Attachment_0002_-_FRLA_Drawings.pdf
PDF 27 MB Posted
- Attached to
- FRLA - WATER SHEDDING IMPROVEMENTS Federal contract opportunity
- Solicitation number
- 140P4321R0021
About this file
This document provides details on a federal contract opportunity for water shedding improvements issued by the Department of the Interior National Park Service Northeast Region. Solicitation number 140P4321R0021 seeks bids for FRLA - WATER SHEDDING IMPROVEMENTS to address runoff and drainage concerns at an unspecified National Park location. Interested vendors are instructed to review Attachment_0002_-_FRLA_Drawings.pdf for additional technical specifications and scope of work details. The opportunity type is listed as a solicitation, though no further information is included on response due dates, award timing, or other procurement terms.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P4321R0021_Amd_0003.pdf | ||
| Attachment_0004_-_Civil_with_markups_0003.pdf | ||
| Sol_140P4321R0021_Amd_0002.pdf | ||
| Sol_140P4321R0021_Amd_0001.pdf | ||
| B08_-_Attachment_0003_-_DOL_DBA_WD_MA20210001.pdf | ||
| Attachment_0001_-_FRLA_Paint_House_and_Office_Improve_Roofs_Specifications.pdf | ||
| Sol_140P4321R0021.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FREDERICK LAW
OLMSTED N.H.S.
SHEET SHEET NO. TITLE
1 COVER
2 A1.1 ROOF OVERVIEW PLAN, ABBREVIATIONS GENERAL NOTES
3 A1.2 ROOF PLAN HOUSE AND BARN
4 A1.3 ROOF PLAN OFFICE, PLANTING, DRAFTING, VAULT
5 A2.1 ELEVATIONS - EAST AND WEST HOUSE
6 A2.2 ELEVATIONS - SOUTH HOUSE
7 A2.3 ELEVATIONS - NORTH HOUSE
8 A2.4 ELEVATIONS - EAST OFFICE/DRAFTING
9 A2.5 ELEVATIONS - OFFICE/PLANTING
10 A2.6 ELEVATIONS - VAULT/DRAFTING/PLANTING
11 A2.7 ELEVATIONS - VAULT/DRAFTING/BARN
12 A3.1 ROOF TYPICAL CONDITIONS
13 A3.2 ROOF TYPICAL CONDITIONS
14 A3.3 ROOF DETAILS
15 A4.1 WINDOW/DOOR/SHUTTER TYPES
16 A4.2 WINDOW TYPICAL CONDITIONS
17 A4.3 SHUTTER/STORM TYPICAL CONDITIONS
18 A4.4 WINDOW DETAILS
19 A5.1 WOODWORK DETAILS
20 A6.1 WINDOW SCHEDULE
21 A6.2 WINDOW SCHEDULE
22 A6.3 WINDOW SCHEDULE
23 A6.4 WINDOW SCHEDULE
24 A6.5 WINDOW SCHEDULE
25 A6.6 WINDOW SCHEDULE
26 A6.7 WINDOW SCHEDULE
VAULT
HOUSE
OFFICE
DRAFTING WING
VAULT
PLANTING ROOM
BARN
TITLE OF PROJECT
PAINT HOUSE, IMPROVE ROOF
PAINT OFFICE, IMPROVE ROOF
FREDERICK LAW OLMSTED NATIONAL HISTORIC SITE
DRAWING NO.:
PMIS NO.:
SHEET:
1 OF
NAME OF PARK
UNITED STATES DEPARTMENT OF THE INTERIOR
NATIONAL PARK SERVICE
INTERIOR REGION 1 - NORTHEAST - APPALACHIAN
HISTORIC ARCHITECTURE, CONSERVATION,
AND ENGINEERING CENTER (HACE)
REGION
NORTHEAST
COUNTY
NORFOLK
STATE
MASSACHUSETTS
PMIS NO. 223735 PAINT HOUSE, IMPROVE ROOF
PMIS NO. 223737 PAINT OFFICE, IMPROVE ROOF
VICINITY PLAN
MARCH 01, 2021
SITE PLAN
223735
223737
THIS PROJECT
MARK SHT DATE INITREVISION
175030
SOLICITATION DOCS 03/01/2021
AutoCAD SHX Text 2A
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
CAMBRIDGE
AutoCAD SHX Text
ROXBURY
AutoCAD SHX Text
BROOKLINE
AutoCAD SHX Text
BOSTON
AutoCAD SHX Text
BRIGHTON
AutoCAD SHX Text
JAMAICA
AutoCAD SHX Text
PLAIN
AutoCAD SHX Text
SOUTH BOSTON
AutoCAD SHX Text
BOSTON
AutoCAD SHX Text
INNER
AutoCAD SHX Text
HARBOR
AutoCAD SHX Text
CHARLES RIVER
AutoCAD SHX Text
JAMAICA
AutoCAD SHX Text
POND
AutoCAD SHX Text
BROOKLINE
AutoCAD SHX Text
RESERVOIR
AutoCAD SHX Text
FRESH
AutoCAD SHX Text
POND
AutoCAD SHX Text
OLD HARBOR
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
BOYLSTON
AutoCAD SHX Text
STREET
AutoCAD SHX Text
BEACON
AutoCAD SHX Text
STREET
AutoCAD SHX Text
MASSACH
AutoCAD SHX Text
USETTS ST.
BARN
PLANTING
VAULT
DRAFTINGOFFICE
HOUSE
COURTYARD
A
A4
A4
A4
A
A
A
A4
A
43'-3
" 10'-11
A
A
A4
9'-11
55'-3
24'-6
29'-9
14'-9"
METAL
ROOF
METAL
ROOF
BUILT UP
ROOF
METAL
ROOF
EPDM
METAL
ROOF
BUILT UP
ROOF
D
S6
O
S5
O
S4
H
S2
H
S1
H
S3
SLATE
ASPHALT
BUILT-UP
ROLL ROOFING
SYMBOL KEY:
WINDOW
DOOR
DETAIL
NOTE
D1.1
D1.1
GENERAL NOTES:
1. PLANS AND ELEVATIONS in this set incorporate reproductions of measured drawings prepared from a variety of sources. Certain portions of these drawings have been updated to reflect current existing conditions. Missing elevations have been composed from these existing documents. Dimensions and scales are approximate; the
Contractor is responsible for field verifying all dimensions and conditions.
2. DRAWINGS are prepared and coordinated with the technical specifications; both components comprIse the Project Manual and govern the work of this project.
3. EXISTING CONDITIONS are noted to provide a guide to typical conditions. The
Contractor shall verify all existing conditions prior to beginning work and bring any discrepancies to the Government's attention. Dimensions are for reference only; the
Contractor is responsible for field verification of all dimensions and conditions on site prior to proceeding with work, preparing shop drawings, or ordering materials.
4. PROTECTION of existing materials to remain is the Contractor's responsibility. The structure is a NATIONAL HISTORIC LANDMARK and existing materials are significant historic features that must be retained and protected during the course of the work.
Refer to the Project Manual for additional information regarding protection of building features.
5. ROOFING and flashing shall be 100% weather tight on a dailiy basis; remove only as much roofing as can be replaced on the same day.
ABBREVIATIONS
ADJ ADJACENT
BR BRICK
CEM CEMENT
CI CAST IRON
CU COPPER
D DIAMETER
DS DOWNSPOUT
EXG EXISTING
FLR FLOOR
FNDN FOUNDATION
JT JOINT
LCC LEAD COATED COPPER
ZCC ZINC-TIN COATED COPPER
MEMB MEMBRANE
MTL METAL
NTS NOT TO SCALE
STL STEEL
STN STONE
T&G TONGUE AND GROOVE
TYP TYPICAL
UON UNLESS OTHERWISE NOTED
VIF VERIFY IN FIELD
WD WOOD
Roof Overall Plan
A1.1
DESIGNED:
CADD:
TECH REV:
DATE:
SUB SHEET
NO.:
SUB SHEET NO.:
CONSTRUCTION DOCUMENTS
seh seh
SEH
03/01/2021
A1.1
Roof Overview Plan 4 0 4
SCALE OF FEET
1/4" = 1'-0"
PMIS
NO.:
SHEET
Scale: 1/4" = 1'-0" when printed full size on 22" x 34" sheet
U.N.O.
FREDERICK LAW OLMSTED NATIONAL HISTORIC SITE
PAINT HOUSE, IMPROVE ROOF PAINT OFFICE, IMPROVE ROOF
175030
223735
223737 of 26
CONTRACTOR STAGING
AREA
MAINTAIN OWNER
ACCESS TO BARN
VAULT
DRAFTINGOFFICE
HOUSE
LAUNDRY YARD
A2.1
A2.1
A2.2
A
A
A2.3
COURT YARD
#40
#40
#40
A
A
SKY
SKY
SKY
#20
SLATE
ASPHALT
BUILT-UP
ROLL ROOFING
FLAT SEAM METAL
SYMBOL KEY:
WINDOW
DOOR
ELEVATION
NOTE
D1.1
A
LAUNDRY YARD
B4
B1
B2
B2 B3
B3
BARN COURT YARD
A2.7
A2.7
A2.7
A2.7
B5
Key Notes - Barn Roof
B1 NEW LINER IN NEW GUTTER: Oil existing new wood gutter. Install custom LCC gutter liner and adjust gutter as required to integrate with new roofing. Provide additional trim to match existing; prep and paint. See 1/A3.3
B2 INSTALL ZCC GUTTER LINERS: Install owner furnished custom ZCC gutter liner. Provide outlets and other materials for complete system. See Detail 3/A3.3.
B3 REPAIR ASPHALT ROOFING: Integrate flashing and waterproof membrane with new gutter liners to ensure a water-tight connection, replace missing courses of 3 tab asphalt shingles with new to match existing entire extent of eave edge.
B4 REPLACE SBS ROOF: Remove existing roofing to plywood substrate. Repair substrate as required and ensure that roof deck slopes to gutter. Install new SBS roof system. Match existing edge nailed detail to emulate historic roll roofing. See
1/A3.3.
B5 INSTALL DRIP EDGE: Remove 3 tab asphalt roofing to expose hangers, remove half round copper gutter, install drip and flashing, re-install gutter.
Key Notes - Roof:
1. REPLACE BUR ROOF: Remove existing multi-ply BUR and coal tar pitch roof to deck. Install tapered cover board and build up NE corner as required to slope to gutters. Remove and re-install siding for waterproof membrane at wall/roof junction on north and east;
turn up membrane 8" min. See 5/A3.3.
2. INSTALL LCC GUTTER LINER. Modify existing owner-furnished custom gutter liner to create a concealed expansion joint at new downspout. Install liner.
3. REPAIR ROOF DOWNSPOUT: Provide CMU downspout keeper blocks (3) to provide minimum of 1/4" per foot slope to outlet. Make sure all downspout sections are securely attached to each other with copper or brass screws. See 7/A3.3.
4. REPLACE and EXTEND GUTTER DIVERTER: Remove existing lead and sheet metal flashing and siding at end of gutter where it abuts main house. Provide additional flashing, wood blocking, and epoxy repairs at corner to create a water-tight condition between gutter and wall. Provide LCC overflow diverter and flashing to direct water into gutter and away from corner. Integrate with gutter liner.
5. NEW DOWNSPOUT: Provide new downspout to match existing downspouts at location. Include boot and run below grade to daylight at west end of ell. Prep, prime and paint.
6. SLATE EAVE REPAIR: Remove 5'-0" (12 courses +/-) of slate at eave and repair any damage to sheathing. Install waterproof membrane (min. 4'-0") and underlayment to exposed roof area,install flashing as req. to tie into existing. Re-install slate. See 2/A3.3 and 4/A3.3.
7. REPLACE CORNICE TRIM: Provide new wood cornice materials to match existing. Work includes crown, bed, and trim moldings with custom profiles. See 2/A3.3.
8. SELECTED SLATE REPAIR: Replace broken, cracked, unsound slate with new to match existing; # indicates quantity per slope.
9. RIDGE CAPS: Replace copper ridge caps with new to match existing.
10. SNOW GUARDS: Replace snow guards with new pad-style retrofit guards; retain existing pigtail type where possible.
11. ASPHALT ROOF REPAIR: Remove and replace 15 s.f. of existing 3-tab asphalt shingle to match. Remove and re-install siding on west wall for installation of additional waterproof membrane; turn up 1'-0" typ. and extend onto roof deck to cover area of shingle replacement.
12. ASPHALT ROOF REPLACEMENT: Remove and replace existing 3-tab asphalt shingle to match, install waterproof membrane over entire roof deck. Remove and salvage siding on abutting walls to allow for membrane to turn up 1'-0" typ.
13. ROLL ROOFING: Remove existing roofing and sheathing. Install new plywood sheathing, waterproof membrane, and underlayment, and SBS roof with granulated surface. Provide nailed rolled edge to emulate historic roll roofing.
14. UNCOATED FLAT SEAM METAL ROOF: Inspect all seams for splits or breaks; re-solder as req. to restore watertight condition.
15. COATED TERNE and COPPER METAL ROOFING: Inspect roofing for splits, breaks, corrosion. Remove previous coatings in deteriorated areas, prep surface, apply appropriate primer, re-coat entire roof with compatible elastomeric coating.
16. EPDM ROOF: Inspect for tears, bubbles, seam failure.
17. EXTEND ROOF DOWNSPOUT: Extend existing downspout to discharge into gutter, prime and paint.
18. RENEW BUR ROOF: Remove organic material from roof; scrape back loose, unbonded gravel materials from west side of roof, cleanout exg. copper lined gutter. Reapply bituminous to exposed area and refresh gravel material, bonding to bituminous.
19. REPAIR SKYLIGHTS [Bid Option 5]: Inspect steel and wood frame skylights section loss and corrosion; replace steel as required;
remove caps and glass and reglaze; conserve broken lites. Remove corrosion from metal surfaces; repair wood frames, sash, prime, paint. See 1/A3.2 and 2/A3.2 for skylight window repairs.
20. RE-HANG GUTTER: Re-hang half round gutter; replace, provide additional brackets as req.
21. GUTTER REPLACEMENT: Document existing gutter/eave condition; replace wood gutters with new wood gutter to match, replace/repair/adjust substrate/blocking/fascia/soffit/trim. Install new LCC gutter liners.
22. REPLACE WOOD GUTTER SECTION: Provide new wood gutter. # indicates estimated l.f.
23. EAVE HEAT TRACE: Provide eave edge heat trace.
24. REPLACE CUPOLA FLASHING: Remove existing wood cupola structure to access flashing; replace existing base flashing with new.
Re-install wood structure.
