About this file

This document is an amendment to a solicitation for roof and water shedding system repairs at the Frederick Law Olmsted National Historic Site. The amendment provides responses to questions from prospective offerors, extends the response deadline to November 16th, and schedules a second pre-bid site visit on November 8th. The responses clarify that the project superintendent cannot fill the roles of both quality control manager and site safety officer, indicate that no hazmat report is available, define the scope of work in courtyard and perimeter areas, provide square footage for uncoated copper and EPDM roofing materials, and estimate quantities for wood gutters, downspouts, and subsurface drainage. The solicitation is issued by the National Park Service Northeast Region for repairs to improve the roof and water shedding systems at the Frederick Law Olmsted National Historic Site in Brookline, Massachusetts.

View the file

Other files for this federal contract opportunity

Other files attached to FRLA - WATER SHEDDING IMPROVEMENTS, newest first.
File Type Posted
Attachment_0004_-_Civil_with_markups_0003.pdf PDF
Sol_140P4321R0021_Amd_0002.pdf PDF
Sol_140P4321R0021_Amd_0001.pdf PDF
Sol_140P4321R0021.pdf PDF
B08_-_Attachment_0003_-_DOL_DBA_WD_MA20210001.pdf PDF
Attachment_0001_-_FRLA_Paint_House_and_Office_Improve_Roofs_Specifications.pdf PDF
Attachment_0002_-_FRLA_Drawings.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

140P4321R0021 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

Boston MA 02129-4543

PNN

Building I-1 Charlestown Navy Yard Boston National Historical Park

NPS, NER - NE MABO

11/05/20210003

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

08/24/2021

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

The purpose of this Amendment is to provide a response to questions received, and to schedule a second organized pre-bid site visit.

Therefore:

1) A response to all questions received is provided and attached, including Attachment 0004

- Civil with Markups.

2) A second organized pre-bid site visit is scheduled for 10:00 am EST on November 8, 2021.

All interested offerors shall meet at Frederick Law Olmsted National Historic Site, 99

Warren Street, Brookline, MA 02445.

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Jason Albright

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 4

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

140P4321R0021/0003

Legacy Doc #: NPS

Period of Performance: 11/01/2021 to 05/01/2023

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

Request for Quote Number 140P4321R0021 Repair and Improve Roof and Water Shedding Systems for Frederick Law Olmsted National Historic Site Amendment 0003

DESCRIPTION OF AMENDMENT/MODIFICATION

The following are a list of questions received for the Solicitation Number 140P4321R0021, Repair and Improve Roof and Water Shedding Systems for Frederick Law Olmsted National Historic Site.

1) Is it possible to arrange another site visit prior to the 10/29/21 bid date?

Answer:

Yes. The bid period will be extended to Tuesday November 16, 2021. A second site visit will be available on 11/8/2021 at 10:00 a.m.

2) Can the role of the Site Safety officer and the CQC Manager be performed by the Project Superintendent due to the dollar size magnitude of the project?

Answer: No. The project is large and complex enough to require that the Project Superintendent not be required to wear three hats. Per the specification [Section 01 40 00, 1,6 C page 3] the Project Manager or Superintendent may also perform the duties of the CQCS. However the CQCS must be on site when any work is being performed by the contractor or subcontractors. The Site Safety Officer must be fully qualified, able to manage and meet OSHA requirements and be separate from the Site Safety Officer and CQC Manager. The Site Safety Officer duties and qualifications should be fully detailed in the Accident Prevention Plan. The Site Safety Officer may perform other duties, but must also be on site when work by the contractor or subcontractors is being performed.

3) Is there a HAZ MAT report available for the buildings?

Answer: There is no Haz/Mat report available.

4) What extent/area and detail apply to sections 321100 & 329119?

Answer: The sections refer to the courtyard area that is defined by the Barn, Planting Room, Office, and House. The Courtyard is intended to be sloped at a 5% grade and over time there has been some erosion and settlement. As part of the stoop repair at the North entrance stabilized aggregate will be required to be added to restore the 5% slope and feather in the work for access. See note 2/A2.3 and note S1.

Section 329119 addresses selected areas around the immediate building perimeter that have lost material due to scouring from overflowing gutters as well as any spot

Request for Quote Number 140P4321R0021 Repair and Improve Roof and Water Shedding Systems for Frederick Law Olmsted National Historic Site Amendment 0003 grading/fill/restoration work required as part of the work of this contract. See notes 9 and S1. The S1 note generally refers to soil materials, however on some areas of the Courtyard materials will consist of stabilized aggregate to match the existing adjacent surface.

5) Reference Drawing A1.2,Key notes 6 &7 and B2:Is the extent of these items limited only to the allowance footage called per 2/A3.3 for at each indicated location?

Answer: Note 6 on A1.2 refers to a band of work along the entire perimeter of the House slate roof denoted by a boxed line on the south, east, and north. Note 7 refers to sections of deteriorated cornice that exist along the south, north, and east areas of the House.

Detail 2 and 4/A3.3 details existing conditions and proposed repairs to the cornice to correct/improve conditions. The “Remove and salvage for re-installation 4’-0” of exg.

slate roof at eave” should read “Remove and salvage for re-installation 5’-0” of exg. slate roof at eave”.

6) Reference Drawing A1.2,Key Notes14 & 16: Advise as to the square foot areas to be included in our proposal?

Answer:

Note 14 Uncoated Copper roofing area is: 500 s.f.

Note 16 EPDM roof area is: 950 s.f.

7) Reference Drawing A1.3,General Roof/Drainage Notes: Please identify as the extent / lineal footage/location for the Wood Gutter, Downspouts and Subsurface Drainage items?

Answer:

Wood Gutter: 800 l.f.

Downspout l.f.: 780 l.f.

Almost every gutter on the site with almost no exceptions is a wood gutter.

Currently only one of these gutters, on the west side of the office, is lined. On the main house, upper roof of the open third floor porch and the gutter on the north side of the barn are half round copper gutters. The drawings indicate gutter locations and there are black dots which indicate downspout locations.

The downspout l.f. noted above includes downspouts on the Barn

Subsurface Drainage Plan – See Attached. Blue highlighted lines indicate areas to investigate. Estimate 1000 l.f. of drainage.