Attachment 0001_SOW Attachment 1.7 - Project Schedule_v1.xlsx
XLSX spreadsheet 59 KB Posted
- Solicitation number
- W51EW7-26-R-A002
About this file
This is a Project Schedule (Gantt Chart) attachment for a Statement of Work related to the Franklin Commuter Line over East Street Bridge Replacement project under MBTA Contract No. B92PS24, Task Order No. 6. The schedule was created on December 10, 2018, with a beginning date of November 10, 2018, and reflects work planned through June 6, 2019.
The schedule encompasses six major phases totaling approximately 715 days of effort across multiple work packages. Phase 1 (Project Management) runs November 10, 2018 to June 6, 2019 with 209 man-hours and includes Notice to Proceed, Task Specific QA Plan, and Task Specific Project Management Plan. Phase 2 (Analysis of Existing Conditions) spans November 14, 2018 to March 19, 2019 with 125 man-hours, covering research and review of available data, field inspections, MBTA ROW/Safety Training, and preliminary environmental assessments. Phase 3 (Topographic and Property Survey) runs November 14, 2018 to February 12, 2019 with 90 man-hours for field surveys and drawing preparation. Phase 4 (Geotechnical Investigation) covers November 14, 2018 to February 12, 2019 with 90 man-hours, including coordination with Keolis GZA, utility clearance, field drilling, lab testing, and geotechnical reporting. Phase 5 (Bridge Type Study Report) extends from January 2, 2019 to June 6, 2019 with 155 man-hours, encompassing substructure evaluation, superstructure replacement alternatives, construction sequencing concepts, roadway evaluation, clearance mitigation alternatives, detour planning, and MBTA review and finalization. Phase 6 (Value Analysis) runs January 2, 2019 to March 19, 2019 with 76 man-hours for value engineering, constructability analysis, quantity takeoffs, cost analysis, and project scheduling across all project alternatives.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REV01
| 1.0 | 0.0 | 43414.0 | 43421.0 | 43428.0 | 43435.0 | 43442.0 | 43449.0 | 43456.0 | 43463.0 | 43470.0 | 43477.0 | 43484.0 | 43491.0 | 43498.0 | 43505.0 | 43512.0 | 43519.0 | 43526.0 | 43533.0 | 43540.0 | 43547.0 | 43554.0 | 43561.0 | 43568.0 | 43575.0 | 43582.0 | 43589.0 | 43596.0 | 43603.0 | 43610.0 | 43617.0 | 43624.0 | 43631.0 | 43638.0 | 43645.0 | 43652.0 | 43659.0 | 43666.0 | 43673.0 | 43680.0 | 43687.0 | 43694.0 | 43701.0 | 43708.0 | 43715.0 | 43722.0 | 43729.0 | 43736.0 | |
| Time Period | |||||||||||||||||||||||||||||||||||||||||||||||||
| Weekly |
| Gantt Chart Dates | |||
| Beginning Date | 11/10/18 | Updated: | 12/10/18 |
| Today | 9/15/25 | By: | COR |
| 2018 | 2019 | ||||||||||||||||||||||||||||||||||||||||||||||||
| (format critical path tasks in red text below) | Start | End | Task | Nov | Nov | Nov | Dec | Dec | Dec | Dec | Dec | Jan | Jan | Jan | Jan | Feb | Feb | Feb | Feb | Mar | Mar | Mar | Mar | Mar | Apr | Apr | Apr | Apr | May | May | May | May | Jun | Jun | Jun | Jun | Jun | Jul | Jul | Jul | Jul | Aug | Aug | Aug | |||||
| Level | Sr. No. | Task | Resource/MH | Date | Date | Duration (days) | 10 | 17 | 24 | 1 | 8 | 15 | 22 | 29 | 5 | 12 | 19 | 26 | 2 | 9 | 16 | 23 | 2 | 9 | 16 | 23 | 30 | 6 | 13 | 20 | 27 | 4 | 11 | 18 | 25 | 1 | 8 | 15 | 22 | 29 | 6 | 13 | 20 | 27 | 3 | 10 | 17 | ||
| 1 | P | 1 | Project Management | 11/10/2018 | 6/6/19 | 209 | |||||||||||||||||||||||||||||||||||||||||||
| A | 1.1 | Notice to Proceed | 11/10/2018 | 11/13/2018 | 3 | 1.1 | 43414.0 | 43421.0 | 43428.0 | 43435.0 | 43442.0 | 43449.0 | 43456.0 | 43463.0 | 43470.0 | 43477.0 | 43484.0 | 43491.0 | 43498.0 | 43505.0 | 43512.0 | 43519.0 | 43526.0 | 43533.0 | 43540.0 | 43547.0 | 43554.0 | 43561.0 | 43568.0 | 43575.0 | 43582.0 | 43589.0 | 43596.0 | 43603.0 | 43610.0 | 43617.0 | 43624.0 | 43631.0 | 43638.0 | 43645.0 | 43652.0 | 43659.0 | 43666.0 | 43673.0 | 43680.0 | 43687.0 | 43694.0 | ||
| A | 1.2 | Task Specific QA Plan | 20 | 11/26/2018 | 12/14/2018 | 18 | 1.2 | 43414.0 | 43421.0 | 43428.0 | 43435.0 | 43442.0 | 43449.0 | 43456.0 | 43463.0 | 43470.0 | 43477.0 | 43484.0 | 43491.0 | 43498.0 | 43505.0 | 43512.0 | 43519.0 | 43526.0 | 43533.0 | 43540.0 | 43547.0 | 43554.0 | 43561.0 | 43568.0 | 43575.0 | 43582.0 | 43589.0 | 43596.0 | 43603.0 | 43610.0 | 43617.0 | 43624.0 | 43631.0 | 43638.0 | 43645.0 | 43652.0 | 43659.0 | 43666.0 | 43673.0 | 43680.0 | 43687.0 | 43694.0 | |
| A | 1.3 | Task Specific Project Management Plan | 20 | 11/26/2018 | 12/14/2018 | 18 | 1.3 | 43414.0 | 43421.0 | 43428.0 | 43435.0 | 43442.0 | 43449.0 | 43456.0 | 43463.0 | 43470.0 | 43477.0 | 43484.0 | 43491.0 | 43498.0 | 43505.0 | 43512.0 | 43519.0 | 43526.0 | 43533.0 | 43540.0 | 43547.0 | 43554.0 | 43561.0 | 43568.0 | 43575.0 | 43582.0 | 43589.0 | 43596.0 | 43603.0 | 43610.0 | 43617.0 | 43624.0 | 43631.0 | 43638.0 | 43645.0 | 43652.0 | 43659.0 | 43666.0 | 43673.0 | 43680.0 | 43687.0 | 43694.0 | |
| 0 | 0 | 43414.0 | 43421.0 | 43428.0 | 43435.0 | 43442.0 | 43449.0 | 43456.0 | 43463.0 | 43470.0 | 43477.0 | 43484.0 | 43491.0 | 43498.0 | 43505.0 | 43512.0 | 43519.0 | 43526.0 | 43533.0 | 43540.0 | 43547.0 | 43554.0 | 43561.0 | 43568.0 | 43575.0 | 43582.0 | 43589.0 | 43596.0 | 43603.0 | 43610.0 | 43617.0 | 43624.0 | 43631.0 | 43638.0 | 43645.0 | 43652.0 | 43659.0 | 43666.0 | 43673.0 | 43680.0 | 43687.0 | 43694.0 | |||||||
| 2 | P | 2 | Analysis of Existing Conditions | 11/14/2018 | 3/19/19 | 125 | 43414.0 | 43421.0 | 43428.0 | 43435.0 | 43442.0 | 43449.0 | 43456.0 | 43463.0 | 43470.0 | 43477.0 | 43484.0 | 43491.0 | 43498.0 | 43505.0 | 43512.0 | 43519.0 | 43526.0 | 43533.0 | 43540.0 | 43547.0 | 43554.0 | 43561.0 | 43568.0 | 43575.0 | 43582.0 | 43589.0 | 43596.0 | 43603.0 | 43610.0 | 43617.0 | 43624.0 | 43631.0 | 43638.0 | 43645.0 | 43652.0 | 43659.0 | 43666.0 | 43673.0 | 43680.0 | 43687.0 | 43694.0 | ||
| A | 2.1 | Research & Review Available Data and Plans | 22 | 11/14/2018 | 01/29/2019 | 76 | 2.1 | 43414.0 | 43421.0 | 43428.0 | 43435.0 | 43442.0 | 43449.0 | 43456.0 | 43463.0 | 43470.0 | 43477.0 | 43484.0 | 43491.0 | 43498.0 | 43505.0 | 43512.0 | 43519.0 | 43526.0 | 43533.0 | 43540.0 | 43547.0 | 43554.0 | 43561.0 | 43568.0 | 43575.0 | 43582.0 | 43589.0 | 43596.0 | 43603.0 | 43610.0 | 43617.0 | 43624.0 | 43631.0 | 43638.0 | 43645.0 | 43652.0 | 43659.0 | 43666.0 | 43673.0 | 43680.0 | 43687.0 | 43694.0 | |
| A | 2.2 | Plan/Coordinate Field Inspection | 12 | 11/14/2018 | 12/30/2018 | 46 | 2.2 | 43414.0 | 43421.0 | 43428.0 | 43435.0 | 43442.0 | 43449.0 | 43456.0 | 43463.0 | 43470.0 | 43477.0 | 43484.0 | 43491.0 | 43498.0 | 43505.0 | 43512.0 | 43519.0 | 43526.0 | 43533.0 | 43540.0 | 43547.0 | 43554.0 | 43561.0 | 43568.0 | 43575.0 | 43582.0 | 43589.0 | 43596.0 | 43603.0 | 43610.0 | 43617.0 | 43624.0 | 43631.0 | 43638.0 | 43645.0 | 43652.0 | 43659.0 | 43666.0 | 43673.0 | 43680.0 | 43687.0 | 43694.0 | |
| A | 2.3 | Field Inspection & Summary of Findings | 46 | 01/03/2019 | 01/09/2019 | 6 | 2.3 | 43414.0 | 43421.0 | 43428.0 | 43435.0 | 43442.0 | 43449.0 | 43456.0 | 43463.0 | 43470.0 | 43477.0 | 43484.0 | 43491.0 | 43498.0 | 43505.0 | 43512.0 | 43519.0 | 43526.0 | 43533.0 | 43540.0 | 43547.0 | 43554.0 | 43561.0 | 43568.0 | 43575.0 | 43582.0 | 43589.0 | 43596.0 | 43603.0 | 43610.0 | 43617.0 | 43624.0 | 43631.0 | 43638.0 | 43645.0 | 43652.0 | 43659.0 | 43666.0 | 43673.0 | 43680.0 | 43687.0 | 43694.0 | |
| A | 2.4 | MBTA ROW/Safety Training | 48 | 12/01/2018 | 12/19/2018 | 18 | 2.4 | 43414.0 | 43421.0 | 43428.0 | 43435.0 | 43442.0 | 43449.0 | 43456.0 | 43463.0 | 43470.0 | 43477.0 | 43484.0 | 43491.0 | 43498.0 | 43505.0 | 43512.0 | 43519.0 | 43526.0 | 43533.0 | 43540.0 | 43547.0 | 43554.0 | 43561.0 | 43568.0 | 43575.0 | 43582.0 | 43589.0 | 43596.0 | 43603.0 | 43610.0 | 43617.0 | 43624.0 | 43631.0 | 43638.0 | 43645.0 | 43652.0 | 43659.0 | 43666.0 | 43673.0 | 43680.0 | 43687.0 | 43694.0 | |
| A | 2.5 | Preliminary Assessment - Environmental Checklist for Design | 14 | 01/02/2019 | 03/19/2019 | 76 | 2.5 | 43414.0 | 43421.0 | 43428.0 | 43435.0 | 43442.0 | 43449.0 | 43456.0 | 43463.0 | 43470.0 | 43477.0 | 43484.0 | 43491.0 | 43498.0 | 43505.0 | 43512.0 | 43519.0 | 43526.0 | 43533.0 | 43540.0 | 43547.0 | 43554.0 | 43561.0 | 43568.0 | 43575.0 | 43582.0 | 43589.0 | 43596.0 | 43603.0 | 43610.0 | 43617.0 | 43624.0 | 43631.0 | 43638.0 | 43645.0 | 43652.0 | 43659.0 | 43666.0 | 43673.0 | 43680.0 | 43687.0 | 43694.0 | |
| A | 2.6 | Preliminary Assessment - Project Checklist for Environmental | 14 | 01/02/2019 | 03/19/2019 | 76 | 2.6 | 43414.0 | 43421.0 | 43428.0 | 43435.0 | 43442.0 | 43449.0 | 43456.0 | 43463.0 | 43470.0 | 43477.0 | 43484.0 | 43491.0 | 43498.0 | 43505.0 | 43512.0 | 43519.0 | 43526.0 | 43533.0 | 43540.0 | 43547.0 | 43554.0 | 43561.0 | 43568.0 | 43575.0 | 43582.0 | 43589.0 | 43596.0 | 43603.0 | 43610.0 | 43617.0 | 43624.0 | 43631.0 | 43638.0 | 43645.0 | 43652.0 | 43659.0 | 43666.0 | 43673.0 | 43680.0 | 43687.0 | 43694.0 | |
| 2 | P | 3 | Topograhic and Property Survey | 11/14/2018 | 2/12/19 | 90 | 3 | 43414.0 | 43421.0 | 43428.0 | 43435.0 | 43442.0 | 43449.0 | 43456.0 | 43463.0 | 43470.0 | 43477.0 | 43484.0 | 43491.0 | 43498.0 | 43505.0 | 43512.0 | 43519.0 | 43526.0 | 43533.0 | 43540.0 | 43547.0 | 43554.0 | 43561.0 | 43568.0 | 43575.0 | 43582.0 | 43589.0 | 43596.0 | 43603.0 | 43610.0 | 43617.0 | 43624.0 | 43631.0 | 43638.0 | 43645.0 | 43652.0 | 43659.0 | 43666.0 | 43673.0 | 43680.0 | 43687.0 | 43694.0 | |
| A | 3.1 | Field Work "Surveys" | 340 | 12/12/2018 | 01/15/2019 | 34 | 3.1 | 43414.0 | 43421.0 | 43428.0 | 43435.0 | 43442.0 | 43449.0 | 43456.0 | 43463.0 | 43470.0 | 43477.0 | 43484.0 | 43491.0 | 43498.0 | 43505.0 | 43512.0 | 43519.0 | 43526.0 | 43533.0 | 43540.0 | 43547.0 | 43554.0 | 43561.0 | 43568.0 | 43575.0 | 43582.0 | 43589.0 | 43596.0 | 43603.0 | 43610.0 | 43617.0 | 43624.0 | 43631.0 | 43638.0 | 43645.0 | 43652.0 | 43659.0 | 43666.0 | 43673.0 | 43680.0 | 43687.0 | 43694.0 | |
| A | 3.2 | Survey Drawing Preparation | 120 | 01/02/2019 | 01/29/2019 | 27 | 3.2 | 43414.0 | 43421.0 | 43428.0 | 43435.0 | 43442.0 | 43449.0 | 43456.0 | 43463.0 | 43470.0 | 43477.0 | 43484.0 | 43491.0 | 43498.0 | 43505.0 | 43512.0 | 43519.0 | 43526.0 | 43533.0 | 43540.0 | 43547.0 | 43554.0 | 43561.0 | 43568.0 | 43575.0 | 43582.0 | 43589.0 | 43596.0 | 43603.0 | 43610.0 | 43617.0 | 43624.0 | 43631.0 | 43638.0 | 43645.0 | 43652.0 | 43659.0 | 43666.0 | 43673.0 | 43680.0 | 43687.0 | 43694.0 | |
| 3 | P | 4 | Geotechnical Investigation | 11/14/2018 | 2/12/19 | 90 | 4 | 43414.0 | 43421.0 | 43428.0 | 43435.0 | 43442.0 | 43449.0 | 43456.0 | 43463.0 | 43470.0 | 43477.0 | 43484.0 | 43491.0 | 43498.0 | 43505.0 | 43512.0 | 43519.0 | 43526.0 | 43533.0 | 43540.0 | 43547.0 | 43554.0 | 43561.0 | 43568.0 | 43575.0 | 43582.0 | 43589.0 | 43596.0 | 43603.0 | 43610.0 | 43617.0 | 43624.0 | 43631.0 | 43638.0 | 43645.0 | 43652.0 | 43659.0 | 43666.0 | 43673.0 | 43680.0 | 43687.0 | 43694.0 | |
| A | 4.1 | Coordination w/ Keolis | GZA | 11/14/2018 | 12/18/2018 | 34 | 4.1 | 43414.0 | 43421.0 | 43428.0 | 43435.0 | 43442.0 | 43449.0 | 43456.0 | 43463.0 | 43470.0 | 43477.0 | 43484.0 | 43491.0 | 43498.0 | 43505.0 | 43512.0 | 43519.0 | 43526.0 | 43533.0 | 43540.0 | 43547.0 | 43554.0 | 43561.0 | 43568.0 | 43575.0 | 43582.0 | 43589.0 | 43596.0 | 43603.0 | 43610.0 | 43617.0 | 43624.0 | 43631.0 | 43638.0 | 43645.0 | 43652.0 | 43659.0 | 43666.0 | 43673.0 | 43680.0 | 43687.0 | 43694.0 | |
| A | 4.2 | Utility Clearance/access coordination with Keolis | GZA | 11/28/2018 | 12/18/2018 | 20 | 4.2 | 43414.0 | 43421.0 | 43428.0 | 43435.0 | 43442.0 | 43449.0 | 43456.0 | 43463.0 | 43470.0 | 43477.0 | 43484.0 | 43491.0 | 43498.0 | 43505.0 | 43512.0 | 43519.0 | 43526.0 | 43533.0 | 43540.0 | 43547.0 | 43554.0 | 43561.0 | 43568.0 | 43575.0 | 43582.0 | 43589.0 | 43596.0 | 43603.0 | 43610.0 | 43617.0 | 43624.0 | 43631.0 | 43638.0 | 43645.0 | 43652.0 | 43659.0 | 43666.0 | 43673.0 | 43680.0 | 43687.0 | 43694.0 | |
| A | 4.3 | Field Drilling | GZA | 01/06/2019 | 01/09/2019 | 3 | 4.3 | 43414.0 | 43421.0 | 43428.0 | 43435.0 | 43442.0 | 43449.0 | 43456.0 | 43463.0 | 43470.0 | 43477.0 | 43484.0 | 43491.0 | 43498.0 | 43505.0 | 43512.0 | 43519.0 | 43526.0 | 43533.0 | 43540.0 | 43547.0 | 43554.0 | 43561.0 | 43568.0 | 43575.0 | 43582.0 | 43589.0 | 43596.0 | 43603.0 | 43610.0 | 43617.0 | 43624.0 | 43631.0 | 43638.0 | 43645.0 | 43652.0 | 43659.0 | 43666.0 | 43673.0 | 43680.0 | 43687.0 | 43694.0 | |
| A | 4.4 | Lab Testing | GZA | 01/09/2019 | 01/15/2019 | 6 | 4.4 | 43414.0 | 43421.0 | 43428.0 | 43435.0 | 43442.0 | 43449.0 | 43456.0 | 43463.0 | 43470.0 | 43477.0 | 43484.0 | 43491.0 | 43498.0 | 43505.0 | 43512.0 | 43519.0 | 43526.0 | 43533.0 | 43540.0 | 43547.0 | 43554.0 | 43561.0 | 43568.0 | 43575.0 | 43582.0 | 43589.0 | 43596.0 | 43603.0 | 43610.0 | 43617.0 | 43624.0 | 43631.0 | 43638.0 | 43645.0 | 43652.0 | 43659.0 | 43666.0 | 43673.0 | 43680.0 | 43687.0 | 43694.0 | |
| A | 4.5 | Draft geotech Report | GZA | 01/16/2019 | 02/12/2019 | 27 | 4.5 | 43414.0 | 43421.0 | 43428.0 | 43435.0 | 43442.0 | 43449.0 | 43456.0 | 43463.0 | 43470.0 | 43477.0 | 43484.0 | 43491.0 | 43498.0 | 43505.0 | 43512.0 | 43519.0 | 43526.0 | 43533.0 | 43540.0 | 43547.0 | 43554.0 | 43561.0 | 43568.0 | 43575.0 | 43582.0 | 43589.0 | 43596.0 | 43603.0 | 43610.0 | 43617.0 | 43624.0 | 43631.0 | 43638.0 | 43645.0 | 43652.0 | 43659.0 | 43666.0 | 43673.0 | 43680.0 | 43687.0 | 43694.0 | |
| 5 | P | 5 | Bridge Type Study Report | 01/2/2019 | 6/6/19 | 155 | 5 | 43414.0 | 43421.0 | 43428.0 | 43435.0 | 43442.0 | 43449.0 | 43456.0 | 43463.0 | 43470.0 | 43477.0 | 43484.0 | 43491.0 | 43498.0 | 43505.0 | 43512.0 | 43519.0 | 43526.0 | 43533.0 | 43540.0 | 43547.0 | 43554.0 | 43561.0 | 43568.0 | 43575.0 | 43582.0 | 43589.0 | 43596.0 | 43603.0 | 43610.0 | 43617.0 | 43624.0 | 43631.0 | 43638.0 | 43645.0 | 43652.0 | 43659.0 | 43666.0 | 43673.0 | 43680.0 | 43687.0 | 43694.0 | |
| A | 5.1 | Existing Substructure Evaluation and Assessment | 44 | 01/30/2019 | 02/19/2019 | 20 | 5.1 | 43414.0 | 43421.0 | 43428.0 | 43435.0 | 43442.0 | 43449.0 | 43456.0 | 43463.0 | 43470.0 | 43477.0 | 43484.0 | 43491.0 | 43498.0 | 43505.0 | 43512.0 | 43519.0 | 43526.0 | 43533.0 | 43540.0 | 43547.0 | 43554.0 | 43561.0 | 43568.0 | 43575.0 | 43582.0 | 43589.0 | 43596.0 | 43603.0 | 43610.0 | 43617.0 | 43624.0 | 43631.0 | 43638.0 | 43645.0 | 43652.0 | 43659.0 | 43666.0 | 43673.0 | 43680.0 | 43687.0 | 43694.0 | |
| A | 5.2 | Superstructure Replacement Alternatives (3 Types) | 100 | 01/02/2019 | 02/19/2019 | 48 | 5.2 | 43414.0 | 43421.0 | 43428.0 | 43435.0 | 43442.0 | 43449.0 | 43456.0 | 43463.0 | 43470.0 | 43477.0 | 43484.0 | 43491.0 | 43498.0 | 43505.0 | 43512.0 | 43519.0 | 43526.0 | 43533.0 | 43540.0 | 43547.0 | 43554.0 | 43561.0 | 43568.0 | 43575.0 | 43582.0 | 43589.0 | 43596.0 | 43603.0 | 43610.0 | 43617.0 | 43624.0 | 43631.0 | 43638.0 | 43645.0 | 43652.0 | 43659.0 | 43666.0 | 43673.0 | 43680.0 | 43687.0 | 43694.0 | |
| A | 5.3 | Sequence of Construction Concepts | 48 | 01/23/2019 | 02/19/2019 | 27 | 5.3 | 43414.0 | 43421.0 | 43428.0 | 43435.0 | 43442.0 | 43449.0 | 43456.0 | 43463.0 | 43470.0 | 43477.0 | 43484.0 | 43491.0 | 43498.0 | 43505.0 | 43512.0 | 43519.0 | 43526.0 | 43533.0 | 43540.0 | 43547.0 | 43554.0 | 43561.0 | 43568.0 | 43575.0 | 43582.0 | 43589.0 | 43596.0 | 43603.0 | 43610.0 | 43617.0 | 43624.0 | 43631.0 | 43638.0 | 43645.0 | 43652.0 | 43659.0 | 43666.0 | 43673.0 | 43680.0 | 43687.0 | 43694.0 | |
| A | 5.4 | Exist. Roadway Evaluation and Assessment | 24 | 01/30/2019 | 02/05/2019 | 6 | 5.4 | 43414.0 | 43421.0 | 43428.0 | 43435.0 | 43442.0 | 43449.0 | 43456.0 | 43463.0 | 43470.0 | 43477.0 | 43484.0 | 43491.0 | 43498.0 | 43505.0 | 43512.0 | 43519.0 | 43526.0 | 43533.0 | 43540.0 | 43547.0 | 43554.0 | 43561.0 | 43568.0 | 43575.0 | 43582.0 | 43589.0 | 43596.0 | 43603.0 | 43610.0 | 43617.0 | 43624.0 | 43631.0 | 43638.0 | 43645.0 | 43652.0 | 43659.0 | 43666.0 | 43673.0 | 43680.0 | 43687.0 | 43694.0 | |
| A | 5.5 | Roadway Clearance Mitigation Alternatives (Hor./Vert. 2 Alternates) | 106 | 02/06/2019 | 03/05/2019 | 27 | 5.5 | 43414.0 | 43421.0 | 43428.0 | 43435.0 | 43442.0 | 43449.0 | 43456.0 | 43463.0 | 43470.0 | 43477.0 | 43484.0 | 43491.0 | 43498.0 | 43505.0 | 43512.0 | 43519.0 | 43526.0 | 43533.0 | 43540.0 | 43547.0 | 43554.0 | 43561.0 | 43568.0 | 43575.0 | 43582.0 | 43589.0 | 43596.0 | 43603.0 | 43610.0 | 43617.0 | 43624.0 | 43631.0 | 43638.0 | 43645.0 | 43652.0 | 43659.0 | 43666.0 | 43673.0 | 43680.0 | 43687.0 | 43694.0 | |
| A | 5.6 | Preparation of Conceptual Detour Plan | 22 | 03/06/2019 | 03/12/2019 | 6 | 5.6 | 43414.0 | 43421.0 | 43428.0 | 43435.0 | 43442.0 | 43449.0 | 43456.0 | 43463.0 | 43470.0 | 43477.0 | 43484.0 | 43491.0 | 43498.0 | 43505.0 | 43512.0 | 43519.0 | 43526.0 | 43533.0 | 43540.0 | 43547.0 | 43554.0 | 43561.0 | 43568.0 | 43575.0 | 43582.0 | 43589.0 | 43596.0 | 43603.0 | 43610.0 | 43617.0 | 43624.0 | 43631.0 | 43638.0 | 43645.0 | 43652.0 | 43659.0 | 43666.0 | 43673.0 | 43680.0 | 43687.0 | 43694.0 | |
| A | 5.7 | Evaluation and Prepare Draft Report | 88 | 02/20/2019 | 03/19/2019 | 27 | 5.7 | 43414.0 | 43421.0 | 43428.0 | 43435.0 | 43442.0 | 43449.0 | 43456.0 | 43463.0 | 43470.0 | 43477.0 | 43484.0 | 43491.0 | 43498.0 | 43505.0 | 43512.0 | 43519.0 | 43526.0 | 43533.0 | 43540.0 | 43547.0 | 43554.0 | 43561.0 | 43568.0 | 43575.0 | 43582.0 | 43589.0 | 43596.0 | 43603.0 | 43610.0 | 43617.0 | 43624.0 | 43631.0 | 43638.0 | 43645.0 | 43652.0 | 43659.0 | 43666.0 | 43673.0 | 43680.0 | 43687.0 | 43694.0 | |
| QA Review | 8 | 03/26/2019 | 04/01/2019 | 6 | 43414.0 | 43421.0 | 43428.0 | 43435.0 | 43442.0 | 43449.0 | 43456.0 | 43463.0 | 43470.0 | 43477.0 | 43484.0 | 43491.0 | 43498.0 | 43505.0 | 43512.0 | 43519.0 | 43526.0 | 43533.0 | 43540.0 | 43547.0 | 43554.0 | 43561.0 | 43568.0 | 43575.0 | 43582.0 | 43589.0 | 43596.0 | 43603.0 | 43610.0 | 43617.0 | 43624.0 | 43631.0 | 43638.0 | 43645.0 | 43652.0 | 43659.0 | 43666.0 | 43673.0 | 43680.0 | 43687.0 | 43694.0 | ||||
| QA Updates | 24 | 04/02/2019 | 04/08/2019 | 6 | 43414.0 | 43421.0 | 43428.0 | 43435.0 | 43442.0 | 43449.0 | 43456.0 | 43463.0 | 43470.0 | 43477.0 | 43484.0 | 43491.0 | 43498.0 | 43505.0 | 43512.0 | 43519.0 | 43526.0 | 43533.0 | 43540.0 | 43547.0 | 43554.0 | 43561.0 | 43568.0 | 43575.0 | 43582.0 | 43589.0 | 43596.0 | 43603.0 | 43610.0 | 43617.0 | 43624.0 | 43631.0 | 43638.0 | 43645.0 | 43652.0 | 43659.0 | 43666.0 | 43673.0 | 43680.0 | 43687.0 | 43694.0 | ||||
| 5.8 | Submit Type Study Report | 0 | 04/09/2019 | 04/09/2019 | 0 | 43414.0 | 43421.0 | 43428.0 | 43435.0 | 43442.0 | 43449.0 | 43456.0 | 43463.0 | 43470.0 | 43477.0 | 43484.0 | 43491.0 | 43498.0 | 43505.0 | 43512.0 | 43519.0 | 43526.0 | 43533.0 | 43540.0 | 43547.0 | 43554.0 | 43561.0 | 43568.0 | 43575.0 | 43582.0 | 43589.0 | 43596.0 | 43603.0 | 43610.0 | 43617.0 | 43624.0 | 43631.0 | 43638.0 | 43645.0 | 43652.0 | 43659.0 | 43666.0 | 43673.0 | 43680.0 | 43687.0 | 43694.0 | |||
| A | 5.9 | MBTA Review | MBTA | 04/10/2019 | 05/08/2019 | 28 | 5.9 | 43414.0 | 43421.0 | 43428.0 | 43435.0 | 43442.0 | 43449.0 | 43456.0 | 43463.0 | 43470.0 | 43477.0 | 43484.0 | 43491.0 | 43498.0 | 43505.0 | 43512.0 | 43519.0 | 43526.0 | 43533.0 | 43540.0 | 43547.0 | 43554.0 | 43561.0 | 43568.0 | 43575.0 | 43582.0 | 43589.0 | 43596.0 | 43603.0 | 43610.0 | 43617.0 | 43624.0 | 43631.0 | 43638.0 | 43645.0 | 43652.0 | 43659.0 | 43666.0 | 43673.0 | 43680.0 | 43687.0 | 43694.0 | |
| A | 5.1 | Finalize Report Upon MBTA Review | 24 | 05/09/2019 | 06/06/2019 | 28 | 5.1 | 43414.0 | 43421.0 | 43428.0 | 43435.0 | 43442.0 | 43449.0 | 43456.0 | 43463.0 | 43470.0 | 43477.0 | 43484.0 | 43491.0 | 43498.0 | 43505.0 | 43512.0 | 43519.0 | 43526.0 | 43533.0 | 43540.0 | 43547.0 | 43554.0 | 43561.0 | 43568.0 | 43575.0 | 43582.0 | 43589.0 | 43596.0 | 43603.0 | 43610.0 | 43617.0 | 43624.0 | 43631.0 | 43638.0 | 43645.0 | 43652.0 | 43659.0 | 43666.0 | 43673.0 | 43680.0 | 43687.0 | 43694.0 | |
| P | 6 | Value Analysis | 01/2/2019 | 3/19/19 | 76 | 6 | 43414.0 | 43421.0 | 43428.0 | 43435.0 | 43442.0 | 43449.0 | 43456.0 | 43463.0 | 43470.0 | 43477.0 | 43484.0 | 43491.0 | 43498.0 | 43505.0 | 43512.0 | 43519.0 | 43526.0 | 43533.0 | 43540.0 | 43547.0 | 43554.0 | 43561.0 | 43568.0 | 43575.0 | 43582.0 | 43589.0 | 43596.0 | 43603.0 | 43610.0 | 43617.0 | 43624.0 | 43631.0 | 43638.0 | 43645.0 | 43652.0 | 43659.0 | 43666.0 | 43673.0 | 43680.0 | 43687.0 | 43694.0 | ||
| A | 6.1 | Value Engineering | 44 | 01/02/2019 | 02/19/2019 | 48 | 6.1 | 43414.0 | 43421.0 | 43428.0 | 43435.0 | 43442.0 | 43449.0 | 43456.0 | 43463.0 | 43470.0 | 43477.0 | 43484.0 | 43491.0 | 43498.0 | 43505.0 | 43512.0 | 43519.0 | 43526.0 | 43533.0 | 43540.0 | 43547.0 | 43554.0 | 43561.0 | 43568.0 | 43575.0 | 43582.0 | 43589.0 | 43596.0 | 43603.0 | 43610.0 | 43617.0 | 43624.0 | 43631.0 | 43638.0 | 43645.0 | 43652.0 | 43659.0 | 43666.0 | 43673.0 | 43680.0 | 43687.0 | 43694.0 | |
| A | 6.2 | Constructability | 52 | 01/30/2019 | 02/20/2019 | 21 | 6.2 | 43414.0 | 43421.0 | 43428.0 | 43435.0 | 43442.0 | 43449.0 | 43456.0 | 43463.0 | 43470.0 | 43477.0 | 43484.0 | 43491.0 | 43498.0 | 43505.0 | 43512.0 | 43519.0 | 43526.0 | 43533.0 | 43540.0 | 43547.0 | 43554.0 | 43561.0 | 43568.0 | 43575.0 | 43582.0 | 43589.0 | 43596.0 | 43603.0 | 43610.0 | 43617.0 | 43624.0 | 43631.0 | 43638.0 | 43645.0 | 43652.0 | 43659.0 | 43666.0 | 43673.0 | 43680.0 | 43687.0 | 43694.0 | |
| A | 6.3 | Preliminary Quantity Take-Off (All Alternates) | 58 | 02/20/2019 | 03/05/2019 | 13 | 6.3 | 43414.0 | 43421.0 | 43428.0 | 43435.0 | 43442.0 | 43449.0 | 43456.0 | 43463.0 | 43470.0 | 43477.0 | 43484.0 | 43491.0 | 43498.0 | 43505.0 | 43512.0 | 43519.0 | 43526.0 | 43533.0 | 43540.0 | 43547.0 | 43554.0 | 43561.0 | 43568.0 | 43575.0 | 43582.0 | 43589.0 | 43596.0 | 43603.0 | 43610.0 | 43617.0 | 43624.0 | 43631.0 | 43638.0 | 43645.0 | 43652.0 | 43659.0 | 43666.0 | 43673.0 | 43680.0 | 43687.0 | 43694.0 | |
| A | 6.4 | Cost Analysis / Project Estimates (All Alternates) | 66 | 03/06/2019 | 03/19/2019 | 13 | 6.4 | 43414.0 | 43421.0 | 43428.0 | 43435.0 | 43442.0 | 43449.0 | 43456.0 | 43463.0 | 43470.0 | 43477.0 | 43484.0 | 43491.0 | 43498.0 | 43505.0 | 43512.0 | 43519.0 | 43526.0 | 43533.0 | 43540.0 | 43547.0 | 43554.0 | 43561.0 | 43568.0 | 43575.0 | 43582.0 | 43589.0 | 43596.0 | 43603.0 | 43610.0 | 43617.0 | 43624.0 | 43631.0 | 43638.0 | 43645.0 | 43652.0 | 43659.0 | 43666.0 | 43673.0 | 43680.0 | 43687.0 | 43694.0 | |
| A | 6.5 | Project Schedule | 40 | 03/06/2019 | 03/19/2019 | 13 | 6.5 | 43414.0 | 43421.0 | 43428.0 | 43435.0 | 43442.0 | 43449.0 | 43456.0 | 43463.0 | 43470.0 | 43477.0 | 43484.0 | 43491.0 | 43498.0 | 43505.0 | 43512.0 | 43519.0 | 43526.0 | 43533.0 | 43540.0 | 43547.0 | 43554.0 | 43561.0 | 43568.0 | 43575.0 | 43582.0 | 43589.0 | 43596.0 | 43603.0 | 43610.0 | 43617.0 | 43624.0 | 43631.0 | 43638.0 | 43645.0 | 43652.0 | 43659.0 | 43666.0 | 43673.0 | 43680.0 | 43687.0 | 43694.0 |
&D &T MBTA Contract No. B92PS24 - Task Order No. 6 Franklin Commuter Line over East Street Bridge Replacement Work Flow Management &P of &N