This document is a process flowchart depicting the Dig Permit Process for excavation work. The process begins when a completed JMRHH-1254 form is submitted via email or in person to the Excavation Permit Coordinator (EPC). The EPC reviews the form for proper information, documentation, and schematics, determining whether it was filed out properly.

If the form is properly completed, the EPC assesses whether the work constitutes an emergency. For non-emergency requests, the EPC communicates receipt within ten business days and schedules execution with the requestor. For emergency requests, the EPC immediately contacts the O&M Chief or Director for coordination and requires O&M Leadership to contact Miss Utilities and the National Electrical Code (NEC) immediately. The EPC then emails the 1254 documentation to the Shop Foreman and NEC for execution, with the Army Material Command (ArMA) EPC creating a case and image. The Government Fleet Evaluation Board (GFEBS) IW28 EPC converts the notification to a Work Order and assigns it to the appropriate Work Center. Simultaneously, the EPC cross-references the permit under the relevant Service Order/Work Order/Project field, adds information to the Dig Permit Tracker on SharePoint, and reviews daily for status updates. Once all trades are complete, the EPC follows up with NEC and O&M personnel, inputs the permit expiration date (30 days from issuance), emails the requestor an approved Excavation Permit, and updates the Dig Permit Tracker. The requestor is responsible for upkeep of markings. Extension requests follow a separate process where the requestor submits an extension request, the EPC submits a memorandum to the Branch Chief for review and approval, and the Branch Chief approves and returns approval via email, with total extensions not exceeding 180 days.

View the file

Other files

File Type Posted
Solicitation Amendment W51EW726RA0020004 SF 30.pdf PDF
Attachment 0014 - Hazardous Material Survey Report 04MAY2026.pdf PDF
Attachment 0001 - NCR MATOC SOW 24APR2026 v2.pdf PDF
Solicitation Amendment W51EW726RA0020001 SF 30.pdf PDF
Attachment 0007 - Seed Project Site Visit Map.pptx PPTX presentation
Attachment 0006 - Contractor Bid Sheet.xlsx XLSX spreadsheet
61 - Attachment 0004 SEED PROJ SOW 1991 ENL BRKS PH 4 3rd FLR DOM 041861.pdf PDF
55 - Attachment 0004 SEED PROJ SOW 1991 ENL BRKS PH 4 DWG INDEX 041710.pdf PDF
40 - Attachment 0004 SEED PROJ SOW 1991 ENL BRKS PH 4 EQP SCHD 041834.pdf PDF
32 - Attachment 0004 SEED PROJ SOW 2008 Panel Schedules Overall Renov 072831.pdf PDF
27 - Attachment 0004 SEED PROJ SOW 1991 ENL BRKS PH 4 LEGD 041881.pdf PDF
26 - Attachment 0004 SEED PROJ SOW 1991 ENL BRKS PH 4 DEMO SITE PLAN 041875.pdf PDF
23 - Attachment 0004 SEED PROJ SOW 1991 ENL BRKS PH 4 2nd 3rd FLR RECEPT 041886.pdf PDF
20 - Attachment 0004 SEED PROJ SOW 1991 ENL BRKS PH 4 1st FLR PWR 041887.pdf PDF
16 - Attachment 0004 SEED PROJ SOW Attach 1991 ENCLOSURE.pdf PDF
6 - Attachment 0004 SEED PROJ SOW Attach 1991 ENL BRKS PH 4 CLG PLN 041761.pdf PDF
Attachment 0001_SOW APPENDIX 2.7.3 JBMHH DPW Fillable Excavation Permit.pdf PDF
Attachment 0001_SOW Attachment 1.8 - Equipment Warranty Tag Form.pdf PDF
Attachment 0001_SOW Attachment 1.7 - Project Schedule_v1.xlsx XLSX spreadsheet
Attachment 0001_SOW Attachment 1.4 - Site Specific Requirements.pdf PDF
Attachment 0001_SOW Attachment 1.3 - Daily Report Template.pdf PDF
69 - Attachment 0004 SEED PROJ SOW 2020 Title Sheet Alter 1st Flr BTH 085806.pdf PDF
66 - Attachment 0004 SEED PROJ SOW 1991 ENL BRKS PH 4 FDN PLN 041804.pdf PDF
63 - Attachment 0004 SEED PROJ SOW 1991 ENL BRKS PH 4 PLUMB PLN 041872.pdf PDF
60 - Attachment 0004 SEED PROJ SOW 1991 ENL BRKS PH 4 2nd FLR DRN 041856.pdf PDF
54 - Attachment 0004 SEED PROJ SOW 1991 ENL BRKS PH 4 1st FLR DOM WTR 041859.pdf PDF
53 - Attachment 0004 SEED PROJ SOW 1991 ENL BRKS PH 4 ATTIC FLR PLN 041826.pdf PDF
50 - Attachment 0004 SEED PROJ SOW 2020 MECH PLMB ALTER 1ST FLR BTH 085810.pdf PDF
47 - Attachment 0004 SEED PROJ SOW 2014 WTR BFLW DEVICE 079606.pdf PDF
46 - Attachment 0004 SEED PROJ SOW 2007 MECH PLN UPGD 054886.pdf PDF
43 - Attachment 0004 SEED PROJ SOW 1991 ENL BRKS PH 4 MTW DETS 041854.pdf PDF
36 - Attachment 0004 SEED PROJ SOW 1991 ENL BRKS PH 4 DETS 041836.pdf PDF
31 - Attachment 0004 SEED PROJ SOW 1991 ENL BRKS PH 4 SITE PLN 041877.pdf PDF
30 - Attachment 0004 SEED PROJ SOW 1991 ENL BRKS PH 4 PWR RISR SIG 041891.pdf PDF
28 - Attachment 0004 SEED PROJ SOW 1991 ENL BRKS PH 4 LTG FIX SCHED 041882.pdf PDF
25 - Attachment 0004 SEED PROJ SOW 1991 ENL BRKS PH 4 ATTIC SIG 041890.pdf PDF
24 - Attachment 0004 SEED PROJ SOW 1991 ENL BRKS PH 4 2nd 3rd FLR SIG 041889.pdf PDF
19 - Attachment 0004 SEED PROJ SOW 1991 ENL BRKS PH 4 1st FLR LHTG 041883.pdf PDF
17 - Attachment 0004 SEED PROJ SOW 2020 Legends Alter 1st FLR BTH 085812.pdf PDF
12 - Attachment 0004 SEED PROJ SOW Attach 1991 EBK VBRJS OG 4 TLT PLNS 041784.pdf PDF
11 - Attachment 0004 SEED PROJ SOW Attach 1991 ENL BRKS PH 4 STAIR PLNS 041783.pdf PDF
9 - Attachment 0004 SEED PROJ SOW Attach 1991 ENL BRKS PH 4 SIGNAGE 2nd 041798.pdf PDF
3 - Attachment 0004 SEED PROJ SOW Attach 1991 ENL BRKS PH 4 1st FLR PLN 041753.pdf PDF
Attachment 0002 - NCR MATOC Rate Sheet - NTE.xlsx XLSX spreadsheet
Attachment 0001_SOW APPENDIX 2.7.8 MYER DPW Excavation Permit.pdf PDF
Attachment 0001_SOW APPENDIX 2.7.7 JBMHH Schematic Outline.pdf PDF
Attachment 0001_SOW APPENDIX 2.7.1 JBMHH Color Map.pdf PDF
Attachment 0001_SOW APPENDIX 2.1.2 APG Environmental Requirements.pdf PDF
Attachment 0001_SOW Attachment 1.6 - Engineering Form 4025.pdf PDF
Attachment 0001_SOW Attachment 1.5 - QCR Submittal Form.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .