Replace Selected AHUs and Remove from, existing geothermal System, Cooperative Oxford Lab, Oxford, MD Page 1 of 10
Statement of Work
Construction Services for Replacement of AHUs 2,3,5,and 9 and Remove Off of Existing Geothermal system at Cooperative Oxford Lab
1. ADMINISTRATIVE OVERVIEW:
Purpose: The purpose of this statement of work is to obtain construction services for replacement of four (4) Air Handling Units (AHUs) which are part of an existing HVAC/Geothermal system at Cooperative Oxford Lab (COL), main lab building, located at 904 S. Morris St., Oxford, MD 21654.
The units to be replaced are AHU-2, AHU-3, AHU-5, and AHU-9. The scope of work includes but is not limited to, all necessary utility improvements and tie-ins, supply of required materials, demolition, insulation, interior finishes, hardware and electrical service per plans and specifications. NOTE: All installed equipment shall have high-energy efficiency ratings and improve the energy efficiency of the building as a whole. The goal of this project is to remove the remaining four AHU;s off the existing geothermal system and allow them to operate independently from the geothermal system.
**If new ACCU’s can be installed and the existing AHU’s retrofitted with appropriate coils to support operations then we would prefer that above total replacement options.**
1.1 Background:
The COL main building is a 16,000 square foot building comprising 5,000 SF of laboratories with the remainder utilized as general office space. Building construction type is concrete slab on grade with brick and block walls with wood truss roof structure and asphalt shingle roofing. The original building was constructed in the early 1960’s with an addition constructed in the mid- 1990’s. Building heating and cooling is accomplished through air handling units, each equipped with dual temperature and dedicated heating water coils, and hydronic finned tube radiation along window walls and entry vestibules. The building’s heating water system consists of supply and return water piping, propane-fired boiler, circulating pump and ancillary equipment. The dual temperature system consists of a water source heat pump chiller primary/ secondary piping and pumping configuration, geothermal closed bore Ground Loop Heat Exchanger (GLHX) and condenser water pump. Supplemental ductless split DX heat pump units have been installed in laboratory spaces.
The building is served by nine (9) AHUs, which were originally installed in 1995 and retrofitted in 2008 when the geothermal system was installed. Four AHU’s remaining on the geothermal system are equipped with one dual temperature coil and one heating coil. Water from the heat pump chiller is circulated through the dual temperature coil providing heating or cooling depending on the building’s overall demand. On extremely cold days the boiler provides supplemental heating to the dedicated heating coil. All dual temperature and heating water coils are equipped with 3-way modulating control valves. The present HVAC/geothermal system at COL, originally installed in 2008, does not provide adequate heating, cooling and
Replace Selected AHUs and Remove from, existing geothermal System, Cooperative Oxford Lab, Oxford, MD Page 2 of 10 dehumidification to the main lab building and will be decommissioned after the removal of these four remaining AHU’s.
1.2 Key Personnel. The Contractor shall provide the names and contact information (including after hours, weekend and holiday) of key personnel to be assigned as project manager; lead mechanical and electrical engineers. Any changes or substitutions must be approved in advance by the Contracting Officer.
Replace Selected AHUs and Remove from, existing geothermal System, Cooperative Oxford Lab, Oxford, MD Page 3 of 10
2. STATEMENT OF WORK
2.1 Project Overview
The National Oceanic and Atmospheric Administration (NOAA) seeks to obtain a firm, fixed price for construction services from an HVAC construction/controls firm that will be able to successfully replace four existing AHU’s, removing the existing units off the existing geothermal system.
All improvements shall be constructed in accordance with the latest editions, supplements and revisions of the following criteria.
1. Uniform Federal Accessibility Standards (UFAS).
2. Local and State Building Codes.
3. Environmental and Federal Acquisition Regulations.
4. All codes having legal jurisdiction.
5. Utility Codes Fire Codes
6. Green Building requirements
Tasks
● Contractor shall provide a proposal for complete decommissioning, removal, and disposal of Existing:
Unit Number
Brand Model Serial Number
Tons Location
AHU-2 Magic Air
BVE20ABAAAAAG6AL
4AAAABM
W191117917 5 M-110A
AHU-3 Magic Air
BVE20ABAAAAAG6AL
4AAAABM
W191117916 5 M-110A
AHU-5 Magic Air
BVE20ABAAAAAG6AL
4AAAABM
W171101294 5 M-150A
AHU-9 Magic Air
BVE16ABAAAAACG6L
4AAAABM
W171101293 4 M-145A
● Contractor shall install new AHU’s (only if existing AHU’s cannot be outfitted with appropriate coils to support operations) and associated ACCU’s . New AHUs must be similar in size dimensions to old units in order to fit into existing ductwork and mechanical rooms.
Replace Selected AHUs and Remove from, existing geothermal System, Cooperative Oxford Lab, Oxford, MD Page 4 of 10
● Contractor shall program, commission, and ensure system compatibility of new installed AHU’s;
● Contractor shall inspect existing vent ducts and actuators for serviceability and repair as necessary;
● Contractor shall install secondary containment panels under new AHU’s;
● Contractor shall provide and install drain pan safety switch on each unit
● Contractor shall Test and Balance newly installed AHU’s and provide report;
● Contractor shall perform a space-by-space evaluation to determine all existing conditions affecting the work in this scope.
● Contractor shall dispose of project/construction trash daily off site.
● Contractor is advised that the building is occupied, and that the contractor is responsible to ensure that it is maintained in a weather tight condition while executing the AHU work. The contractor will be held liable for any damage caused to the building(s) and ancillary structures, and/or injury to the occupants resulting from the execution of the work or from not exercising proper precautionary protective measures. Any cost of repair/replacement resulting from damages shall be at the contractor's expense.
Site Visit: Potential bidders are highly encouraged to make a site visit. Potential bidders shall determine all existing conditions affecting the tasks in this Statement of Work and be familiar with site constraints, building layout and utility conditions for purposes of formulating proposals. It is the Contractor’s responsibility to confirm existing conditions and evaluate Statement of Work of the project requirements. Contractor must confirm the accuracy of dimensions on drawings.
Failure to determine existing conditions will not be considered a basis for granting additional compensation.
Strategy: The intent of the project is to remove the remaining AHU’s connected to the existing geothermal system off the geothermal system entirely.
a. Pump Control Strategies: Establish and implement Optimal Pump Control strategies for energy efficient operation without sacrificing system performance.
b. Building Schedule and Fan Mode Optimization: A major function of the HVAC system is to maintain the room temperature and humidity at a proper level that can meet both the thermal comfort and the indoor air quality requirements for the occupants. Completed system is expected to achieve 70-72 degrees in heating mode and 72-74 degrees in cooling mode.
Develop and implement an optimal sequence of operation and schedule equipment to minimize operational set points and energy consumption, while maintaining the required space set-points.
c. Commissioning Authority Coordination: Coordinate efforts to optimize system energy efficiency with independent Government furnished Commissioning Authority and installing trades (temperature control, test and balance, HVAC technicians, etc.). Include all costs of coordination of associated trades in the proposal. Demonstrate successful system operation and optimization to authorized Government representative and Contracting Officer (CO) prior to system acceptance.
Replace Selected AHUs and Remove from, existing geothermal System, Cooperative Oxford Lab, Oxford, MD Page 5 of 10
2.2 Contractor Example Projects
The Contractor shall provide, as part of the proposal, examples and details of at least two
(2) recent (within the last 5 years) commercial or institutional HVAC/geothermal projects on which they were the prime contractor and which are currently in operation. Projects within 170 miles of Oxford, MD are preferred. Two references, including names, titles, phone numbers and e-mail addresses, shall be provided for each project.
2.3 Construction Phase Requirements
a. Contractor is responsible for obtaining all building permits required by the local authority having jurisdiction.
b. Contractor shall provide submittal log no later than commencement of construction activities, including target dates for submission of each anticipated submittal.
c. Contractor shall provide the Government (COR) with copies of all shop drawings and submittals for review. Government shall have ten (10) working days to provide comments to the Contractor.
d. Government staff (COR)and facility personnel will inspect work on a regular basis to assure conformance with contract terms.
e. The Contractor shall have a qualified project manager on site at all times when work is being performed by the general contractor or any subcontractors.
f. The Contractor shall take into consideration that the construction work will be performed at an operational research facility with approximately 40 individuals working in the building daily and are dependent upon relatively comfortable temperature and humidity conditions. It may be necessary to adjust construction working hours, depending on duration of time AHUs will be out of service and ambient outdoor temperature and humidity conditions.
g. COL employees will not accept or sign for contractor deliveries. The contractor is responsible for all materials & equipment delivered at site. Contractor must assume delivery of materials at their home office or at COL for commencement of work.
h. All stored materials must be kept in such a manner to prevent any damage and prevent theft or entrance of persons other than contractor employees necessary to complete project tasks.
i. Construction areas are to be appropriately isolated from COL staff and ongoing COL work.
j. All wastes are to be removed at the Contractor’s expense and no materials are to be left onsite upon job completion. Daily cleanup is required.
k. Contractor is to provide: i) final as-built scale drawings and plans; ii) all operation/owner’s manuals; iii) training on new systems; and, iv) training on interface of new AHUs with existing HVAC software control systems.
2.4 Foreign Nationals and Background Checks:
Prior authorization must be obtained from the Department of Commerce Security Office for any foreign national performing work at the Cooperative Oxford Lab as defined in NAO 207-12.
Contractor employees must sign in at the front desk, present valid identification, and sign a visitors log declaring whether or not they are a US citizen every time they visit the COL. Sending a foreign
Replace Selected AHUs and Remove from, existing geothermal System, Cooperative Oxford Lab, Oxford, MD Page 6 of 10 national to perform work at the Oxford facility without notification and obtaining appropriate clearance will result in workers being turned away without obligation for any compensation to the Contractor for services rendered and will be grounds for contract termination.
The Contractor shall provide proof that all on-site employees are U.S. citizens or legal aliens.
The Contractor shall not employ personnel with felony convictions, or with a record of narcotics use, for work at COL. The Contractor is responsible for completing a security investigation on all employees prior to their commencement of work at the COL in connection with this contract.
2.5 Acceptance Requirements
Contractor shall notify the Government in writing a minimum of two weeks in advance of anticipated achievement of Substantial Completion, so that Government may schedule an Acceptance Inspection. Prior to the scheduled inspection, the Government must receive the following:
a. Contractor has signed a Certificate of Substantial Completion.
b. Any Permit(s) as applicable.
c. Documentation from 3rd Party Commissioning Agent indicating successful Commissioning of all systems. During commissioning, summary of each system element to be commissioned, each commissioning procedure to be executed, and all documentation required for the final commissioning. All documentation requirements for the project, which includes checklists for recorded inspections, startup, functional performance test, unit capacities, installation & operations instructions, etc.
d. The Government AE will verify Commissioning Report, Test & Balance report, all training requirements and review of the Owner’s Operational and Maintenance manual for the project.
e. Contractor’s punch list of any outstanding items
2.6 Project Close-Out Requirements
Within 30 days of Government Acceptance, the Contractor shall provide the following:
● Record Drawings, defined as design drawings updated to reflect as-built conditions.
● O&M manuals, warranties and licenses.
● Updated Punch List indicating that all outstanding items have been completed.
2.7 Meetings
The contractor shall conduct a Project Kick-off Meeting within 10 working days of contract award. At the Kick-off Meeting, provide a briefing of the Project Schedule. Provide an overview of the project design approach, and a list of any long-lead items that will require early submittal processing to maintain project schedule.
The contractor shall conduct weekly Progress Meetings throughout the project; to facilitate team discussion and resolution of issues, the contractor/project manager is to run meetings using a web- based conferencing platform such as “WebEx” or “GoToMeeting” or Google
Replace Selected AHUs and Remove from, existing geothermal System, Cooperative Oxford Lab, Oxford, MD Page 7 of 10
Hangouts. At the meetings, provide project status, 2-week look ahead, status on outstanding actions, and status of RFIs and submittals.
Meeting notes, summarizing issues discussed, decisions reached, action items and next steps, to be issued by e-mail to the project team within 24 hours of each meeting.
The contractor’s Project Manager and/or delegated representative must attend all project related meetings in order to provide updates; discuss/address issues/action items;
answer/address any questions pertaining to the project from the Government/team members;
and to accomplish the project per the requirements within a timely manner.
2.8 Schedule
The Contractor shall prepare and provide a project schedule for completion of all Construction, installation and commissioning work to achieve substantial completion within ninety (90) calendar days of the Notice to Proceed. Provide all schedules in pdf and in modifiable MS Project format. Provide weekly updates of the schedule to the Government showing actual dates work is started and completed.
2.9 Supplemental Requirements Contractor Initiated Changes.
After following award, the contractor initiated changes from the scope of work are subject to Government approval. All Contractor initiated changes must be separately documented and not presented as normal submission material. Government acceptance of normal submission documents shall not be deemed as approval of a Contractor initiated change. The Contractor must provide all information and materials necessary to satisfy the Government as to need, benefit, and/or comparability.
2.9.2 Computer Aided Design (CAD).
All record drawings and estimates shall conform to the GSA Region 3 CAD Deliverables Policy. This policy may be obtained at http://www.gsa.gov/midatlanticcadpolicy.
2.9.3 Government Documents
All “sensitive but unclassified” (SBU) building information, either in electronic or paper formats, shall have imprinted on each page of the information:
PROPERTY OF THE UNITED STATES GOVERNMENT
FOR OFFICIAL USE ONLY
Do not remove this notice Properly destroy documents when no longer needed
The following paragraph shall be included on the cover page of the information (such as the cover sheet on record drawings) and on the label of all magnetic media:
PROPERTY OF THE UNITED STATES GOVERNMENT
COPYING, DISSEMINATION, OR DISTRIBUTION OF THESE DRAWINGS, PLANS, OR
SPECIFICATIONS TO UNAUTHORIZED USERS IS PROHIBITED
Do not remove this notice http://www.gsa.gov/portal/content/101343
Replace Selected AHUs and Remove from, existing geothermal System, Cooperative Oxford Lab, Oxford, MD Page 8 of 10
Properly destroy documents when no longer needed The above statements shall be prominently labeled in bold-type in a size appropriate for the documents. On a set of construction drawings, for example, the statements shall be in a minimum of 14-point bold-type.
2.9.4 Construction Waste Management
The Contractor must identify all construction and demolition waste suitable for diversion from land-filling and describe diversion via reuse by the Government, salvage for use by others, recycling, etc., as appropriate, in the construction documents.
Diversion to the maximum extent possible, with a minimum requirement of 50% by weight, is to be specified and achieved by the construction/installation contractor. If 50% cannot be achieved, a justification must be generated by the Contractor and submitted for an approval by the Government. The Contractor shall refer to these links http://www.gsa.gov/portal/content/140703 and http://www.gsa.gov/portal/content/140703 for additional references and specific requirements.
1. All waste materials must be tracked through recycling and waste invoices, weigh station documentation, donation documentation, salvage documentation, etc. to demonstrate the overall quantity of waste and the percent of the total, which was diverted from the landfill. Provide COL documentation on quantity and weight of recycled and disposed waste.
2. At project closeout, the a final waste report must be submitted indicating all waste materials, where they were taken and the percent of the total waste that was diverted from the landfill.
2.9.5 Government Green Purchasing Policy
The Government green purchasing criteria and/or requirements will apply to ALL materials purchased in this project. The Contractor shall be cognizant of these requirements; and shall refer to the noted link http://www.gsa.gov/portal/content/140703 in order to further understand the Government’s green purchasing policy.
2.9.6 Conformance with Environmental Management Systems
The A/E shall perform work under this contract consistent with the relevant policies and objectives identified in the agency, organizational, or facility environmental management systems (EMS) set forth in the contract. The Contractor shall perform work in a manner that conforms to all appropriate Environmental Management Programs and Operational Controls identified by the agency, organizational, or facility EMS, and shall provide monitoring and measurement information as necessary for the organization to address environmental performance relative to the environmental, energy, and transportation management goals. In the event an environmental nonconformance or noncompliance associated with the contracted services is identified, the Contractor shall expeditiously take all necessary corrective or preventative actions. In the case of a noncompliance, the http://www.gsa.gov/portal/content/140703 http://www.gsa.gov/portal/content/140703 http://www.gsa.gov/portal/content/140703
Replace Selected AHUs and Remove from, existing geothermal System, Cooperative Oxford Lab, Oxford, MD Page 9 of 10
Contractor shall respond and take corrective action immediately. In the case of a nonconformance, the Contractor shall respond and take corrective action based on the time schedule established by the EMS Site Coordinator. In addition, the Contractor shall ensure that its employees are aware of the roles and responsibilities identified for them by the environmental management system and how those requirements affect the work performed under this contract. Those responsibilities shall include the following:
2.10 Conduct of Contractor Personnel
The Contractor’s employees are subject to and shall observe and comply with all applicable regulations, policies, and procedures. In accordance with established security regulations and safety policies, Contractor employees shall not enter restricted areas. The Contractor shall be responsible for the selection, certification, assignment, supervision, management, and control of employees with the advice of the NOAA Contracting Officer (CO) and the Contracting Officer’s Representative (COR) in the performance of all contract work. The removal from the job site of any employee shall not relieve the Contractor of the requirement to provide sufficient personnel to perform the terms and conditions of the contract. The Contractor’s employees shall not use offices, rooms, work areas, or any other undesignated areas for their own use. When a task is completed, such employees shall immediately leave the area. Contract personnel shall not use or operate telephones, radios, computer terminals, or any other Government or privately owned equipment or property without the express permission of the COL COR. The Contractor’s employees shall not disturb papers on desks, nor open desk drawers or cabinets. Breaks shall not be spent in offices or room areas, but taken only in the assigned break areas. While waiting for transportation, or while on work breaks, they shall not block or impede movement on ramps, doorways, corridors, or walkways.
Contractor employees must sign in at the front desk, present valid identification, and sign a visitors log declaring whether or not they are a US citizen every time they visit the COL.
2.11 Work Schedules/Shifts
The Contractor shall accomplish all work for the COL during the hours of 7:30am and 4:30 pm Monday through Friday, excluding Federal Holidays. Weekend or Federal Holiday work is generally not permitted.
2.12 Government Requirements
In order to comply with the Debt Collection Improvement Act of 1966, Contractors must be registered in the System for Award Management (SAM) to be considered for award of a federal contract. For information regarding SAM registration, contact the SAM website at www.sam.gov.
Contractor’s must note on their proposal if they accept payment by credit card, list any pertinent GSA contract information along with effective contract dates, and provide a DUNs number.
2.13 Point of Contact
Greg Wilson, Contracting Officer Representative & Project Manager NOAA, National Ocean Service National Centers for Coastal Ocean Science https://www.sam.gov/portal/public/SAM/
Replace Selected AHUs and Remove from, existing geothermal System, Cooperative Oxford Lab, Oxford, MD Page 10 of 10
Cooperative Oxford Laboratory 904 South Morris Street Oxford, Maryland 21654-9724 Phone: (443) 684-5393 FAX: (410) 226-5925 greg.wilson@noaa.gov mailto:greg.wilson@noaa.gov
| 1. ADMINISTRATIVE OVERVIEW: |
| **If new ACCU’s can be installed and the existing AHU’s retrofitted with appropriate coils to support operations then we would prefer that above total replacement options.** |
| 1.1 Background: |
| 2. STATEMENT OF WORK |
| Tasks |
| 2.2 Contractor Example Projects |
| 2.3 Construction Phase Requirements |
| 2.4 Foreign Nationals and Background Checks: |
| 2.5 Acceptance Requirements |
| 2.6 Project Close-Out Requirements |
| 2.7 Meetings |
| 2.8 Schedule |
| 2.9 Supplemental Requirements Contractor Initiated Changes. |
| 2.9.2 Computer Aided Design (CAD). |
| 2.9.3 Government Documents |
| 2.9.4 Construction Waste Management |
| 2.9.5 Government Green Purchasing Policy |
| 2.9.6 Conformance with Environmental Management Systems |
| 2.10 Conduct of Contractor Personnel |
| 2.11 Work Schedules/Shifts |
| 2.12 Government Requirements |
| 2.13 Point of Contact |