendar days from receipt of the Notice to Proceed. The contract administration sequence requires submission of Performance and Payment Bonds within 10 calendar days of award in accordance with FAR requirements.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 1 DIRECT LABOR

ATTACHMENT 0003 – CONTRACTOR COST BREAKDOWN FORM
Solicitation Number: W15QKN-26-Q-1BNR
Project Title: Renovation of Common Areas, Single Soldier UPH, Building 209, Fort Hamilton, NY
Offeror Name: _______________________________________
CAGE Code: __________________
INSTRUCTIONS: Offerors must complete this form (or provide a substantially similar spreadsheet) to detail the buildup of their Firm-Fixed-Price offer for CLIN 0001. All labor rates must meet or exceed the mandatory minimums established in the attached Davis-Bacon Act Wage Determination.
Provide a breakdown of the labor categories, estimated hours, and fully burdened labor rates required to complete the SOW.
Labor Category / TradeEst. HoursBase Hourly Rate (per Wage Det.)Fringe RateFully Burdened Hourly RateTotal Labor Cost
HVAC Mechanic / Pipefitter$$$$
Painter / Surface Prep$$$$
Plumber$$$$
General Laborer$$$$
Site Superintendent$$$$
[Add rows as needed]$$$$
TOTAL DIRECT LABOR:$

SECTION 2 DIRECT MATERIALS

Provide an itemized list of the major materials and fixtures required by the SOW.
Material Description / ItemQuantityUnitUnit CostTotal Material Cost
4-Ton Split Unit Air Conditioner1EA$$
Water Source Heat Pumps (as specified)EA$$
Paint, Primer, and Prep Materials1LOT$$
Cove Base and AdhesivesLF/LOT$$
Blackout Shades / BlindsEA$$
Urinal and Plumbing Hardware1EA$$
Shower Curtains and RodsEA$$
[Add rows as needed]$$
TOTAL DIRECT MATERIALS:$

SECTION 3 EQUIPMENT & RENTALS

Provide a breakdown of proposed equipment (owned or rented) necessary to complete the SOW.
Equipment Type / DescriptionQuantityDays/Hours RequiredRate (Daily/Hourly)Total Equipment Cost
Scaffolding / Lifts (for ceiling work)$$
Specialized HVAC handling equipment$$
General construction tools/vehicles1LOT$$
[Add rows as needed]$$
TOTAL EQUIPMENT:$

SECTION 4 SUBCONTRACTOR COSTS

If utilizing subcontractors, provide the total estimated cost for their portion of the work. (Note: The Prime Contractor must still provide a detailed buildup of these costs upon Government request).
Subcontractor NameTrade / Scope of Work PerformedTotal Subcontract Cost
$
$
TOTAL SUBCONTRACTOR COSTS:$

SECTION 5 INDIRECT COSTS & PROF

Summarize the direct costs and apply applicable indirect rates and profit.
Cost ElementCalculation BasisTotal Cost
A. Total Direct Costs(Sum of Sections 1, 2, 3, and 4)$
B. Overhead( ___ % of Direct Costs)$
C. General & Administrative (G&A)( ___ % of Direct Costs + Overhead)$
D. Subtotal Cost(A + B + C)$
E. Profit( ___ % of Subtotal Cost)$
F. Bonds and Insurance(Estimated Cost for Bid, Perf. & Payment Bonds)$
GRAND TOTAL FIXED PRICE (CLIN 0001):(D + E + F)$