25. EXTEND LIP OF GUTTER: Increase lip of gutter to improve capacity and resist overflow. See 4/A3.2.
26. RAFTER TIES: Provide supplemental rafter ties (2) at vault attic framing. See 3/A3.2.
GENERAL ROOF/DRAINAGE/SITE DRAINAGE NOTES:
REPAIR EXISTING WOOD GUTTERS: Remove existing rotted or damaged portions of wood gutter to sound material. Consolidate and patch wood gutter with epoxy materials to create a solid surface. Close and fill all open joints at corners/joins. Enlarge outlets to max. diameter possible; adjust gutter pitch to provide adequate slope to outlets. See drawing notes for areas requiring new wood gutter sections. Install custom lead coated copper (LCC) gutter liners and coordinate with roofing repairs/replacement. Replace existing heat trace system, activate, and test system.
DOWNSPOUTS: Remove and replace existing heat trace system with new. Inspect all downspouts sections for loose/burst/stressed seams; repair/replace sections as req. Ensure all sections are securely attached with copper or brass screws. Ensure that all downspout brackets are secured to building and adequate in number;
replace in-kind any missing/damaged accessories.
SUBSURFACE DRAINAGE: Inspect and clean out all catch basins, dry wells, etc. and flush all subsurface drain lines to ensure that all are clear of debris and flowing freely to public mains; ensure downspouts are discharging into drain boots. Cleanout two areaway drains at basement access stairs.
ICE MELT SYSTEM: Replace all ice melt cables; cables typically exist on certain roof areas, in all gutters, and down all downspouts/boots. Provide additional cabling and accessories as required at new gutters/downspouts and/or at eaves as noted on drawings. Update controls as required to provide a fully functional system; test and re-energize system.
House Roof Plan
A1.2
Key Plan
DESIGNED:
CADD:
TECH REV:
DATE:
SUB SHEET
NO.:
SUB SHEET NO.:
CONSTRUCTION DOCUMENTS
seh seh
SEH
03/01/2021
A1.2
Roof Plan
PMIS
NO.:
SHEET
FREDERICK LAW OLMSTED NATIONAL HISTORIC SITE
PAINT HOUSE, IMPROVE ROOF PAINT OFFICE, IMPROVE ROOF
175030
223735
223737
3 of
Barn Roof Plan
A1.2
See Sheet
A1.3
1/8" = 1'-0"
1/8" = 1'-0"
House and Barn
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
SCALE OF FEET
1/8" = 1'-0"
VAULT
DRAFTINGOFFICE
HOUSE
A
A
A
A
A2.4
A
A
A
A2.3
COURT YARD
A
SKY
SKY
SKY
SKY
#20
A
#23
#62
#40
#40
#50
#75
#20
#20
#10
SLATE
ASPHALT
BUILT-UP
ROLL ROOFING
FLAT SEAM METAL
SYMBOL KEY:
WINDOW
DOOR
ELEVATION
NOTE
D1.1
Key Notes - Roof:
1. REPLACE BUR ROOF: Remove existing multi-ply BUR and coal tar pitch roof to deck. Install tapered cover board and build up NE corner as required to slope to gutters. Remove and re-install siding for waterproof membrane at wall/roof junction on north and east;
turn up membrane 8" min. See 5/A3.3.
2. INSTALL LCC GUTTER LINER. Modify existing owner-furnished custom gutter liner to create a concealed expansion joint at new downspout. Install liner.
3. REPAIR ROOF DOWNSPOUT: Provide CMU downspout keeper blocks (3) to provide minimum of 1/4" per foot slope to outlet. Make sure all downspout sections are securely attached to each other with copper or brass screws. See 7/A3.3.
4. REPLACE and EXTEND GUTTER DIVERTER: Remove existing lead and sheet metal flashing and siding at end of gutter where it abuts main house. Provide additional flashing, wood blocking, and epoxy repairs at corner to create a water-tight condition between gutter and wall. Provide LCC overflow diverter and flashing to direct water into gutter and away from corner. Integrate with gutter liner.
5. NEW DOWNSPOUT: Provide new downspout to match existing downspouts at location. Include boot and run below grade to daylight at west end of ell. Prep, prime and paint.
6. SLATE EAVE REPAIR: Remove 5'-0" (12 courses +/-) of slate at eave and repair any damage to sheathing. Install waterproof membrane (min. 4'-0") and underlayment to exposed roof area,install flashing as req. to tie into existing. Re-install slate. See 2/A3.3 and 4/A3.3.
7. REPLACE CORNICE TRIM: Provide new wood cornice materials to match existing. Work includes crown, bed, and trim moldings with custom profiles. See 2/A3.3.
8. SELECTED SLATE REPAIR: Replace broken, cracked, unsound slate with new to match existing; # indicates quantity per slope.
9. RIDGE CAPS: Replace copper ridge caps with new to match existing.
10. SNOW GUARDS: Replace snow guards with new pad-style retrofit guards; retain existing pigtail type where possible.
11. ASPHALT ROOF REPAIR: Remove and replace 15 s.f. of existing 3-tab asphalt shingle to match. Remove and re-install siding on west wall for installation of additional waterproof membrane; turn up 1'-0" typ. and extend onto roof deck to cover area of shingle replacement.
12. ASPHALT ROOF REPLACEMENT: Remove and replace existing 3-tab asphalt shingle to match, install waterproof membrane over entire roof deck. Remove and salvage siding on abutting walls to allow for membrane to turn up 1'-0" typ.
13. ROLL ROOFING: Remove existing roofing and sheathing. Install new plywood sheathing, waterproof membrane, and underlayment, and SBS roof with granulated surface. Provide nailed rolled edge to emulate historic roll roofing.
14. UNCOATED FLAT SEAM METAL ROOF: Inspect all seams for splits or breaks; re-solder as req. to restore watertight condition.
15. COATED TERNE and COPPER METAL ROOFING: Inspect roofing for splits, breaks, corrosion. Remove previous coatings in deteriorated areas, prep surface, apply appropriate primer, re-coat entire roof with compatible elastomeric coating.
16. EPDM ROOF: Inspect for tears, bubbles, seam failure.
17. EXTEND ROOF DOWNSPOUT: Extend existing downspout to discharge into gutter, prime and paint.
18. RENEW BUR ROOF: Remove organic material from roof; scrape back loose, unbonded gravel materials from west side of roof, cleanout exg. copper lined gutter. Reapply bituminous to exposed area and refresh gravel material, bonding to bituminous.
19. REPAIR SKYLIGHTS [Bid Option 5]: Inspect steel and wood frame skylights section loss and corrosion; replace steel as required;
remove caps and glass and reglaze; conserve broken lites. Remove corrosion from metal surfaces; repair wood frames, sash, prime, paint. See 1/A3.2 and 2/A3.2 for skylight window repairs.
20. RE-HANG GUTTER: Re-hang half round gutter; replace, provide additional brackets as req.
21. GUTTER REPLACEMENT: Document existing gutter/eave condition; replace wood gutters with new wood gutter to match, replace/repair/adjust substrate/blocking/fascia/soffit/trim. Install new LCC gutter liners.
22. REPLACE WOOD GUTTER SECTION: Provide new wood gutter. # indicates estimated l.f.
23. EAVE HEAT TRACE: Provide eave edge heat trace.
24. REPLACE CUPOLA FLASHING: Remove existing wood cupola structure to access flashing; replace existing base flashing with new.
Re-install wood structure.
25. EXTEND LIP OF GUTTER: Increase lip of gutter to improve capacity and resist overflow. See 4/A3.2.
26. RAFTER TIES: Provide supplemental rafter ties (2) at vault attic framing. See 3/A3.2.
GENERAL ROOF/DRAINAGE/SITE DRAINAGE NOTES:
REPAIR EXISTING WOOD GUTTERS: Remove existing rotted or damaged portions of wood gutter to sound material. Consolidate and patch wood gutter with epoxy materials to create a solid surface. Close and fill all open joints at corners/joins. Enlarge outlets to max. diameter possible; adjust gutter pitch to provide adequate slope to outlets. See drawing notes for areas requiring new wood gutter sections. Install custom lead coated copper (LCC) gutter liners and coordinate with roofing repairs/replacement. Replace existing heat trace system, activate, and test system.
DOWNSPOUTS: Remove and replace existing heat trace system with new. Inspect all downspouts sections for loose/burst/stressed seams; repair/replace sections as req. Ensure all sections are securely attached with copper or brass screws. Ensure that all downspout brackets are secured to building and adequate in number;
replace in-kind any missing/damaged accessories.
SUBSURFACE DRAINAGE: Inspect and clean out all catch basins, dry wells, etc. and flush all subsurface drain lines to ensure that all are clear of debris and flowing freely to public mains; ensure downspouts are discharging into drain boots. Cleanout two areaway drains at basement access stairs.
ICE MELT SYSTEM: Replace all ice melt cables; cables typically exist on certain roof areas, in all gutters, and down all downspouts/boots. Provide additional cabling and accessories as required at new gutters/downspouts and/or at eaves as noted on drawings. Update controls as required to provide a fully functional system; test and re-energize system.
Office, Planting, Drafting, Vault Roof Plan
A1.3
Key Plan
DESIGNED:
CADD:
TECH REV:
DATE:
SUB SHEET
NO.:
SUB SHEET NO.:
CONSTRUCTION DOCUMENTS
seh seh
SEH
03/01/2021
A1.3
Roof Plan
PMIS
NO.:
SHEET
FREDERICK LAW OLMSTED NATIONAL HISTORIC SITE
PAINT HOUSE, IMPROVE ROOF PAINT OFFICE, IMPROVE ROOF
175030
223735
223737 of 26
See Sheet
A1.2
1/8 " = 1'-0"
Office, Planting, Drafting, Vault
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
SCALE OF FEET
W1
M1
M3
M4
M1
W1
W4
C1
W4
W4
W1
3'-6"
WH
WH
WH
WH
WH
WH
D100
WH
D200
WH
D201
WH
WH
WH
WH
WH
WH
WH
WH
WH
WH
WH
WH
M1
WH
WH
WH
WH
WH
A3.2
W4
S1
HOUSE
W1
W2
W2
C1
M1
C1
C1
E1
W3
A2.1
EH
EH
EH
EH
EH
EH
EH
104 EH
D102
EH
EO
EH
D100
EH
EH
EH
EH
EH
EH
W1
M1
EH
D101
EH
D100
SAND AND REFINISH
FIR DECKING
PAINT INTERIOR OF
VESTIBULE TYP.
REPLACE
NOSING
ENTIRE
LENGTH
RE-SECURE
NOSING TYP.
DUTCHMAN REPAIR PLINTH, TORUS, AND
BASE OF COLUMN. ASSUME
OF PLINTH
AND TORUS AND 20 SQ. INCH OF COLUMN.
REPAIR
DETERIORATED
GUTTER SECTION;
REPLACE MISSING
BANDMOLDING;
RE-SECURE TRIM
ENTRY ROOF GUTTERS DO NOT RECEIVE
LINERS. REHABILITATE EXISTING WOOD
GUTTERS, APPLY PRESERVATIVE
TREATMENT TYP.
NH
SH
General Notes - Exterior
1. Notes are indicative of general areas of repair and intent of work. Quantities are estimates only; additional repairs may be required to meet the scope noted.
2. See window and door schedules for additional repairs which may encompass exterior trim, sills, and flashing work.
3. The entire structure will be primed and painted. Repair work noted is in addition to typical prep work required for exterior painting which may include caulking, patching, sanding, nailing, filling, cleaning, and the like.
4. All repairs shall be primed and back primed on all surfaces and cut ends as part of the repair work.
5. Dutchman/epoxy repairs are used to generally describe the type of work required;
see specifications for additional information on repair requirements.
6. Scarf all joints between existing and new woodwork; prime/backprime. If there are more than three joints in a 8'-0” section of running trim (water table, stringcourse/sill course, siding) requiring repair, replace in entirety.
7. Re-nail/re-secure all siding joins/scarfs.
8. Replace all ice melt cables; re-energize system and test. Cables typically exist on selected roof areas, in all gutters, and down all downspouts.
Key Notes - Exterior
W1 # Replace # l.f. of siding
W2 # Replace # l.f. of watertable
W3 # Replace # l.f. of string course/sill
W4 # Replace # l.f. of 1x trim
G1 Replace wood gutter section
C1 Remove organic staining
M1 # Repoint # s.f. of masonry
M2 # NOT USED
M3 # Rebuild # s.f. of masonry
M4# Brick replacement
M5 Parge masonry
S1 Fill and stabilize eroded area
E1# Epoxy consolidate/fill repair
1. Rehabilitate mortise and tenon shutter screen. Remove, rebuild joints as req., reinstall. See window schedule for shutter scope.
2. Rehabilitate hoist. Dutchman/epoxy repairs; add cap flashing nailed to top face;
paint.
3. Re-nail popped nails typ.
4. Rehabilitate fence. Replace deteriorated 4x6 posts (24 lf), bottom 2x8 rails (16 lf), secure lattice, re-secure to rebuilt brick base, paint.
5. Rebuild brick pier 1 typ. Provide Simpson post bracket anchored to masonry for each post; 2 typ.
6. New shutter; see window schedule.
7. Rebuild brick fence base. Repoint and rebuild masonry, replace broken/spalled brick with new. Use salvaged exg. brick on visible faces.
8. Rehabilitate rafter tails. Dutchman and epoxy repairs.
9. Reset and level bluestone step on compacted gravel and sand base.
10. Consolidate cracked clapboard ends left side; preserve trellis holes, provide new wood plugs to fill missing on left and right sides.
11. Rehabilitate entablature woodwork. Replace failed Dutchman at panel stiles/rails and below threshold, epoxy repair threshold, replace missing band molding at pilasters.
12. Rehabilitate cornice/gutter. Document existing conditions along length of elevation; conditions vary. Remove and salvage existing wood gutter and sound trim. Rework fascia, blocking, substrate as req. and coordinate with roof eave and gutter work. All new trim/moldings to match existing; assume custom profiles.
13. Provide waterproof membrane under siding typ.
14. Rehabilitate junction of sun printer and building face. Dutchman 20 l.f. sill course, remove siding as required to install flashing and extend over top and sides of brace joints and over sill; paint.
15. Seal joint between drafting entrance and vault.
16. Remove vine holdfasts from siding.
17. Re-secure conduit and electrical lines to siding.
18. Clean heavy organic soiling at gutters and trim at sleeping porch on east and north sides.
19. Remove, salvage, and reinstall siding as required to inspect and repair substrate/sheathing.
20. Re-secure butt ends/joins at sheathing typ.
21. Repair decorative trim panel.
22. Replace deteriorated posts.
23. Restore spalled, damaged concrete stoop; custom aggregate and concrete mix to match existing materials.
Key Plan
DESIGNED:
CADD:
TECH REV:
DATE:
SUB SHEET
NO.:
SUB SHEET NO.:
CONSTRUCTION DOCUMENTS
seh seh
SEH
03/01/2021
A2.1
Elevations
East and West House
4 0 4
SCALE OF FEET
1/4" = 1'-0"
PMIS
NO.:
SHEET
Scale: 1/4" = 1'-0" when printed full size on 22" x 34" sheet
U.N.O.
FREDERICK LAW OLMSTED NATIONAL HISTORIC SITE
PAINT HOUSE, IMPROVE ROOF PAINT OFFICE, IMPROVE ROOF
175030
223735
223737 of 26
West Elevation - House
A2.1
East Elevation - House
A2.1
Vestibule
A2.1
1/4" = 1'-0" 1/4" = 1'-0"
1/4" = 1'-0"
W4
M1
M1
M1
S1
M1
M4
M1
M5
M1
M4
M1
M4
W1
W2
W4
W1
W1
W1
M1
A2.1
SH
SH
SH
SH
SH
SH
SH
SH
SH
SH
SH
SH
SH
SH
SH
SH
SH
SH
209SH
SH
SH
SH
SH
SH
SH
SH
SH
SH
SH
SH
SH
SH
SKY
SKY
SH
SH
SH
SH
SH
D100
SH
M4
SH
W1
SH
W4
SH
D101
General Notes - Exterior
1. Notes are indicative of general areas of repair and intent of work. Quantities are estimates only; additional repairs may be required to meet the scope noted.
2. See window and door schedules for additional repairs which may encompass exterior trim, sills, and flashing work.
3. The entire structure will be primed and painted. Repair work noted is in addition to typical prep work required for exterior painting which may include caulking, patching, sanding, nailing, filling, cleaning, and the like.
4. All repairs shall be primed and back primed on all surfaces and cut ends as part of the repair work.
5. Dutchman/epoxy repairs are used to generally describe the type of work required;
see specifications for additional information on repair requirements.
6. Scarf all joints between existing and new woodwork; prime/backprime. If there are more than three joints in a 8'-0” section of running trim (water table, stringcourse/sill course, siding) requiring repair, replace in entirety.
7. Re-nail/re-secure all siding joins/scarfs.
8. Replace all ice melt cables; re-energize system and test. Cables typically exist on selected roof areas, in all gutters, and down all downspouts.
Key Notes - Exterior
W1 # Replace # l.f. of siding
W2 # Replace # l.f. of watertable
W3 # Replace # l.f. of string course/sill
W4 # Replace # l.f. of 1x trim
G1 Replace wood gutter section
C1 Remove organic staining
M1 # Repoint # s.f. of masonry
M2 # NOT USED
M3 # Rebuild # s.f. of masonry
M4# Brick replacement
M5 Parge masonry
S1 Fill and stabilize eroded area
E1# Epoxy consolidate/fill repair
1. Rehabilitate mortise and tenon shutter screen. Remove, rebuild joints as req., reinstall. See window schedule for shutter scope.
2. Rehabilitate hoist. Dutchman/epoxy repairs; add cap flashing nailed to top face;
paint.
3. Re-nail popped nails typ.
4. Rehabilitate fence. Replace deteriorated 4x6 posts (24 lf), bottom 2x8 rails (16 lf), secure lattice, re-secure to rebuilt brick base, paint.
5. Rebuild brick pier 1 typ. Provide Simpson post bracket anchored to masonry for each post; 2 typ.
6. New shutter; see window schedule.
7. Rebuild brick fence base. Repoint and rebuild masonry, replace broken/spalled brick with new. Use salvaged exg. brick on visible faces.
8. Rehabilitate rafter tails. Dutchman and epoxy repairs.
9. Reset and level bluestone step on compacted gravel and sand base.
10. Consolidate cracked clapboard ends left side; preserve trellis holes, provide new wood plugs to fill missing on left and right sides.
11. Rehabilitate entablature woodwork. Replace failed Dutchman at panel stiles/rails and below threshold, epoxy repair threshold, replace missing band molding at pilasters.
12. Rehabilitate cornice/gutter. Document existing conditions along length of elevation; conditions vary. Remove and salvage existing wood gutter and sound trim. Rework fascia, blocking, substrate as req. and coordinate with roof eave and gutter work. All new trim/moldings to match existing; assume custom profiles.
13. Provide waterproof membrane under siding typ.
14. Rehabilitate junction of sun printer and building face. Dutchman 20 l.f. sill course, remove siding as required to install flashing and extend over top and sides of brace joints and over sill; paint.
15. Seal joint between drafting entrance and vault.
16. Remove vine holdfasts from siding.
17. Re-secure conduit and electrical lines to siding.
18. Clean heavy organic soiling at gutters and trim at sleeping porch on east and north sides.
19. Remove, salvage, and reinstall siding as required to inspect and repair substrate/sheathing.
20. Re-secure butt ends/joins at sheathing typ.
21. Repair decorative trim panel.
22. Replace deteriorated posts.
23. Restore spalled, damaged concrete stoop; custom aggregate and concrete mix to match existing materials.
Key Plan
DESIGNED:
CADD:
TECH REV:
DATE:
SUB SHEET
NO.:
SUB SHEET NO.:
ONSTRUCTION DOCUMENTS
seh seh
SEH
03/01/2021
A2.2
4 0 4
SCALE OF FEET
1/4" = 1'-0"
PMIS
NO.:
SHEET
Scale: 1/4" = 1'-0" when printed full size on 22" x 34" sheet
U.N.O.
FREDERICK LAW OLMSTED NATIONAL HISTORIC SITE
PAINT HOUSE, IMPROVE ROOF PAINT OFFICE, IMPROVE ROOF
175030
223735
223737 of 26
South Elevation - House
A2.2 1/4" = 1'-0"
Elevations
South House
REPLACE
SIDING
AND
TRIM
REPLACE
DETERIORATED
SHEATHING
BOARDS AND
ROOFING
REPLACE WOOD
BOARD AND BATTEN
DOOR BOARDS
SALVAGE AND
REUSE HARDWARE
WOOD KEEPER TOP
AND CANE BOLT
BOTTOM EACH LEAF
REPLACE ROOFING
ROLL OVER EDGES
AND FACE NAIL TYP.
REPLACE
TRIM AND
REPAIR
SHEATHING
INTERIOR FACE OF DOORS
NH
D001
General Notes - Exterior
1. Notes are indicative of general areas of repair and intent of work. Quantities are estimates only; additional repairs may be required to meet the scope noted.
2. See window and door schedules for additional repairs which may encompass exterior trim, sills, and flashing work.
3. The entire structure will be primed and painted. Repair work noted is in addition to typical prep work required for exterior painting which may include caulking, patching, sanding, nailing, filling, cleaning, and the like.
4. All repairs shall be primed and back primed on all surfaces and cut ends as part of the repair work.
5. Dutchman/epoxy repairs are used to generally describe the type of work required;
see specifications for additional information on repair requirements.
6. Scarf all joints between existing and new woodwork; prime/backprime. If there are more than three joints in a 8'-0” section of running trim (water table, stringcourse/sill course, siding) requiring repair, replace in entirety.
7. Re-nail/re-secure all siding joins/scarfs.
8. Replace all ice melt cables; re-energize system and test. Cables typically exist on selected roof areas, in all gutters, and down all downspouts.
Key Notes - Exterior
W1 # Replace # l.f. of siding
W2 # Replace # l.f. of watertable
W3 # Replace # l.f. of string course/sill
W4 # Replace # l.f. of 1x trim
G1 Replace wood gutter section
C1 Remove organic staining
M1 # Repoint # s.f. of masonry
M2 # NOT USED
M3 # Rebuild # s.f. of masonry
M4# Brick replacement
M5 Parge masonry
S1 Fill and stabilize eroded area
E1# Epoxy consolidate/fill repair
1. Rehabilitate mortise and tenon shutter screen. Remove, rebuild joints as req., reinstall. See window schedule for shutter scope.
2. Rehabilitate hoist. Dutchman/epoxy repairs; add cap flashing nailed to top face;
paint.
3. Re-nail popped nails typ.
4. Rehabilitate fence. Replace deteriorated 4x6 posts (24 lf), bottom 2x8 rails (16 lf), secure lattice, re-secure to rebuilt brick base, paint.
5. Rebuild brick pier 1 typ. Provide Simpson post bracket anchored to masonry for each post; 2 typ.
6. New shutter; see window schedule.
7. Rebuild brick fence base. Repoint and rebuild masonry, replace broken/spalled brick with new. Use salvaged exg. brick on visible faces.
8. Rehabilitate rafter tails. Dutchman and epoxy repairs.
9. Reset and level bluestone step on compacted gravel and sand base.
10. Consolidate cracked clapboard ends left side; preserve trellis holes, provide new wood plugs to fill missing on left and right sides.
11. Rehabilitate entablature woodwork. Replace failed Dutchman at panel stiles/rails and below threshold, epoxy repair threshold, replace missing band molding at pilasters.
12. Rehabilitate cornice/gutter. Document existing conditions along length of elevation; conditions vary. Remove and salvage existing wood gutter and sound trim. Rework fascia, blocking, substrate as req. and coordinate with roof eave and gutter work. All new trim/moldings to match existing; assume custom profiles.
13. Provide waterproof membrane under siding typ.
14. Rehabilitate junction of sun printer and building face. Dutchman 20 l.f. sill course, remove siding as required to install flashing and extend over top and sides of brace joints and over sill; paint.
15. Seal joint between drafting entrance and vault.
16. Remove vine holdfasts from siding.
17. Re-secure conduit and electrical lines to siding.
18. Clean heavy organic soiling at gutters and trim at sleeping porch on east and north sides.
19. Remove, salvage, and reinstall siding as required to inspect and repair substrate/sheathing.
20. Re-secure butt ends/joins at sheathing typ.
21. Repair decorative trim panel.
22. Replace deteriorated posts.
23. Restore spalled, damaged concrete stoop; custom aggregate and concrete mix to match existing materials.
PAINTED STEEL 1
"Ø
FLANGE MOUNTED TO
DECK.
PT FRAMING; PROVIDE
ADDITIONAL BLOCKING
AT HANDRAIL
COPPER FLASHING AT
LEDGER; TUCK UNDER
TRIM BOARD
ANY EXG. FOUNDATION
TO REMAIN
FRAME DECKING WITH NOSING
AND FACE WITH 1X TRIM TYP.
HOLD OFF GRADE 1"
PROVIDE 4" x 8" GRANITE
SLAB WIDTH OF DECK SET
LEVEL AND HOLD TOP AT
NEW GRADE
EXG. GRADE 139.21
NEW GRADE 139.43
STOOP 139.21
THRESHOLD 140.60
3'-6"
5'-6"
ADD 2" +/- OF STABILIZED
STONE DUST AT STOOP;
FEATHER OUT TO A 5%
SLOPE
NEW WOOD STOOP WITH
FIR DECKING AND STEEL
HANDRAIL. CENTER ON
DOOR.
5'-6"
7"
7"
NEW GRADE AND STOOP
NH
D100
HOUSE BARN
W1
W4
W4
W1
C1
A2.3
A2.3
W1
W1
W2
X
Ax.x
W4
W1
NH
NH
NH
NH
NH
NH
NH
NH
NH
NH
NH
NH
NH
NH
NH
NH
NH
NH
NH
NH
SKY
SKY SKY
NH
NH
NH
NH
NH
NH
NH
D001
NH
D100
S1
NH
Key Plan
DESIGNED:
CADD:
TECH REV:
DATE:
SUB SHEET
NO.:
SUB SHEET NO.:
CONSTRUCTION DOCUMENTS
seh seh
SEH
A2.3
4 0 4
SCALE OF FEET
1/4" = 1'-0"
PMIS
NO.:
SHEET
Scale: 1/4" = 1'-0" when printed full size on 22" x 34" sheet
U.N.O.
FREDERICK LAW OLMSTED NATIONAL HISTORIC SITE
PAINT HOUSE, IMPROVE ROOF PAINT OFFICE, IMPROVE ROOF
223735
223737 of 26
North Elevation - House
A2.3
North Elevation - Areaway
A2.3
North Stoop
A2.3
1/4" = 1'-0"
1/4" = 1'-0"
1/4" = 1'-0"
03/01/2021
175030
North House
OFFICE
DRAFTING VAULT
E1
G1
G1
W3
W3
W3
W3
EH
EO
EO
EO
EO
EO
EO
EO
ED
ED
ED
ED
ED
ED
ED
ED
EO
EO
EO
EO
EO
EO
ED
ED
ED
ED
ED
ED
ED
ED
ED
ED
ED
ED
ED
ED
D001
W1
W4
General Notes - Exterior
1. Notes are indicative of general areas of repair and intent of work. Quantities are estimates only; additional repairs may be required to meet the scope noted.
2. See window and door schedules for additional repairs which may encompass exterior trim, sills, and flashing work.
3. The entire structure will be primed and painted. Repair work noted is in addition to typical prep work required for exterior painting which may include caulking, patching, sanding, nailing, filling, cleaning, and the like.
4. All repairs shall be primed and back primed on all surfaces and cut ends as part of the repair work.
5. Dutchman/epoxy repairs are used to generally describe the type of work required;
see specifications for additional information on repair requirements.
6. Scarf all joints between existing and new woodwork; prime/backprime. If there are more than three joints in a 8'-0” section of running trim (water table, stringcourse/sill course, siding) requiring repair, replace in entirety.
7. Re-nail/re-secure all siding joins/scarfs.
8. Replace all ice melt cables; re-energize system and test. Cables typically exist on selected roof areas, in all gutters, and down all downspouts.
Key Notes - Exterior
W1 # Replace # l.f. of siding
W2 # Replace # l.f. of watertable
W3 # Replace # l.f. of string course/sill
W4 # Replace # l.f. of 1x trim
G1 Replace wood gutter section
C1 Remove organic staining
M1 # Repoint # s.f. of masonry
M2 # NOT USED
M3 # Rebuild # s.f. of masonry
M4# Brick replacement
M5 Parge masonry
S1 Fill and stabilize eroded area
E1# Epoxy consolidate/fill repair
1. Rehabilitate mortise and tenon shutter screen. Remove, rebuild joints as req., reinstall. See window schedule for shutter scope.
2. Rehabilitate hoist. Dutchman/epoxy repairs; add cap flashing nailed to top face;
paint.
3. Re-nail popped nails typ.
4. Rehabilitate fence. Replace deteriorated 4x6 posts (24 lf), bottom 2x8 rails (16 lf), secure lattice, re-secure to rebuilt brick base, paint.
5. Rebuild brick pier 1 typ. Provide Simpson post bracket anchored to masonry for each post; 2 typ.
6. New shutter; see window schedule.
7. Rebuild brick fence base. Repoint and rebuild masonry, replace broken/spalled brick with new. Use salvaged exg. brick on visible faces.
8. Rehabilitate rafter tails. Dutchman and epoxy repairs.
9. Reset and level bluestone step on compacted gravel and sand base.
10. Consolidate cracked clapboard ends left side; preserve trellis holes, provide new wood plugs to fill missing on left and right sides.
11. Rehabilitate entablature woodwork. Replace failed Dutchman at panel stiles/rails and below threshold, epoxy repair threshold, replace missing band molding at pilasters.
12. Rehabilitate cornice/gutter. Document existing conditions along length of elevation; conditions vary. Remove and salvage existing wood gutter and sound trim. Rework fascia, blocking, substrate as req. and coordinate with roof eave and gutter work. All new trim/moldings to match existing; assume custom profiles.
13. Provide waterproof membrane under siding typ.
14. Rehabilitate junction of sun printer and building face. Dutchman 20 l.f. sill course, remove siding as required to install flashing and extend over top and sides of brace joints and over sill; paint.
15. Seal joint between drafting entrance and vault.
16. Remove vine holdfasts from siding.
17. Re-secure conduit and electrical lines to siding.
18. Clean heavy organic soiling at gutters and trim at sleeping porch on east and north sides.
19. Remove, salvage, and reinstall siding as required to inspect and repair substrate/sheathing.
20. Re-secure butt ends/joins at sheathing typ.
21. Repair decorative trim panel.
22. Replace deteriorated posts.
23. Restore spalled, damaged concrete stoop; custom aggregate and concrete mix to match existing materials.
Key Plan
DESIGNED:
CADD:
TECH REV:
DATE:
SUB SHEET
NO.:
SUB SHEET NO.:
CONSTRUCTION DOCUMENTS
seh seh
SEH
A2.4
4 0 4
SCALE OF FEET
1/4" = 1'-0"
PMIS
NO.:
SHEET
Scale: 1/4" = 1'-0" when printed full size on 22" x 34" sheet
U.N.O.
FREDERICK LAW OLMSTED NATIONAL HISTORIC SITE
PAINT HOUSE, IMPROVE ROOF PAINT OFFICE, IMPROVE ROOF
223735
223737 of 26
East Elevation - Office and Drafting
A2.4
South Elevation - Drafting
A2.4
1/4" = 1'-0" N.T.S.
03/01/2021
175030
East Office and Drafting
C1
M1
W3
M5
WO
WO
WO
WO
WO
WO
WO
WO
WO
WO
D001
WO
W3
W4
W4
W1
W1
E1
SP
SP
SP
SP
SP
SP
SP
SP
SP
SP
D001
SP
SP
W1
W4
W3
W3
W3
W4
E1
M1
WP
WP
WP
W4
WP
S1
W4
SO
SO
General Notes - Exterior
1. Notes are indicative of general areas of repair and intent of work. Quantities are estimates only; additional repairs may be required to meet the scope noted.
2. See window and door schedules for additional repairs which may encompass exterior trim, sills, and flashing work.
3. The entire structure will be primed and painted. Repair work noted is in addition to typical prep work required for exterior painting which may include caulking, patching, sanding, nailing, filling, cleaning, and the like.
4. All repairs shall be primed and back primed on all surfaces and cut ends as part of the repair work.
5. Dutchman/epoxy repairs are used to generally describe the type of work required;
see specifications for additional information on repair requirements.
6. Scarf all joints between existing and new woodwork; prime/backprime. If there are more than three joints in a 8'-0” section of running trim (water table, stringcourse/sill course, siding) requiring repair, replace in entirety.
7. Re-nail/re-secure all siding joins/scarfs.
8. Replace all ice melt cables; re-energize system and test. Cables typically exist on selected roof areas, in all gutters, and down all downspouts.
Key Notes - Exterior
W1 # Replace # l.f. of siding
W2 # Replace # l.f. of watertable
W3 # Replace # l.f. of string course/sill
W4 # Replace # l.f. of 1x trim
G1 Replace wood gutter section
C1 Remove organic staining
M1 # Repoint # s.f. of masonry
M2 # NOT USED
M3 # Rebuild # s.f. of masonry
M4# Brick replacement
M5 Parge masonry
S1 Fill and stabilize eroded area
E1# Epoxy consolidate/fill repair
1. Rehabilitate mortise and tenon shutter screen. Remove, rebuild joints as req., reinstall. See window schedule for shutter scope.
2. Rehabilitate hoist. Dutchman/epoxy repairs; add cap flashing nailed to top face;
paint.
3. Re-nail popped nails typ.
4. Rehabilitate fence. Replace deteriorated 4x6 posts (24 lf), bottom 2x8 rails (16 lf), secure lattice, re-secure to rebuilt brick base, paint.
5. Rebuild brick pier 1 typ. Provide Simpson post bracket anchored to masonry for each post; 2 typ.
6. New shutter; see window schedule.
7. Rebuild brick fence base. Repoint and rebuild masonry, replace broken/spalled brick with new. Use salvaged exg. brick on visible faces.
8. Rehabilitate rafter tails. Dutchman and epoxy repairs.
9. Reset and level bluestone step on compacted gravel and sand base.
10. Consolidate cracked clapboard ends left side; preserve trellis holes, provide new wood plugs to fill missing on left and right sides.
11. Rehabilitate entablature woodwork. Replace failed Dutchman at panel stiles/rails and below threshold, epoxy repair threshold, replace missing band molding at pilasters.
12. Rehabilitate cornice/gutter. Document existing conditions along length of elevation; conditions vary. Remove and salvage existing wood gutter and sound trim. Rework fascia, blocking, substrate as req. and coordinate with roof eave and gutter work. All new trim/moldings to match existing; assume custom profiles.
13. Provide waterproof membrane under siding typ.
14. Rehabilitate junction of sun printer and building face. Dutchman 20 l.f. sill course, remove siding as required to install flashing and extend over top and sides of brace joints and over sill; paint.
15. Seal joint between drafting entrance and vault.
16. Remove vine holdfasts from siding.
17. Re-secure conduit and electrical lines to siding.
18. Clean heavy organic soiling at gutters and trim at sleeping porch on east and north sides.
19. Remove, salvage, and reinstall siding as required to inspect and repair substrate/sheathing.
20. Re-secure butt ends/joins at sheathing typ.
21. Repair decorative trim panel.
22. Replace deteriorated posts.
23. Restore spalled, damaged concrete stoop; custom aggregate and concrete mix to match existing materials.
Key Plan
DESIGNED:
CADD:
TECH REV:
DATE:
SUB SHEET
NO.:
SUB SHEET NO.:
CONSTRUCTION DOCUMENTS
seh seh
SEH
A2.5
4 0 4
SCALE OF FEET
1/4" = 1'-0"
PMIS
NO.:
SHEET
Scale: 1/4" = 1'-0" when printed full size on 22" x 34" sheet
U.N.O.
FREDERICK LAW OLMSTED NATIONAL HISTORIC SITE
PAINT HOUSE, IMPROVE ROOF PAINT OFFICE, IMPROVE ROOF
223735
223737 of 26
West Elevation - Office
West Elevation - Planting
A2.5
South Elevation - Planting
A2.5 A2.5
South Elevation - Office
A2.5
1/4" = 1'-0" 1/4" = 1'-0"
1/4" = 1'-0"
N.T.S.
03/01/2021
175030
West Office, South, West Planting
W1
W3
W1
W4
A3.2
WD
WD
WD
WD
WD
WD
WD
WD
WD
D100
WD
WD
SKY
WD
D101
WD
WD
WD
WD
A2.3 SIM
M1
M1
W3
E1
W3
NP
NP
NP
NP
NP
NP
NP
NP
NP
NP
NP
NP
NP
NP
NP
M1
M1
C1
M4
General Notes - Exterior
1. Notes are indicative of general areas of repair and intent of work. Quantities are estimates only; additional repairs may be required to meet the scope noted.
2. See window and door schedules for additional repairs which may encompass exterior trim, sills, and flashing work.
3. The entire structure will be primed and painted. Repair work noted is in addition to typical prep work required for exterior painting which may include caulking, patching, sanding, nailing, filling, cleaning, and the like.
4. All repairs shall be primed and back primed on all surfaces and cut ends as part of the repair work.
5. Dutchman/epoxy repairs are used to generally describe the type of work required;
see specifications for additional information on repair requirements.
6. Scarf all joints between existing and new woodwork; prime/backprime. If there are more than three joints in a 8'-0” section of running trim (water table, stringcourse/sill course, siding) requiring repair, replace in entirety.
7. Re-nail/re-secure all siding joins/scarfs.
8. Replace all ice melt cables; re-energize system and test. Cables typically exist on selected roof areas, in all gutters, and down all downspouts.
Key Notes - Exterior
W1 # Replace # l.f. of siding
W2 # Replace # l.f. of watertable
W3 # Replace # l.f. of string course/sill
W4 # Replace # l.f. of 1x trim
G1 Replace wood gutter section
C1 Remove organic staining
M1 # Repoint # s.f. of masonry
M2 # NOT USED
M3 # Rebuild # s.f. of masonry
M4# Brick replacement
M5 Parge masonry
S1 Fill and stabilize eroded area
E1# Epoxy consolidate/fill repair
1. Rehabilitate mortise and tenon shutter screen. Remove, rebuild joints as req., reinstall. See window schedule for shutter scope.
2. Rehabilitate hoist. Dutchman/epoxy repairs; add cap flashing nailed to top face;
paint.
3. Re-nail popped nails typ.
4. Rehabilitate fence. Replace deteriorated 4x6 posts (24 lf), bottom 2x8 rails (16 lf), secure lattice, re-secure to rebuilt brick base, paint.
5. Rebuild brick pier 1 typ. Provide Simpson post bracket anchored to masonry for each post; 2 typ.
6. New shutter; see window schedule.
7. Rebuild brick fence base. Repoint and rebuild masonry, replace broken/spalled brick with new. Use salvaged exg. brick on visible faces.
8. Rehabilitate rafter tails. Dutchman and epoxy repairs.
9. Reset and level bluestone step on compacted gravel and sand base.
10. Consolidate cracked clapboard ends left side; preserve trellis holes, provide new wood plugs to fill missing on left and right sides.
11. Rehabilitate entablature woodwork. Replace failed Dutchman at panel stiles/rails and below threshold, epoxy repair threshold, replace missing band molding at pilasters.
12. Rehabilitate cornice/gutter. Document existing conditions along length of elevation; conditions vary. Remove and salvage existing wood gutter and sound trim. Rework fascia, blocking, substrate as req. and coordinate with roof eave and gutter work. All new trim/moldings to match existing; assume custom profiles.
13. Provide waterproof membrane under siding typ.
14. Rehabilitate junction of sun printer and building face. Dutchman 20 l.f. sill course, remove siding as required to install flashing and extend over top and sides of brace joints and over sill; paint.
15. Seal joint between drafting entrance and vault.
16. Remove vine holdfasts from siding.
17. Re-secure conduit and electrical lines to siding.
18. Clean heavy organic soiling at gutters and trim at sleeping porch on east and north sides.
19. Remove, salvage, and reinstall siding as required to inspect and repair substrate/sheathing.
20. Re-secure butt ends/joins at sheathing typ.
21. Repair decorative trim panel.
22. Replace deteriorated posts.
23. Restore spalled, damaged concrete stoop; custom aggregate and concrete mix to match existing materials.
Key Plan
DESIGNED:
CADD:
TECH REV:
DATE:
SUB SHEET
NO.:
SUB SHEET NO.:
CONSTRUCTION DOCUMENTS
seh seh
SEH
A2.6
4 0 4
SCALE OF FEET
1/4" = 1'-0"
PMIS
NO.:
SHEET
Scale: 1/4" = 1'-0" when printed full size on 22" x 34" sheet
U.N.O.
FREDERICK LAW OLMSTED NATIONAL HISTORIC SITE
PAINT HOUSE, IMPROVE ROOF PAINT OFFICE, IMPROVE ROOF
223735
223737 of 26
North Elevation - Planting
South Elevation - Vault
A2.6
West Elevation - Drafting and Vault
A2.6 A2.6
1/4" = 1'-0"
1/4" = 1'-0"
1/4" = 1'-0"
03/01/2021
175030
North Planting, West, South Drafting and Vault
14'-0" +/-
B21
B22
B24
D2.2
D1.7
South
D1.8
B22
W3
W3
W2
ND
ND
ND
ND
ND
ND
ND
ND
ND
ND
ND
11'-2" +/-
9'-0" +/-
B17
B1
B2 B3
B7
B8B9
B10
B11
B6
D2.1
D1.5
D1.4
D1.1
North
D1.3 D1.2
B20
B5
B4
B25
B18
B19
D1.9
FENCE N.I.C.
22'-0" +/-
B16
B6
B13
B15
B6
B9
B12
B14
106 104
D1.6
General Notes - Barn
1. Provide hook and eye hardware at all screen doors.
2. All epoxy and dutchman repairs shall be sanded smooth, prepped, primed, and painted two finish coats.
3. Areas requiring repainting shall include the entire component. Paint to logical separation between elements not requiring painting to ensure that work blends with existing surfaces. Caulk all joints in areas requiring painting/repair.
4. Replace ice melt cables; re-energize system and test.
Key Notes - Barn Exterior - B#
1. Epoxy repair to wood head casing
2. Epoxy repair wood sill
3. Rake and repoint stone foundation below D1.1; level and reset step
4. Epoxy repair to corner board
5. Dutchman repair at eave return
6. Dutchman and epoxy repair at sill and casing
7. Epoxy repair at fascia above D2.1; sand smooth joint at gutter
8. Dutchman and epoxy repair at casing and sill window 102
9. Replace screen
10. Replace broken glass
11. Adjust screen door to close tightly
12. Scrape, prep, prime, and paint fascia entire length
13. Epoxy repairs at joint between sill and jamb
14. Prep, prime and paint clapboards
15. Remove sash, replace pins, prep, prime, paint
16. Paint watertable at right corner
17. Dutchman repair fascia
18. Epoxy repair rafter tail and joint between rafters
19. Dutchman repair sill; prep, prime, paint window casing/trim 206, 208
20. Dutchman repair corner board
21. Dutchman repair door D1.8 bottom; hide joint behind hinge; replace and paint vent; prep, prime, paint area between corner board and change in plane.
22. Prep, prime, paint casing at D2.2
23. Epoxy repair casing and sill at D1.7
24. Prep, prime and paint entire casing at window 205.
25. Remove gate; reset lower pintle, seal surround at both pintles. Epoxy repair cracked corner board; reinstall gate.
General Notes - Exterior
1. Notes are indicative of general areas of repair and intent of work. Quantities are estimates only; additional repairs may be required to meet the scope noted.
2. See window and door schedules for additional repairs which may encompass exterior trim, sills, and flashing work.
3. The entire structure will be primed and painted. Repair work noted is in addition to typical prep work required for exterior painting which may include caulking, patching, sanding, nailing, filling, cleaning, and the like.
4. All repairs shall be primed and back primed on all surfaces and cut ends as part of the repair work.
5. Dutchman/epoxy repairs are used to generally describe the type of work required;
see specifications for additional information on repair requirements.
6. Scarf all joints between existing and new woodwork; prime/backprime. If there are more than three joints in a 8'-0” section of running trim (water table, stringcourse/sill course, siding) requiring repair, replace in…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .