Attach_B_Specifications_07.16.2026.pdf

PDF 2 MB Posted

Attached to
ODVA HVAC Replacement for the Lebanon Veterans Home in Lebanon Oregon
Solicitation number
S-27400-00016236
Issued by
Lake County, Oregon

About this file

This file is a comprehensive project manual and specifications document for the HVAC Remodel of the Oregon Veterans' Home in Lebanon, prepared by Forward Architecture, LLC, on behalf of the Oregon Department of Veterans' Affairs. The project involves the alteration and HVAC system replacement for a 154-bed skilled nursing facility where the owner intends to continue occupying the building during construction with limited temporary relocation. The scope includes demolition and removal work, alterations to existing HVAC, plumbing, electrical, fire suppression, fire alarm, telephone, and security systems, with all work indicated on drawings and specifications throughout the project manual. Key project contacts include Troy Croff as the Facility and Construction Project Manager for the owner, Kaley Fought as Principal Architect at Forward Architecture LLC, and Takako Baker as Principal at MFIA Inc., the mechanical and electrical engineering consultant. The contractor must submit a preliminary construction schedule within 10 days of the Notice to Proceed, a complete schedule within 20 days, and updated schedules with each application for payment. Progress photographs must be submitted with each payment application, taken within three days prior to submission. The contract requires compliance with the State of Oregon General Conditions for Public Improvement Projects and adherence to multiple regulatory codes including the Oregon Structural Specialty Code (2022), Oregon Mechanical Specialty Code (2022), Oregon Energy Efficiency Specialty Code (2025), and applicable local amendments.

The document establishes substantial quality assurance requirements, including that any mechanical contractor must be legally established and licensed in Oregon for a minimum of five years and must have minimum 10 years of documented experience installing Variable Refrigerant Flow (VRF) systems exceeding 20 tons capacity, with at least three I-occupancy facility installations completed within the past five years. Substitution requests must be submitted during procurement using form 00 4325 or during construction using form 00 6325, with architectural approval required prior to fabrication or installation. All products must comply with Indoor Emissions Standards and VOC content restrictions as specified in Section 01 6116, with acceptable evidence including GREENGUARD Gold certification, SCS certifications, or independent laboratory testing. The contractor must provide temporary utilities, sanitary facilities, security, waste removal, and maintain a weathertight field office. Payment procedures require applications submitted at intervals specified in the agreement using Owner and Architect-approved forms, with schedule of values formatted according to the project manual table of contents. The project manual does not identify specific contract pricing, funding sources, set-asides, or award dates within the specifications sections provided, nor does it identify an incumbent contractor.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

00 0101

HVAC Remodel for Oregon Veterans' Home, Lebanon 00 0101 - 1 Project Title Page

SECTION 00 0101

PROJECT TITLE PAGE

PROJECT MANUAL

FOR

HVAC REMODEL FOR OREGON VETERANS' HOME, LEBANON

OREGON DEPARTMENT OF VETERANS' AFFAIRS

600 N 5TH ST

LEBANON, OREGON97355

DATE: 07-16-2026

PREPARED BY:

FORWARD ARCHITECTURE, LLC

END OF SECTION

R KALEY M FOUGHTEG

ISTERED ARCHITECT

S TAT E OF OREGONSALEM, OREGON

00 0101

Veterans' Home, Lebanon 00 0101 - 2 Project Title Page

This page intentionally left blank

00 0103

Veterans' Home, Lebanon 00 0103 - 1 Project Directory

SECTION 00 0103

PROJECT DIRECTORY

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Identification of project team members and their contact information.

1.02 OWNER:

A. Name: Oregon Department of Veterans' Affairs B. Primary Contact: All correspondence from the Contractor to the Architect will be through this party, unless alternate arrangements are mutually agreed upon at preconstruction meeting.

1. Title: Facility and Construction Project Manager.

2. Name: Troy Croff.

1.03 CONSULTANTS:

A. Architect: Design Professional of Record. All correspondence from the Contractor regarding construction documents authored by Architect's consultants will be through this party, unless alternate arrangements are mutually agreed upon at preconstruction meeting.

1. Company Name: Forward Architecture, LLC.

a. Address Line 1: PO Box 44.

b. City: Salem.

c. State: OR.

d. Zip Code: 97308.

e. Telephone: 503.851.7401.

2. Primary Contact:

a. Title: Principal Architect.

b. Name: Kaley Fought.

B. Mechanical Engineering Consultant - HVAC:

1. Company Name: MFIA, Inc.

a. Address Line 1: 2007 Ash St.

b. City: Portland.

c. State: OR.

d. Zip Code: 97214.

e. Telephone: 503.234.0548.

2. Primary Contact:

a. Title: Principal.

b. Name: Takako Baker.

C. Electrical Engineering Consultant:

1. Company Name: MFIA, Inc.

a. Address Line 1: 2007 Ash St.

b. City: Portland.

c. State: OR.

d. Zip Code: 97214.

e. Telephone: 503.234.0548.

2. Primary Contact:

a. Title: Principal.

b. Name: Takako Baker.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

END OF SECTION

00 0103

Veterans' Home, Lebanon 00 0103 - 2 Project Directory

00 0110

Veterans' Home, Lebanon 00 0110 - 1 Table of Contents

SECTION 00 0110

TABLE OF CONTENTS

PROCUREMENT AND CONTRACTING REQUIREMENTS

Division 00 -- Procurement and Contracting Requirements

A. 00 0101 - Project Title Page B. 00 0103 - Project Directory C. 00 0110 - Table of Contents D. 00 4325 - Substitution Request Form - During Procurement E. 00 6325 - Substitution Request Form - During Construction

SPECIFICATIONS

Division 01 -- General Requirements

A. 01 1000 - Summary B. 01 2000 - Price and Payment Procedures C. 01 2500 - Substitution Procedures D. 01 3000 - Administrative Requirements E. 01 3216 - Construction Progress Schedule F. 01 4000 - Quality Requirements G. 01 4100 - Regulatory Requirements H. 01 4216 - Definitions I. 01 5000 - Temporary Facilities and Controls J. 01 5100 - Temporary Utilities K. 01 5813 - Temporary Project Signage L. 01 6000 - Product Requirements M. 01 6116 - Volatile Organic Compound (VOC) Content Restrictions N. 01 7000 - Execution and Closeout Requirements O. 01 7419 - Construction Waste Management and Disposal P. 01 7800 - Closeout Submittals Q. 01 9113 - General Commissioning Requirements

Division 02 -- Existing Conditions (NOT USED) Division 03 -- Concrete (NOT USED) Division 04 -- Masonry (NOT USED) Division 05 -- Metals (NOT USED) Division 06 -- Wood, Plastics, and Composites (NOT USED) Division 07 -- Thermal and Moisture Protection (NOT USED) Division 08 -- Openings (NOT USED) Division 09 -- Finishes

A. 09 9000 - Painting and Coating

00 0110

Veterans' Home, Lebanon 00 0110 - 2 Table of Contents

Division 10 -- Specialties (NOT USED) Division 11 -- Equipment (NOT USED) Division 12 -- Furnishings (NOT USED) Division 13 -- Special Construction (NOT USED) Division 14 -- Conveying Equipment (NOT USED) Division 21 -- Fire Suppression (NOT USED) Division 22 -- Plumbing (NOT USED) Division 23 -- Heating, Ventilating, and Air-Conditioning (HVAC)

A. 23 0500 - HVAC Materials and Methods B. 23 0548 - Mechanical Sound and Vibration Control C. 23 0590 - Testing, Adjusting, and Balancing D. 23 0700 - HVAC Insulation E. 23 0923 - Controls F. 23 0993 - Sequence of Operations for HVAC Controls G. 23 2300 - Refrigerant Piping System H. 23 3000 - Air Distribution I. 23 4000 - Air Cleaning Devices J. 23 7400 - Packaged HVAC Units K. 23 7700 - VRV Heat Recovery

Division 25 -- Integrated Automation (NOT USED) Division 26 -- Electrical

A. 26 0500 - Common Work Results for Electrical B. 26 0519 - Low-Voltage Electrical Power Conductors and Cables C. 26 0526 - Grounding and Bonding for Electrical Systems D. 26 0529 - Hangers and Supports for Electrical Systems E. 26 0533 - Raceway and Boxes for Electrical Systems F. 26 0553 - Identification for Electrical Systems G. 26 2726 - Wiring Devices H. 26 2800 - Circuit Protective Devices

Division 27 -- Communications (NOT USED) Division 28 -- Electronic Safety and Security (NOT USED) Division 31 -- Earthwork (NOT USED) Division 32 -- Exterior Improvements (NOT USED) Division 33 -- Utilities (NOT USED) Division 34 -- Transportation (NOT USED) Division 40 -- Process Integration (NOT USED)

00 4325

Veterans' Home, Lebanon 00 4325 - 1 Substitution Request Form -

During Procurement

SECTION 00 4325

SUBSTITUTION REQUEST FORM - DURING PROCUREMENT

00 4325

Veterans' Home, Lebanon 00 4325 - 2 Substitution Request Form -

During Procurement

TO: ________________________________________________________________________________ PROJECT NAME: ____________________________________________________________________

WE HEREBY SUBMIT FOR CONSIDERATION, THE FOLLOWING PRODUCT INSTEAD OF

SPECIFIED ITEM

FOR ABOVE PROJECT:

SPECIFICATION SECTION: ____________________________________________________________ PARAGRAPH: _______________________________________________________________________ SPECIFIED ITEM: ____________________________________________________________________ PROPOSED SUBSTITUTION: __________________________________________________________ MANUFACTURER: ___________________________________________________________________ ADDRESS: __________________________________________________________________________

FOR PROPOSED SUBSTITUTION:

A. Attach complete data, including product description, specifications, drawings, photographs, and performance and test data adequate for evaluation of the request; applicable portions of the data shall be clearly identified.

B. Data shall also include a description of changes to the Contract Documents that the proposed substitution will require for its proper installation.

THE UNDERSIGNED STATES THAT THE FOLLOWING PARAGRAPHS ARE CORRECT:

A. The proposed substitution does not affect dimensions and functional clearances.

B. The undersigned will pay for changes to the building design, including A/E design, detailing and construction costs caused by the requested substitution.

C. The proposed substitution will have no adverse effect on other trades and will not affect or delay progress schedule.

D. Proposed substitution has been fully investigated and determined to be equal or superior in all respects to specified product.

E. Same warranty will be furnished for proposed substitution as for specified product.

F. Same maintenance service and source of replacement parts, as applicable, is available.

SUBMITTED BY: _____________________________________________________________________ SIGNED BY: _____________________________________________ DATE: _____________________ COMPANY: __________________________________________________________________________ ADDRESS: __________________________________________________________________________ PHONE: ____________________________________________________________________________

ARCHITECT'S REVIEW AND ACTION

__ No Exceptions to Substitution - Make submittals in accordance with specification section 01 2500 Substitution Procedures.

__ Exceptions Noted to Substitution - Make submittals in accordance with specification section 01 2500 Substitution Procedures.

__ Substitution Rejected - Use specified materials.

__ Substitution Received Too Late - Use specified materials.

SIGNED BY: _____________________________________________ DATE: _____________________

00 6325

Veterans' Home, Lebanon 00 6325 - 1 Substitution Request Form -

During Construction

SECTION 00 6325

SUBSTITUTION REQUEST FORM - DURING CONSTRUCTION

Veterans' Home, Lebanon 00 6325 - 2 Substitution Request Form -

During Construction

TO: ________________________________________________________________________________ PROJECT NAME: ____________________________________________________________________

WE HEREBY SUBMIT FOR CONSIDERATION, THE FOLLOWING PRODUCT INSTEAD OF

SPECIFIED ITEM

FOR ABOVE PROJECT:

SPECIFICATION SECTION: ____________________________________________________________ PARAGRAPH: _______________________________________________________________________ SPECIFIED ITEM: ____________________________________________________________________ PROPOSED SUBSTITUTION: __________________________________________________________ Manufacturer: ___________________________________________________________________ Address: _________________________________________________________________________ Installer: ________________________________________________________________________ Address: _________________________________________________________________________ History: __ New product __ 2 - 5 years old __ 5 - 10 years old __ More than 10 years old Differences between proposed substitution and specified product:

FOR PROPOSED SUBSTITUTION:

Reason for not providing specified item:

Similar Installation:

Project: __________________________________________________________________________ Address: _________________________________________________________________________ Architect: ________________________________________________________________________ Owner: ___________________________________________________________________________ Date Installed: ___________________________________________________________________ Proposed Substitution affects other parts of Work: __ No __ Yes; explain:

Savings to Owner for accepting substitution: ______________________________ Proposed substitution changes Contract Time: __ No __ Yes [Add] [Deduct] ______ days.

Supporting Data Attached: __ Drawings __ Product Data __ Samples __ Tests __ Other

THE UNDERSIGNED STATES THAT THE FOLLOWING PARAGRAPHS ARE CORRECT:

A. The proposed substitution does not affect dimensions and functional clearances.

B. The undersigned will pay for changes to the building design, including A/E design, detailing and construction costs caused by the requested substitution.

C. The proposed substitution will have no adverse effect on other trades and will not affect or delay progress schedule.

D. Proposed substitution has been fully investigated and determined to be equal or superior in all respects to specified product.

E. Same warranty will be furnished for proposed substitution as for specified product.

Veterans' Home, Lebanon 00 6325 - 3 Substitution Request Form -

During Construction

F. Same maintenance service and source of replacement parts, as applicable, is available.

G. Cost data as stated above is complete. Claims for additional costs related to accepted substitution which may subsequently become apparent are to be waived.

H. Coordination, installation, and changes in the Work as necessary for accepted substitution will be complete in all respects.

SUBMITTED BY: _____________________________________________________________________

SIGNED BY: ___________________________________________________ DATE:

COMPANY: __________________________________________________________________________ ADDRESS: __________________________________________________________________________ PHONE: ____________________________________________________________________________

ARCHITECT'S REVIEW AND ACTION

__ No Exceptions to Substitution - Make submittals in accordance with specification section 01 2500 Substitution Procedures.

__ Exceptions Noted to Substitution - Make submittals in accordance with specification section 01 2500 Substitution Procedures.

__ Substitution Rejected - Use specified materials.

__ Substitution Received Too Late - Use specified materials.

SIGNED BY: ____________________________________________________ DATE: ______________

Veterans' Home, Lebanon 00 6325 - 4 Substitution Request Form -

During Construction

01 1000

Veterans' Home, Lebanon 01 1000 - 1 Summary

SECTION 01 1000

SUMMARY

PART 1 GENERAL

1.01 PROJECT

A. Project Name: HVAC Remodel for Oregon Veterans' Home, Lebanon B. Owner's Name: Oregon Department of Veterans' Affairs.

C. Architect's Name: Forward Architecture, LLC.

D. The Project consists of the alteration of The Oregon Veterans' Home in Lebanon, a 154-bed

Skilled Nursing Facility. The project scope includes an HVAC system replacement. .

1.02 CONTRACT DESCRIPTION

A. Contract Type: As indicated in the Invitation to Bid. The following shall apply:

1. State of Oregon General Conditions for Public Improvement Project.

1.03 DESCRIPTION OF ALTERATIONS WORK

A. Scope of demolition and removal work is indicated on drawings .

B. Scope of alterations work is indicated on drawings.

C. Plumbing (as required): Alter existing system and add new construction, keeping existing in operation.

D. HVAC: Alter existing system and add new construction, keeping existing in operation. Due to I-occupancy of the facility, continuous compliance with State regulations is required. Contractor to provide temporary system as required to maintain regulatory requirements.

E. Electrical Power and Lighting (as required): Alter existing system and add new construction, keeping existing in operation.

F. Fire Suppression Sprinklers (as required): Alter existing system and add new construction, keeping existing in operation.

1. Modifications to be Design and Build.

G. Fire Alarm (as required): Alter existing system and add new construction, keeping existing in operation.

H. Telephone (as required): Alter existing system and add new construction, keeping existing in operation.

I. Security System (as required): Alter existing system and add new construction, keeping existing in operation.

1.04 WORK BY OWNER

A. Owner will supply and install the following:

1. Items noted OFOI (Owner Furnished, Owner Installed) .

B. Owner will supply the following for installation by Contractor:

1. Items noted OFCI (Owner Furnished, Contractor Installed) .

1.05 OWNER OCCUPANCY

A. Owner intends to continue to occupy all portions of the existing building during the entire construction period. Contractor to coordinate with Owner during system changeover to maintain continuous compliance with regulatory requirements.

B. Owner intends to occupy the Project during construction, with limited temporary relocation .

C. Cooperate with Owner to minimize conflict and to facilitate Owner's operations.

D. Schedule the Work to accommodate Owner occupancy.

1.06 CONTRACTOR USE OF SITE AND PREMISES

A. Construction Operations: Limited to areas coordinated with Owner .

01 1000

Veterans' Home, Lebanon 01 1000 - 2 Summary

1. Locate and conduct construction activities in ways that will limit disturbance to site.

B. Arrange use of site and premises to allow:

1. Owner occupancy.

C. Provide access to and from site as required by law and by Owner:

1. Emergency Building Exits During Construction: Keep all exits required by code open during construction period; provide temporary exit signs if exit routes are temporarily altered.

2. Do not obstruct roadways, sidewalks, or other public ways without permit.

D. Existing building spaces may not be used for storage.

E. Time Restrictions:

1. Limit conduct of especially noisy exterior work to the hours of normal building hours .

F. Utility Outages and Shutdown:

1. Limit disruption of utility services to hours the building is unoccupied.

2. Do not disrupt or shut down life safety systems, including but not limited to fire sprinklers and fire alarm system, without 7 days notice to Owner and authorities having jurisdiction.

3. Prevent accidental disruption of utility services to other facilities.

4. Maintain compliance with regulatory requirements for I-occupancy facilities.

1.07 WORK SEQUENCE

A. Coordinate construction schedule and operations with Owner.

PART 2 PRODUCTS - NOT USED

01 2000

Veterans' Home, Lebanon 01 2000 - 1 Price and Payment Procedures

SECTION 01 2000

PRICE AND PAYMENT PROCEDURES

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Procedures for preparation and submittal of applications for progress payments.

B. Documentation of changes in Contract Sum and Contract Time.

C. Change procedures.

D. Correlation of Contractor submittals based on changes.

E. Procedures for preparation and submittal of application for final payment.

1.02 SCHEDULE OF VALUES

A. Use Schedule of Values Form: Any acceptable to Owner and Architect. Provide for review.

B. Electronic media printout including equivalent information will be considered in lieu of standard form specified; submit draft to Architect for approval.

C. Forms filled out by hand will not be accepted.

D. Format: Utilize the Table of Contents of this Project Manual. Identify each line item with number and title of the specification section. Identify site mobilization.

E. Include in each line item, the amount of Allowances specified in this section. For unit cost

Allowances, identify quantities taken from Contract Documents multiplied by the unit cost to achieve the total for the item.

F. Include separately from each line item, a direct proportional amount of Contractor's overhead and profit.

G. Revise schedule to list approved Change Orders, with each Application For Payment.

1.03 APPLICATIONS FOR PROGRESS PAYMENTS

A. Payment Period: Submit at intervals stipulated in the Agreement.

B. Use Form Any acceptable to Owner and Architect. Provide for review.

C. Electronic media printout including equivalent information will be considered in lieu of standard form specified; submit sample to Architect for approval.

D. Forms filled out by hand will not be accepted.

E. For each item, provide a column for listing each of the following:

1. Item Number.

2. Description of work.

3. Scheduled Values.

4. Previous Applications.

5. Work in Place and Stored Materials under this Application.

6. Authorized Change Orders.

7. Total Completed and Stored to Date of Application.

8. Percentage of Completion.

9. Balance to Finish.

10. Retainage.

F. Execute certification by signature of authorized officer.

G. Use data from approved Schedule of Values. Provide dollar value in each column for each line item for portion of work performed and for stored products.

H. List each authorized Change Order as a separate line item, listing Change Order number and dollar amount as for an original item of work.

Veterans' Home, Lebanon 01 2000 - 2 Price and Payment Procedures

I. Submit one (1) signed and notarized copy of each Application for Payment to Architect and Owner.

J. Include the following with the application:

1. Transmittal letter as specified for submittals in Section 01 3000.

2. Construction progress schedule, revised and current as specified in Section 01 3000.

3. Current construction photographs specified in Section 01 3000.

4. Partial release of liens from major subcontractors and vendors.

5. Project record documents as specified in Section 01 7800, for review by Owner which will be returned to the Contractor.

K. When Architect requires substantiating information, submit data justifying dollar amounts in question. Provide one copy of data with cover letter for each copy of submittal. Show application number and date, and line item by number and description.

1.04 MODIFICATION PROCEDURES

A. For minor changes not involving an adjustment to the Contract Sum or Contract Time, Architect will issue instructions directly to Contractor.

B. For other required changes, Architect will issue a document signed by Owner instructing

Contractor to proceed with the change, for subsequent inclusion in a Change Order.

1. The document will describe the required changes and will designate method of determining any change in Contract Sum or Contract Time.

2. Promptly execute the change.

C. For changes for which advance pricing is desired, Architect will issue a document that includes a detailed description of a proposed change with supplementary or revised drawings and specifications, a change in Contract Time for executing the change with a stipulation of any overtime work required and the period of time during which the requested price will be considered valid. Contractor shall prepare and submit a fixed price quotation within 5 days.

D. Contractor may propose a change by submitting a request for change to Architect, describing the proposed change and its full effect on the work, with a statement describing the reason for the change, and the effect on the Contract Sum and Contract Time with full documentation.

