This is a Purchase Description (RIPD) for repair and maintenance services of a 5-ton Electric Arc Furnace (EAF) at Rock Island Arsenal Joint Manufacturing and Technology Center (RIA-JMTC).
The contractor shall provide all parts, materials, labor, and support equipment not-to-exceed $950,000.00 to repair and maintain equipment RIA#31907, ensuring full operational capabilities from the start of project 24-3-09 (EAF + AOD) until a replacement 5-ton EAF (RIA#29892) is installed and fully operational. All equipment must be new and unused, comply with manufacturer specifications, meet current local, state, and federal regulations, and exclude polychlorinated biphenyl (PCB), ozone-depleting substances, and asbestos materials. The contractor is responsible for equipment delivery to Rock Island Arsenal, with off-loading scheduled between 6:00 am and 12:00 pm on Mondays through Thursdays (excluding holidays). All shipments must be marked for Mr. Robert Mcclure or Mr. Dave Holgorsen (TARA-LGC). The contractor assumes all liability and responsibility for equipment until final acceptance by Rock Island Arsenal, except in cases of intentional damage or gross negligence by government personnel. The contractor must provide qualified, English-speaking service personnel with telephone access during normal working hours (8:00 am–3:00 pm CST, Monday–Friday), 48-hour on-site response capability, and stocked maintenance parts. Service hours for installation, training, and delivery are restricted to 6:00 am–3:30 pm Monday through Thursday. All contractor personnel must comply with extensive security requirements including background checks, anti-terrorism training, Real ID identification (effective May 7, 2025), random antiterrorist measures, and personnel badging procedures specific to Rock Island Arsenal, a Department of Defense facility.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ROCK ISLAND ARSENAL RIPD: E4000-24-3-09
PURCHASE DESCRIPTION DATE: 21-July-26
5-TON EAF MAINTENANCE
1. GENERAL SYSTEM DESCRIPTION
The purpose of this project is to outline the responsibilities required of the contractor during project 24-3-09 Foundry Furnace Replacements IAW RIPD E4000-24-3-09 EAF + AOD. The contractor will be responsible for the successful repair and continued maintenance of the RIA-JMTC 5-Ton Electric Arc Furnace to ensure RIA-JMTC is able to maintain required foundry production during times in which the 3-Ton EAF is down as a part of the aforementioned project. This shall include all parts, materials and labor necessary to make the equipment safely operational and to meet all relevant industry and national standards, per the requirements identified within this document.
2. GENERAL DESIGN STANDARDS
2.1.1 NEW EQUIPMENT: The equipment furnished under this purchase description shall be new and unused.
2.1.2 COMPONENT ENVIRONMENT: Under no circumstances shall a component be used in an application not recommended by the component manufacturer. Components shall not be subjected to conditions of operation beyond the recommendations of the manufacturer, such as excessive heat, lack of lubrication, over-loading.
2.1.3 SURFACE BUILDING AND COATINGS: Welding, brazing, soldering, coating or plating shall be employed only where specified in the original design. These operations may not be employed as a means of reclaiming a defective part.
2.1.4 FASTENING DEVICES: All screws, pins, bolts, and similar parts shall be installed in such a manner as to prevent change in tightness. Those devices subject to removal or adjustment shall not be swaged, peened, staked, or otherwise permanently deformed. They shall not be installed using permanent bonding adhesives.
2.2 Safety, Security and Environmental
2.2.1 SECURITY: The RIA-JMTC is an Army installation subject to Department of Defense safeguards, various precautions, and plant protection measures. All of the below requirements will be necessary of contractors visiting RIA to satisfy requirements of this purchase description; Additional requirements will be placed on contractors requiring access to the Army Network, or Common Access Card (CAC), as specifically detailed below. At all times during the execution of this work, contractor personnel will maintain adequate plant protection devises to minimize espionage, sabotage, and other malicious destruction and damage. The contractor shall comply with all security requirements of the Rock Island Arsenal. Rock Island Arsenal island-wide Force Protection levels may be adjusted/changed at any time, which may cause possible delays and will directly affect procedures for accessing the island.
2.2.1.1 Access and General Protection/Security Policy and Procedures: The contractor and any associated subcontractor employees shall provide all information required for background checks to meet installation access requirements to be accomplished by the installation Director of Emergency Services. All contractor employees must comply with all personal identity verification requirements (IAW FAR clause 52.204-9) as directed by Department of Defense (DoD), Headquarters Department of the Army (HQDA), and any local policy. If the Force Protection Condition (FPCON) changes, the Government may require changes in contractor installation access, security matters, or security processes.
2.2.1.1.1 Access to RIA: Contractor and all subcontractor employees performing work at RIA shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) and any applicable installation, facility access screening and local security policies and procedures.
2.2.1.1.2 Random Antiterrorist Measures Program (RAMP) participation: Contractor personnel are subject to RAMP security program (i.e. vehicle searches, wearing of ID badges, etc.). Contractor shall comply with any, and all instructions issued by the Rock Island Arsenal Police Department. The RAMP is discussed in the RIA-JMTC Anti- Terrorism Training.
2.2.1.1.3 During FPCONs levels of Charlie or Delta, services may be discontinued/postponed due to a higher National or local security threat. Services will resume when FPCON Level is reduced to Bravo, or lower. FPCON levels are described in Anti-Terrorism Level I Training.
2.2.1.1.4 Contractor personnel shall return all Installation Badges and access passes as soon as possible prior to contract completion. RIA-JMTC electronic keys and access passes are accountable items, shad shall be returned within 24-hours of no longer being needed. Items will be returned to the COR, or paced in a drop box at a RIA-JMTC access point.
2.2.1.2 Security Training: The contractor shall complete the following training:
2.2.1.2.1 Anti-Terrorism, Level I: All contractor employees, including subcontractor employees, requiring access to Army installations, facilities, or controlled access areas shall complete Anti-Terrorism (AT) Level I Awareness training. The COR will be provided a copy of the Rock Island Arsenal –Joint Manufacturing and Technology Center (RIA-JMTC) AT Level I Awareness Training and assure that the training is complete.
The contractor shall sign a memorandum of record for each contractor employees and subcontractor employee to the RIA-JMTC Operations Center prior issuing any electronic keys, or access pass being authorized.
2.2.1.2.2 iWatch (See Something, Say Something) Training: The Contractor and all associated subcontractors shall complete iWatch Training. iWatch Training shall be provided during the Anti-Terrorism Training.
2.2.1.3 For Contractors requiring Common Access Card (CAC): Before CAC issuance, the contractor employee requires a favorably adjudicated National Agency Check with Inquiries (NACI) or an equivalent or higher investigation in accordance with Army Directive 2014-05.
The contractor employee will be issued a CAC only if duties involve one of the following:
(1) Both physical access to a DoD facility and access, via logon, to DoD networks onsite, or remotely or (2) Remote access via logon, to a DoD network using DoD-approved remote access procedures, or (3) Physical access to multiple DoD facilities or multiple Non-DoD Federally controlled facilities on behalf of the DoD on a recurring basis for a period of 6-months, or more. At the discretion of the sponsoring activity, an initial CAC may be issued based on a favorable review of the FBI fingerprint check and a successfully scheduled NACI at the Office of Personnel Management. Contractors needing a NACI or equivalent investigation or higher investigation will coordinate this investigation through their COR.
Contractor personnel shall turn in CAC cards upon completion of their contractual obligations, or at the request by the COR, or at the request of the Contracting Officer.
2.2.2 FEDERAL MARIJUANA LAWS REMAIN UNCHANGED: Note: Rock Island Arsenal is under the exclusive federal jurisdiction of the United States. Under federal law, marijuana is still defined as a Schedule I drug, and possession and use of marijuana is still illegal. Any person using or in possession of marijuana on Rock Island Arsenal may be criminally prosecuted in federal district court. In addition, such individuals may be permanently barred from entering Rock Island Arsenal.
2.2.3 REAL ID: Starting 07-May-2025 all personnel entering Rock Island Arsenal will be required to show a Real ID form of identification.
2.2.4 INDUSTRY AND REGULATIONS: The equipment shall comply with the most current of all local, state, and federal laws and regulations listed in Standards and Publications.
2.2.5 MATERIAL EXCLUSIONS: The equipment shall not contain polychlorinated biphenyl (PCB), ozone depleting substances (Class I or Class II), or asbestos materials.
2.2.6 SAFETY REGULATION COMPLIANCE: The contractor shall comply with standard OSHA and RIA safety standards, including conforming to confined space work requirements when applicable.
3. COMPONENT SPECIFICATION
The contractor will either provide or arrange through the use of subcontractors these services: repair and maintenance of the RIA-JMTC 5-Ton EAF. This includes all parts, materials, labor, and supporting equipment necessary to make the equipment safely operational and to meet all relevant industry and national standards, per the requirements identified within this document.
3.1 Equipment Specifications:
3.1.1 The contractor shall provide all parts, materials, labor and necessary support equipment not-to-exceed $950,000.00 to repair and maintain RIA#31907 to ensure full operational capabilities from the start of project 24-3-09 EAF + AOD and until RIA#29892 has been replaced with a new and fully operational 5-Ton EAF.
4. APPROVAL/SHIPPING
4.1 Shipping
4.1.1 RESPONSIBILITY: The contractor is responsible for delivery of the equipment to the Rock Island Arsenal. Adequate preserving of equipment surfaces, packing, marking, and skidding of materials for shipment shall be the responsibility of the contractor. If special lifting devices, such as hooks or eyes, are required for ease of handling, they shall be supplied with the equipment. Any special devices shall be returned to the contractor upon request only if they will not be required for future movement of the equipment, and at the contractor’s expense.
4.1.2 SHIPPING SCHEDULE: Be aware, the Rock Island Arsenal will only off-load equipment arriving between 6:00 am and 12:00 am (noon), local time on Mondays through Thursdays except holidays. For information concerning holidays, the contractor should consult the contracting officer. There is no place to stage transporting vehicles awaiting the arrival of contractors. All equipment shall be delivered at the same time, meaning the same day (multiple trucks are acceptable) unless pre-authorized to deliver on multiple days by the RIA-JMTC contracting officer.
4.1.3 RECEIVER: All shipments to Rock Island Arsenal including installation tools and/or replacement parts, as well as the original shipment of the equipment, shall be marked “ATTN:
Mr. Robert Mcclure or Mr. Dave Holgorsen TARA-LGC”. Items not correctly marked are subject to being returned at the vendor’s expense.
4.1.4 ARRIVAL INSPECTION: Upon receipt of equipment at Rock Island Arsenal, a preliminary inspection shall be performed to determine condition and/or count. This inspection shall be performed by Rock Island Arsenal personnel.
4.2 Installation
4.2.1 LABOR AND MATERIAL: The supplier is solely responsible for providing all labor, materials, hardware, tools, and equipment necessary for complete installation of this system except as specifically listed in this document as being provided by the Rock Island Arsenal.
4.2.2 SUPERVISION: Supervision of the installation process will be the responsibility of the contractor. Rock Island Arsenal shall retain the right to periodic inspection and evaluation of the process, as it deems necessary.
4.2.3 OFF-LOADING/PLACEMENT: Off-loading of the equipment from the delivery vehicle, and placement of the equipment in position for the installation is the responsibility of the contractor. The contractor shall not be allowed to use government equipment to accomplish this work.
4.2.4 OFF-LOADING/PLACEMENT OPTION: At the request of the contractor, Rock Island Arsenal will perform the off-loading and placement of the equipment.
4.2.4.1 Any special requirements or precautions to be observed shall be the responsibility of the contractor to provide.
4.2.4.2 The contractor or his representative may be present during this process; however, such person will be responsible for being present upon arrival of the equipment at Rock Island Arsenal. Off-loading and placement shall not be delayed to allow arrival of the contractor or his representative.
4.2.4.3 If, due to contractor caused difficulties, the equipment or components of the equipment must be moved, removed or replaced by Rock Island Arsenal after initial placement, the contractor shall be billed for such work at current Rock Island Arsenal labor and overhead rates.
4.2.5 LIABILITY: In any case, the equipment remains the property of the contractor, and the contractor shall assume all responsibility and liability for the equipment and the work performed upon it. The government shall be held harmless for any damage done to the equipment at any time up until final acceptance of the equipment by Rock Island Arsenal, except in the case of intentional damage and/or gross negligence on the part of Rock Island Arsenal personnel.
4.2.6 SET-UP: The contractor shall be responsible for set-up and connection of the equipment beyond connections of the utilities to the points of first connection.
4.2.7 SECURITY: The RIA-JMTC is an Army installation subject to Department of Defense safe guards, various precautions, and plant protection measures. At all times during the execution of this SOW, the contractor will maintain adequate plant protection devises to minimize espionage, sabotage, and other malicious destruction and damage. The contractor shall comply with all security requirements of the Rock Island Arsenal. Rock Island Arsenal Island-wide Force Protection levels may be adjusted/changed at any time, which may cause possible delays and will directly affect procedures for accessing the Island.
Delivery Hours or Service Hours: Service calls, equipment installation, training, and equipment delivery (where the contractor offloads) will only be allowed from 0600 – 1530, Monday through Thursday, except for Government Holidays. Deliveries of items where the contractor has opted for Government “off-loading option”, must be received before 1200 hours. These hours are subject to change, however, the Government will notify the contractor of such changes.
5. SERVICE
5.1 Service/Support Requirements
The contractor shall have as a minimum, a verifiable service/repair capability which meets or exceeds the following requirements:
5.1.1 STAFF: Staffed by qualified, English speaking personnel fully knowledgeable in the service/repair of the equipment offered.
5.1.2 TELEPHONE ACCESS: Telephone access to service/repair personnel shall be available for consultation during Rock Island Arsenal normal working hours. Rock Island Arsenal normal working hours are 8:00 am CST to 3:00 pm CST, Monday through Friday, except legal federal holidays.
5.1.3 ON-SITE RESPONSE: Physical, on-site response shall be possible within 48-hrs of notification that service/repair of the equipment is necessary.
5.1.4 MAINTENANCE PARTS: Parts necessary for periodic replacement such as belts, hoses, filters, and other parts normally considered as spare parts, by the manufacturer, shall be stocked and available for shipment.
5.1.5 PRIOR HISTORY: Said service/repair capability shall have been available to the general public prior to the issue date of this purchase description. Adequate proof of prior availability shall be provided upon request.
| 1. GENERAL SYSTEM DESCRIPTION |
| 2. General Design Standards |
| 2.2 Safety, Security and Environmental |
| 3. COMPONENT SPECIFICATION |
| 3.1 Equipment Specifications: |
| 4. APPROVAL/SHIPPING |
| 4.1 Shipping |
| 4.2 Installation |
| 5. SERVICE |
| 5.1 Service/Support Requirements |
File details come from the government source that posted it. Updated .