Attach1-ProjectSite Detail Sketch-PartialDraw-Photos-W912C321Q005A20210805.pdf
PDF 8 MB Posted
- Solicitation number
- W912C321Q005A
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Wind Turbine
Cabinet
HH-4D
Building 399
Building 566
MH-25
New underground fiber optic line layout from existing cabinet next to wind turbine to existing IT Hand Hole HH-4D
New 2FT x 2FT X3 FT pull box
Building 34
(DPW)
Power Substation
Water Park Complex
HH-4C
HH-4B
HH-4A
MH-4
MH-3
WORK SITES OVERVIEW
Wind Turbine
New underground fiber optic line layout from existing cabinet next to wind turbine to existing IT Hand Hole HH-4D
Building 399
Building 34
(DPW)
Power Substation
Water Park Complex
Cabinet
HH-4D
New 2FT x 2FT x 3FT pull box
POTABLE WATER
PVC DR-18 PIPE
HH-4C
HH-4B
HH-4AMH-4
MH-3
WORK SITE WT CABINET TO BLDG. 399
Existing Potable Water Lines Layout
Existing Wastewater Lines Layout Existing Overhead Electric Lines LayoutExisting Stormwater Lines Layout
Existing Street Lighting Distribution
PHOTOS WORK SITE DEMARKING INTENDED TRENCH LINE GENERAL ROUTE - FROM WT CABINET TO BLDG. 399 (1 of 2)
PHOTOS WORK SITE DEMARKING INTENDED TRENCH LINE GENERAL ROUTE - FROM WT CABINET TO BLDG. 399 (2 of 2) carla.rosariorivera Sticky Note Who is going to move the concrete barriers Gov or Contractor? I did not see comments related to action.
carla.rosariorivera Sticky Note See comment above