Attachement 1 - I-75 Zilwaukee Ramps C and G Package.pdf
PDF 231 KB Posted
- Solicitation number
- RFP 591 250000001510 1
- Issued by
- Saginaw County, Brooklyn Village, Michigan
About this file
This is a maintenance project specification document from the Michigan Department of Transportation (MDOT) for the I-75/Zilwaukee Bridge Ramps C and G package located in Buena Vista Township, Saginaw County. The project involves placing a 2-inch HMA (Hot Mix Asphalt) overlay on two ramps: Ramp C, an I-75 southbound on-ramp from M-13 spanning 0.48 miles (Sta. 29+20 to Sta. 54+40), and Ramp G, an I-75 southbound off-ramp to M-13 spanning 0.41 miles (Sta. 6+00 to Sta. 26+50). Both ramps are 16 feet wide with shoulders. The work schedule requires completion between May 5, 2025, and May 16, 2025, with work to be completed within five consecutive calendar days of commencement. Contractors must provide a minimum of three calendar days' notice prior to beginning work to Dan Senske (989-233-1053) and confirm dates with Kirk Habowski (989-225-5978). No site visits or bidders' meetings are specified in this document.
This is a MDOT Maintenance-funded project with no allowance for overpayment or extras; all material, labor, and mobilization costs must be included in the bid price. The HMA specification is 5EML: PG 64-28 with an AWI of 260. Ramp G requires no detour as it will be coordinated with a concurrent project (JN 216727), while Ramp C detour will be handled by MDOT forces. Work on Saturdays and Sundays requires engineer discretion and preapproval. The project will be awarded to the low bidder subject to MDOT approval for funding, with MDOT reserving the right to reject unqualified bids. Before award, MDOT may request a site plan review meeting with the successful low bidder. All work must comply with the Michigan Department of Transportation 2020 Standard Specifications for Construction.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
C S
X
R
R
BUENA VISTA TWP.
T13N,R5E
ZILWAUKEE TWP.
23 W O
L F R
D
O U
T E
R D
R
HACK RD
ZILWAUKEE
CARROL
LT
ON
W E
S T
E R
V E
L T S
T
S H
E R
M A
N R
D
R A
M P G
R A
M P C
S A G I N A
W
S A
G I
N A
W R I
V E
R
JN:
DRAWING SHEET
I-75/M
TITLE
73111
TSC: DATE:DESIGN UNIT: 2/6/25 BCTSC BAY CITY
FILE:
I-75 / ZILWAUKEE BRIDGE RAMPS
TITLE SHEET
NO SCALE
Michigan Department of Transportation
SECT
CS:
MICHIGAN DEPARTMENT OF TRANSPORTATION
SAGINAW COUNTY
BUENA VISTA TOWNSHIP
ROUTE: I-75 / ZILWAUKEE BRIDGE RAMPS
N
RAMP G
RAMP C
I-75/M-13
LOCATION
PROJECT
MDOT Maintenance Project Log
Job Location:
Ramp C, I-75 On Ramp from M-13
0.48 miles, Buena Vista Township, Saginaw County POB Sta 29+20 - Edge of Concrete at M-13 POE Sta 54+40 – To new concrete pavement and HMA shoulder ends
Ramp G, I-75 Off Ramp to M-13
0.41 miles, Buena Vista Township, Saginaw County POB Sta 6+00 POE Sta 26+50 – Edge of Concrete at M-13
Stationing Information:
All stationing information is approximate. Stationing is shown on the 2 plans sheets.
Project Schedule:
Project to be coordinated with JN 216727.
Work may begin immediately after receiving approval from MDOT. Work to be completed between May 5, 2025, to May 16, 2025. Once work starts, must be completed in 5 consecutive days. Notice must be provided to Dan Senske at 989-233- 1053 a minimum of three (3) calendar days prior to beginning work. Also, confirm dates with Kirk Habowski 989-225-5978.
Description of work:
Ramp C The work on this 16’ wide road with shoulders shall consist of placing 2” HMA overlay.
(HMA, 5EML: PG 64-28, AWI: 260).
Ramp G The work on this 16’ wide road with shoulders shall consist of placing 2” HMA overlay.
(HMA, 5EML: PG 64-28, AWI: 260).
Maintaining Traffic:
Ramp G will not require a detour, since it will be coordinated with JN 216727.
Ramp C detour will be done by MDOT forces.
Work on Saturdays and Sundays will be at the Engineers discretion and require preapproval.
This project is a Maintenance funded project, which means that there will be absolutely no overpayment or extras. All material, labor and mobilization shall be included in the bid.
MDOT will have the low bid reviewed and approved for funding. MDOT reserves the right to reject any bid that appears to be unqualified. Before award, MDOT may request a site plan review meeting with the low bid contractor.
The improvements will be done in accordance with the Michigan Department of Transportation 2020 Standard Specifications for Construction.
0 4
0 5 0 5
I-75
M -1
E
N D
CS:
JN:
TSC:
DATE:
DESIGN UNIT:
HORZ. (FT)
BCTSC
BAY CITY
RAMP C
I-75 SB ZILWAUKEE ON RAMP FROM M-13
Michigan Department of Transportation
SECT
HMA SHOULDERS END HERE
EDGE OF NEW CONCRETE PAVEMENT
POE 54+40
EDGE OF HMA/CONC PAVEMENT
POE 54+40
G ra s s
6+
7+0
8+00
9+00
.8
P
O E
M -1
I-75
CS:
JN:
TSC:
DATE:
DESIGN UNIT:
HORZ. (FT)
BCTSC
BAY CITY
RAMP G
I-75 SB ZILWAUKEE OFF RAMP TO M-13
Michigan Department of Transportation
SECT
EDGE OF HMA/CONC PAVEMENT
POE 26+50
POB 6+00
| SB I-75 RAMP TO M-13 TITLE SHEET |
| Ramp C and G zilwaukee bridge proposal |
| RAMP C |
| RAMP G |