This is a template form (ENG Form 4025, May 2017) used by the U.S. Army Corps of Engineers (USACE) for contractors to submit shop drawings, equipment data, material samples, and manufacturer's certificates of compliance for approval. The form is governed by ER 415-1-10 with the proponent agency being CECW-CE.

Section I of the form requires contractors to initiate the submittal request and provide detailed information including: the recipient (USACE office), contractor name and contract number, specification section number, project title and location, transmittal type, and item descriptions with model numbers. Contractors must also indicate whether the transmittal is new or a resubmittal, check applicable categories (FIO, GA, DA, CR, DA/CR, DA/GA), and reference relevant specification paragraphs and drawing sheet numbers. Column entries require submittal type codes (SD-01 through SD-11, ranging from preconstruction to closeout documentation), the number of copies, contractor review codes, and whether a variation from contract requirements is being requested with justification in the remarks section. Section II requires the approving authority to certify review and assign submittal action codes (A through X, including approval as submitted, approval with noted exceptions, disapproval, or receipt acknowledgment) along with signature and date. Instructions specify that transmittals be numbered consecutively using specification section numbers and sequential numbering, that each transmittal cover only one specification section, and that approval does not relieve contractors from full contract compliance.

View the file

Other files

File Type Posted
Solicitation Amendment W51EW726RA0020004 SF 30.pdf PDF
Attachment 0014 - Hazardous Material Survey Report 04MAY2026.pdf PDF
Attachment 0001 - NCR MATOC SOW 24APR2026 v2.pdf PDF
Attachment 0012 - Seed Project SOW Floor Plan Layout.pptx PPTX presentation
Attachment 0011 - NCR MATOC QA A0003 Rev1.pdf PDF
Attachment 0008 - NCR MATOC Section L v6.pdf PDF
Attachment 0004 - Seed Project SOW 15APR2026 v2.pdf PDF
Solicitation Amendment W51EW726RA0020003 SF 30.pdf PDF
Solicitation Amendment W51EW726RA0020002 SF 30.pdf PDF
Solicitation Amendment W51EW726RA0020001 SF 30.pdf PDF
Attachment 0010 - NCR MATOC QA A0001.pdf PDF
Attachment 0009 - NCR MATOC Section M v4.pdf PDF
Attachment 0008 - NCR MATOC Section L v5.pdf PDF
Attachment 0007 - Seed Project Site Visit Map.pptx PPTX presentation
Attachment 0006 - Contractor Bid Sheet.xlsx XLSX spreadsheet
61 - Attachment 0004 SEED PROJ SOW 1991 ENL BRKS PH 4 3rd FLR DOM 041861.pdf PDF
55 - Attachment 0004 SEED PROJ SOW 1991 ENL BRKS PH 4 DWG INDEX 041710.pdf PDF
40 - Attachment 0004 SEED PROJ SOW 1991 ENL BRKS PH 4 EQP SCHD 041834.pdf PDF
32 - Attachment 0004 SEED PROJ SOW 2008 Panel Schedules Overall Renov 072831.pdf PDF
27 - Attachment 0004 SEED PROJ SOW 1991 ENL BRKS PH 4 LEGD 041881.pdf PDF
26 - Attachment 0004 SEED PROJ SOW 1991 ENL BRKS PH 4 DEMO SITE PLAN 041875.pdf PDF
23 - Attachment 0004 SEED PROJ SOW 1991 ENL BRKS PH 4 2nd 3rd FLR RECEPT 041886.pdf PDF
20 - Attachment 0004 SEED PROJ SOW 1991 ENL BRKS PH 4 1st FLR PWR 041887.pdf PDF
16 - Attachment 0004 SEED PROJ SOW Attach 1991 ENCLOSURE.pdf PDF
6 - Attachment 0004 SEED PROJ SOW Attach 1991 ENL BRKS PH 4 CLG PLN 041761.pdf PDF
Attachment 0001_SOW APPENDIX 2.7.3 JBMHH DPW Fillable Excavation Permit.pdf PDF
Attachment 0001_SOW APPENDIX 2.7.2 JBMHH Dig Permit Process.pdf PDF
Attachment 0001_SOW Attachment 1.8 - Equipment Warranty Tag Form.pdf PDF
Attachment 0001_SOW Attachment 1.7 - Project Schedule_v1.xlsx XLSX spreadsheet
Attachment 0001_SOW Attachment 1.4 - Site Specific Requirements.pdf PDF
Attachment 0001_SOW Attachment 1.3 - Daily Report Template.pdf PDF
Attachment 0008 - NCR MATOC Section L v4.pdf PDF
68 - Attachment 0004 SEED PROJ SOW 1991 ENL BRKS PH 4 SECT DETS 041810.pdf PDF
67 - Attachment 0004 SEED PROJ SOW 1991 ENL BRKS PH 4 ROOF FRM PLN 041805.pdf PDF
59 - Attachment 0004 SEED PROJ SOW 1991 ENL BRKS PH 4 2nd FLR DOM 041860.pdf PDF
56 - Attachment 0004 SEED PROJ SOW 1991 ENL BRKS PH 4 TITLE SHT 041709.pdf PDF
51 - Attachment 0004 SEED PROJ SOW 2020 MECH PLMB ALTER 1st FLR BTH 085811.pdf PDF
44 - Attachment 0004 SEED PROJ SOW 1991 ENL BRKS PH 4 PROF SW MTW 041853.pdf PDF
33 - Attachment 0004 SEED PROJ SOW 1991 ENL BRKS PH 4 2nd 3rd FLR PLN 041825.pdf PDF
37 - Attachment 0004 SEED PROJ SOW 1991 ENL BRKS PH 4 DETS 041837.pdf PDF
34 - Attachment 0004 SEED PROJ SOW 1991 ENL BRKS PH 4 CONT DIAG 041828.pdf PDF
35 - Attachment 0004 SEED PROJ SOW 1991 ENL BRKS PH 4 CONT DIAG 041835.pdf PDF
8 - Attachment 0004 SEED PROJ SOW Attach 1991 ENL BRKS PH 4 SIGNAGE 1st 041797.pdf PDF
5 - Attachment 0004 SEED PROJ SOW Attach 1991 ENL BRKS PH 4 DOOR SCHD 041786.pdf PDF
1 - Attachment 0004 SEED PROJ SOW Attach 1991 ENL BRKS PH 4 ELEV 041759 2.pdf PDF
Attachment 0004 - Seed Project SOW 25FEB2026 2.pdf PDF
Attachment 0003 - Past Performance Questionnaire.docx DOCX document
Attachment 0001_SOW APPENDIX 2.7.4 JBMHH Excavation Permit SOP June 2023.pdf PDF
Attachment 0001_SOW APPENDIX 2.1.3 APG Excavation Permit.pdf PDF
Attachment 0001 - NCR MATOC SOW 10FEB2026.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ENG FORM 4025, MAY 2017 PREVIOUS EDITIONS ARE OBSOLETE. Page 1 of 2

U.S. Army Corps of Engineers (USACE)

TRANSMITTAL OF SHOP DRAWINGS, EQUIPMENT DATA, MATERIAL SAMPLES, OR

MANUFACTURER'S CERTIFICATES OF COMPLIANCE

For use of this form, see ER 415-1-10; the proponent agency is CECW-CE.

DATE TRANSMITTAL NO.

SECTION I - REQUEST FOR APPROVAL OF THE FOLLOWING ITEMS (This section will be initiated by the contractor)

TO:

PROJECT TITLE AND LOCATIONSPECIFICATION SEC. NO. (Cover only one section with each transmittal)

FROM: CONTRACT NO. CHECK ONE:

THIS TRANSMITTAL IS FOR: (Check one)

THIS IS A NEW TRANSMITTAL

THIS IS A RESUBMITTAL OF

TRANSMITTAL

FIO GA DA CR DA/CR DA/GA

ITEM

NO.

(See

Note 3)

USACE

ACTION

CODE

(Note 9)

SUBMITTAL

TYPE CODE

(See Note 8)

NO.

OF

COPIES

SPEC.

PARA. NO.

DRAWING

SHEET NO.

CONTRACTOR

REVIEW

CODE

VARIATION

Enter "Y" if requesting a variation

(See Note 6)

DESCRIPTION OF SUBMITTAL ITEM

(Type size, model number/etc.)

a. i.c. d. e. f. g. h.b.

CONTRACT DOCUMENT

REFERENCE

REMARKS

SECTION II - APPROVAL ACTION

I certify that the above submitted items had been reviewed in detail and are correct and in strict conformance with the contract drawings and specifications except as otherwise stated.

NAME OF CONTRACTOR SIGNATURE OF CONTRACTOR

NAME AND TITLE OF APPROVING AUTHORITY SIGNATURE OF APPROVING AUTHORITY DATEENCLOSURES RETURNED (List by item No.)

ENG FORM 4025, MAY 2017 Page 2 of 2

INSTRUCTIONS

1. Section I will be initiated by the Contractor in the required number of copies.

2. Each Transmittal shall be numbered consecutively. The Transmittal Number typically includes two parts separated by a dash (-). The first part is the specification section number. The second part is a sequential number for the submittals under that spec section. If the Transmittal is a resubmittal, then add a decimal point to the end of the original Transmittal Number and begin numbering the resubmittal packages sequentially after the decimal.

3. The "Item No." for each entry on this form will be the same "Item No." as indicated on ENG FORM 4288-R.

4. Submittals requiring expeditious handling will be submitted on a separate ENG Form 4025-R.

5. Items transmitted on each transmittal form will be from the same specification section. Do not combine submittal information from different specification sections in a single transmittal.

6. If the data submitted are intentionally in variance with the contract requirements, indicate a variation in column h, and enter a statement in the Remarks block describing he detailed reason for the variation.

7. ENG Form 4025-R is self-transmitting - a letter of transmittal is not required.

8. When submittal items are transmitted, indicate the "Submittal Type" (SD-01 through SD-11) in column c of Section I.

Submittal types are the following:

SD-01 - Preconstruction SD-02 - Shop Drawings SD-03 - Product Data SD-04 - Samples SD-05 - Design Data SD-06 - Test Reports

SD-07 - Certificates SD-08 - Manufacturer's Instructions SD-09 - Manufacturer's Field Reports SD-10 - O&M Data SD-11 - Closeout

9. For each submittal item, the Contractor will assign Submittal Action Codes in column g of Section I. The U.S. Army Corps of Engineers approving authority will assign Submittal

Action Codes in column i of Section I. The Submittal Action Codes are:

A -- Approved as submitted.

B -- Approved, except as noted on drawings. Resubmission not required.

C -- Approved, except as noted on drawings. Refer to attached comments.

Resubmission required.

D -- Will be returned by separate correspondence.

E -- Disapproved. Refer to attached comments.

10. Approval of items does not relieve the contractor from complying with all the requirements of the contract.

F -- Receipt acknowledged.

X -- Receipt acknowledged, does not comply with contract requirements, as noted.

G -- Other action required (Specify)

K -- Government concurs with intermediate design. (For D-B contracts)

R -- Design submittal is acceptable for release for construction. (For D-B contracts)

ENG FORM 4025, MAY 2017

PREVIOUS EDITIONS ARE OBSOLETE.

Page of

ENG FORM 4025, MAY 2017

Page of U.S. Army Corps of Engineers (USACE)

TRANSMITTAL OF SHOP DRAWINGS, EQUIPMENT DATA, MATERIAL SAMPLES, OR

MANUFACTURER'S CERTIFICATES OF COMPLIANCE

For use of this form, see ER 415-1-10; the proponent agency is CECW-CE.

SECTION I - REQUEST FOR APPROVAL OF THE FOLLOWING ITEMS (This section will be initiated by the contractor)

CHECK ONE:

THIS TRANSMITTAL IS FOR: (Check one)

ITEM

NO.

(See Note 3)

USACE

ACTION

CODE

(Note 9)

SUBMITTAL

TYPE CODE

(See Note 8)

NO.

OF

COPIES

SPEC.

PARA. NO.

DRAWING

SHEET NO.

CONTRACTOR

REVIEW

CODE

VARIATION

Enter "Y" if requesting a variation (See Note 6)

DESCRIPTION OF SUBMITTAL ITEM

(Type size, model number/etc.)

a.

i.

c.

d.

e.

f.

g.

h.

b.

CONTRACT DOCUMENT

REFERENCE

SECTION II - APPROVAL ACTION

I certify that the above submitted items had been reviewed in detail and are correct and in strict conformance with the contract drawings and specifications except as otherwise stated.

INSTRUCTIONS

1. Section I will be initiated by the Contractor in the required number of copies.

2. Each Transmittal shall be numbered consecutively. The Transmittal Number typically includes two parts separated by a dash (-). The first part is the specification section number. The second part is a sequential number for the submittals under that spec section. If the Transmittal is a resubmittal, then add a decimal point to the end of the original Transmittal Number and begin numbering the resubmittal packages sequentially after the decimal.

3. The "Item No." for each entry on this form will be the same "Item No." as indicated on ENG FORM 4288-R.

4. Submittals requiring expeditious handling will be submitted on a separate ENG Form 4025-R.

5. Items transmitted on each transmittal form will be from the same specification section. Do not combine submittal information from different specification sections in a single transmittal.

6. If the data submitted are intentionally in variance with the contract requirements, indicate a variation in column h, and enter a statement in the Remarks block describing he detailed reason for the variation.

7. ENG Form 4025-R is self-transmitting - a letter of transmittal is not required.

8. When submittal items are transmitted, indicate the "Submittal Type" (SD-01 through SD-11) in column c of Section I.

Submittal types are the following:

SD-01 - Preconstruction SD-02 - Shop Drawings SD-03 - Product Data SD-04 - Samples SD-05 - Design Data SD-06 - Test Reports

SD-07 - Certificates SD-08 - Manufacturer's Instructions SD-09 - Manufacturer's Field Reports SD-10 - O&M Data SD-11 - Closeout

9. For each submittal item, the Contractor will assign Submittal Action Codes in column g of Section I. The U.S. Army Corps of Engineers approving authority will assign Submittal Action Codes in column i of Section I. The Submittal Action Codes are:

A -- Approved as submitted. B -- Approved, except as noted on drawings. Resubmission not required. C -- Approved, except as noted on drawings. Refer to attached comments. Resubmission required. D -- Will be returned by separate correspondence. E -- Disapproved. Refer to attached comments.

10. Approval of items does not relieve the contractor from complying with all the requirements of the contract.

F -- Receipt acknowledged.

X -- Receipt acknowledged, does not comply with contract requirements, as noted.

G -- Other action required (Specify) K -- Government concurs with intermediate design. (For D-B contracts) R -- Design submittal is acceptable for release for construction. (For D-B contracts) 1.0 darwin.chen@usace.army.mil 2017-05-24 Forms Design Team Darwin Chen

TRANSMITTAL OF SHOP DRAWINGS, EQUIPMENT DATA, MATERIAL SAMPLES, OR

MANUFACTURER'S CERTIFICATES OF COMPLIANCE

2017-05-24

PrintButton1:
saveas:
EmailSubmitButton1:
CurrentPage:
PageCount:
No1_DateTime:
No2_Transmittal:
No3_To: Dept. of the Army - U.S. Army MICC

Contract Division - 45 West Street Fort Drum, NY 13602

No8_Pro_Title: Repair, Rehab & minor Const. (RRC)
No7_Specification:
No4_From:
No5_Cont_No:
No6a_CheckBox: 1
No6b_CheckBox: 0
No6_Transmittal:
No9a_CheckBox: 0
No9b_CheckBox: 1
No9c_CheckBox: 0
No9d_CheckBox: 0
No9e_CheckBox: 0
No9f_CheckBox: 0
ITEM NO. (See Note 3):
DESCRIPTION OF SUBMITTAL ITEM

(Type size, model number/etc.):

SUBMITTAL TYPE CODE (See Note 8):
NO. OF COPIES: 1
SPEC. PARA. NO.:
DRAWING SHEET NO. :
CONTRACTOR REVIEW CODE
VARIATION Enter "Y" if requesting a variation (See Note 6):
USACE ACTION CODE (Note 9) :
Remarks: This submittal contains
Contractor_Name:
Contractor_Signature:
Authority_Name:
Authority_Signature:
Authority_DateTime:
Enclosures: