Attachment 0001- BIL - Houston District - DPC - SOW.docx

DOCX document 68 KB Posted

Attached to
BIL Funded - District Project Coordinator Contract Support for the Houston District Federal contract opportunity
Solicitation number
697DCK-23-R-00563
Issued by
Department of Transportation Federal Aviation Administration Southwestern Region

About this file

This statement of work outlines requirements for a District Project Coordinator to support the Federal Aviation Administration's implementation of projects funded by the Bipartisan Infrastructure Law in the Houston District. The contractor must provide a coordinator to perform program management, financial management, and independent cost analysis support services. Key responsibilities include assisting the District Manager with program administration, data analysis for project planning and resources, and working with program managers to identify, coordinate, and integrate activities. The coordinator must be available for in-person district meetings and reside within the district boundaries. Monthly progress reports are due within 10 days of each month. Standard operating procedures and an annual report are also required. The performance period is one base year with options to extend.

View the file

Other files for this federal contract opportunity

Other files attached to BIL Funded - District Project Coordinator Contract Support for the Houston District, newest first.
File Type Posted
SIR No. 697DCK-23-R-00563 - Houston District DPC - 07-27-2023.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation No.: 697DCK-23-R-00563 Attachment 0001 - Statement of Work District Project Coordinator Contract Support For the Houston District

STATEMENT OF WORK

Bipartisan Infrastructure LAW (BIL) District Project Coordinator Houston District Table of Contents

INTRODUCTION AND OVERVIEW3
BACKGROUND3
SCOPE OF WORK3
OBJECTIVES3
Program Management Support - District Project Coordination4
Management Analysis – District Project Coordination4
TASKS5-6
END RESULTS/DELIVERABLES6
List of Deliverables by Task6-7
Transmittal/Delivery/Accessibility7
OTHER CONSIDERATIONS7
PROGRESS/COMPLIANCE7

1.0 Introduction and Overview

This Statement of Work (SOW) is for District Project Coordinator (DPC) in support of the Federal Aviation Administration’s portion of the Bipartisan Infrastructure Law (BIL) and reimbursable programs (including those arising from Airport Improvement Program (AIP) appropriations and other directly funded reimbursable projects).

1.1 Background

The Implementation Services Team (AJW-213) is responsible for centralized management and is the single accountable office for the planning, integration, coordination, and implementation of various components. The AJW-213 team Manager is responsible for establishing the necessary infrastructure to ensure timely and efficient program execution. The Implementation Services Team of the Federal Aviation Administration (AJW-213) plays an important role in implementing and executing programs and projects to safely establish, replace, modernize and sustain the National Airspace System (NAS).

1.2 Scope of Work

The Contractor must provide a DPC to support the AJW-213 PMO and the Houston District Manager in development, transition, and implementation activities. The DPC must perform duties to provide program management, program/financial management, independent cost analysis and support services to ATO for the Houston District service area to include professional services for project coordination, resource management, business management, communications, operations and integration, and management analysis. Additional tasks include assisting the District manager with program management administration support to include data analysis involving project planning, resource and financial analysis. The DPC responsibilities also include working with the Program implementation Manager in the preparation of Baseline Scope Agreements.

The DPC will work closely with Tech Services NAS Program Managers (NPMs) and PRG Portfolio Management and Integration (PMI) teams to effectively identify, coordinate and integrate activities within the District.

1.3 Objectives

1.3.1 Technical Work Areas

Types of work that may be performed under this Statement of Work (SOW) are described below. In performing all work under the Contract, the DPC and the PA must adhere to all Occupational Safety and Health Administration (OSHA) requirements, all FAA occupational safety programs and requirements as set forth in the List of Applicable Documents, all taxation laws, and all applicable federal, state and local government codes, statutes, laws and regulations (including the obtaining of any required permits). Requirements may include but not be limited to project coordination and oversight activities related to new construction or installation, restoration, service life extension, demolition/removal, and refurbishment. The Contractor will be responsible for the scope of work contained in this contract and/or authorized/executed modifications thereto. Projects may originate from within the FAA, such as from the Corporate Work Plan (CWP), or from reimbursable agreements between the FAA and other entities that involve protection of US national airspace, national defense or the FAA National Airspace System (NAS).

1.3.2 Program Management Support

The DPC must provide expertise in cross-programmatic planning and coordination of implementation activities as well as operational activities. The DPC will work closely with and enhance the current project support entities within Planning and Requirements Groups (PRG), Engineering Services (ES), Technical Services (TS), System Support Centers (SSCs) and the Districts. The DPC resources are expected to serve the entire District and its Air Traffic Services Community and will serve as the joint liaison between the District Office/SSC (ATS and AJW), Engineering Services, PRG, Headquarters program offices, local Airport District Office personnel, and local commercial airport entities.

1.3.3 Management Analysis

The DPC’s integrated coordination of activities within the Districts is absolutely critical. This requires program coordination among the geographical field locations within the District. The DPC should be available to attend in-person meetings in the District with a 24-hour notice. The DPC will be a trusted third-party agent, who provides expertise in cross- management planning and coordination of implementation activities as well as operational activities throughout the District. The DPC will work closely with and enhance the current project support entities within Planning and Requirements Groups (PRG), Engineering Services (ES), Technical Services (TS), System Support Centers (SSCs) and the Districts. The DPC with will serve the entire District and its Air Traffic Services Community. The DPC will be a NAS Program and Operations Subject Matter Expert (SME) and will serve as the joint liaison between the District Office/SSC (ATS and AJW), Engineering Services, PRG, Headquarters program offices, local Airport District Office personnel, and local commercial airport entities. The DPC will be an active advocate for the coordination, integration and planning of all projects and programs within the district. The DPC will use the FAA project management system and tools (e.g., Corporate Work Plan [CWP]) to identify, coordinate and track implementation activities at the district level.

The DPC require strong analytical and critical thinking capabilities with demonstrated ability to compile, assess and analyze large volumes of data from multiple sources (including operational data, project data, and administrative data sources, etc.) to identify key coordination and integration requirements. The DPC will work closely with Tech Services NAS Program Managers (NPMs) and PRG Portfolio Management and Integration (PMI) teams to effectively identify, coordinate and integrate activities within the District. The DPC should reside in or near the district boundaries to facilitate the integration of work activities among the various field locations and offices within the area of responsibility. The DPC must provide management services that ensure the quality, timeliness, and cost efficiency of all technical efforts provided under this Contract.

1.4 Tasks

The contractor must be cognizant of all the tasks dimensions that each labor category will perform in order meet the Government's expectations.

Each labor category will perform the following core tasks in support of BIL funded projects for the Houston District:

District Project Coordinator

Core Function
Details

Serve as FAA/Airspace District point of contact on project implementation and coordination related issues Serve as the primary FAA point of contact for the District, SSCs, TSOGs, PRG, ATO Management and ES on project related issues Assist with project coordination and communication efforts Serve as liaison for District with the local airport authorities and FAA Airport District Offices (ADOs) Participate in high-visibility or key FAA Stakeholder meetings in support of the District Help all stakeholders speak with ‘One FAA Voice’ Provide an operational overview to all Stakeholders on all District implementation activities.

Facilitate/Coordinate operational and project implementation efforts at the District Level to maximize efficiency and resource utilization Maintain an integrated/coordinated FAA Airspace District Project plan including program/project implementation activities, operational activities, airport activities and plans, etc.

Coordinate project milestones, constraints, solutions, status of active and future high-visibility projects at the District level Compile, assess and analyze large data sets from various sources to identify coordination requirements, impacts, solutions and recommendations Participate in or lead efforts to align FAA resources at the District Level to maximize efficiencies

Core Function
Details

Minimize project implementation impacts on NAS operations Improve coordination and information sharing among all FAA stakeholders including, but not limited to, PRG (PMI, PIMs, Planners, Requirements, Resource Planners, EOSH) ES (Lead Engineers, PIPOCs), TSOG (NPMs/NIM’s, Ops Engineers), and SSCM/SSC Coordinators Anticipate and plan for contingencies for project issues during design, construction and implementation that may adversely affect NAS operations.

Actively explore District initiated ideas and suggestions that improve NAS and Airspace safety and efficiency Support development of Operational Risk Management (ORM) documentation and plans

Strengthen relationship of all FAA participants and stakeholders within the Airspace Districts Ensure effective communication among stakeholders Establish a trustworthy relationship with district personnel and stakeholders Solicit customer feedback for improvements Participate in FAA stakeholder functions/meetings such as: quarterly, weekly, monthly, key stakeholder, key projects

1.5 End Results/Deliverables

AJW-213 requires the DPC to provide final report 30 days prior to end of base year and each option year awarded with breakout of all work completed aligning to each task.

1.5.1 List of Deliverables by Task

Deliverable

Quantity
Due Date

Monthly Progress Report for Tasks A,B,C, D

Original plus 1
10 working days after close of

month

Property Inventory

Original
As required
Standard Operating Procedures
Original; on line and soft copies as required
Annual documentation as needed. Initial SOPs due one month after contract start.

The DPC must upload each deliverable to the BIL sharepoint, an e-mail attachment to Contracting Officer Representative and any others as requested.

1.5.2 Other Considerations

In addition to the above deliverables, the DPC must provide the necessary data to support the analyses provided as part of each task. The contractor must develop and prepare executive level data and briefings, documentation for program and budget reviews.

1.5.3 Progress/Compliance

The AJW-213 requires the DPC to provide status reports, attend meetings, quarterly program reviews in order to monitor progress and ensure compliance. The District manager will have list of agreed upon tasks and activities to be completed and report on by the DPC.

image1.jpeg