Document any requested substitutions in accordance with Section 01 6000.

E. Computation of Change in Contract Amount: As specified in the Agreement and Conditions of the Contract.

F. Substantiation of Costs: Provide full information required for evaluation.

1. Provide the following data:

a. Quantities of products, labor, and equipment.

b. Taxes, insurance, and bonds.

c. Overhead and profit.

d. Justification for any change in Contract Time.

e. Credit for deletions from Contract, similarly documented.

2. Support each claim for additional costs with additional information:

a. Origin and date of claim.

b. Dates and times work was performed, and by whom.

c. Time records and wage rates paid.

d. Invoices and receipts for products, equipment, and subcontracts, similarly documented.

3. For Time and Material work, submit itemized account and supporting data after completion of change, within time limits indicated in the Conditions of the Contract.

G. Execution of Change Orders: Architect will issue Change Orders for signatures of parties as provided in the Conditions of the Contract.

H. After execution of Change Order, promptly revise Schedule of Values and Application for

Payment forms to record each authorized Change Order as a separate line item and adjust the Contract Sum.

Veterans' Home, Lebanon 01 2000 - 3 Price and Payment Procedures

I. Promptly revise progress schedules to reflect any change in Contract Time, revise sub-schedules to adjust times for other items of work affected by the change, and resubmit.

J. Promptly enter changes in Project Record Documents.

1.05 APPLICATION FOR FINAL PAYMENT

A. Prepare Application for Final Payment as specified for progress payments, identifying total adjusted Contract Sum, previous payments, and sum remaining due.

B. Application for Final Payment will not be considered until the following have been accomplished:

1. All closeout procedures specified in Section 01 7000.

PART 2 PRODUCTS - NOT USED

Veterans' Home, Lebanon 01 2000 - 4 Price and Payment Procedures

01 2500

Veterans' Home, Lebanon 01 2500 - 1 Substitution Procedures

SECTION 01 2500

SUBSTITUTION PROCEDURES

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Procedural requirements for proposed substitutions.

1.02 RELATED REQUIREMENTS

A. Section 00 4325 - Substitution Request Form - During Procurement: Required form for substitution requests made prior to award of contract (During procurement).

B. Section 00 6325 - Substitution Request Form - During Construction: Required form for substitution requests made after award of contract (During construction).

1.03 DEFINITIONS

A. Substitutions: Changes from Contract Documents requirements proposed by Contractor to materials, products, assemblies, and equipment.

1. Substitutions for Cause: Proposed due to changed Project circumstances beyond

Contractor's control.

a. Unavailability.

b. Regulatory changes.

2. Substitutions for Convenience: Proposed due to possibility of offering substantial advantage to the Project.

a. Substitution requests offering advantages solely to the Contractor will not be considered.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION

3.01 GENERAL REQUIREMENTS

A. A Substitution Request for products, assemblies, materials, and equipment constitutes a representation that the submitter:

1. Has investigated proposed product and determined that it meets or exceeds the quality level of the specified product, equipment, assembly, or system.

2. Agrees to provide the same warranty for the substitution as for the specified product.

3. Agrees to provide same or equivalent maintenance service and source of replacement parts, as applicable.

4. Agrees to coordinate installation and make changes to other work that may be required for the work to be complete, with no additional cost to Owner.

5. Waives claims for additional costs or time extension that may subsequently become apparent.

6. Agrees to reimburse Owner and Architect for review or redesign services associated with re-approval by authorities.

B. Document each request with complete data substantiating compliance of proposed substitution with Contract Documents. Burden of proof is on proposer.

1. Note explicitly any non-compliant characteristics.

C. Content: Include information necessary for tracking the status of each Substitution Request, and information necessary to provide an actionable response.

1. Forms indicated and included in the Project Manual are adequate for this purpose, and must be used.

D. Limit each request to a single proposed substitution item.

1. Submit an electronic document, combining the request form with supporting data into single document.

3.02 SUBSTITUTION PROCEDURES DURING PROCUREMENT

A. Submittal Time Restrictions:

01 2500

Veterans' Home, Lebanon 01 2500 - 2 Substitution Procedures

1. Instructions to Bidders specifies time restrictions and the documents required for submitting substitution requests during the bidding period.

B. Submittal Form (before award of contract):

1. Submit substitution requests by completing the form in Section 00 4325; see this section for additional information and instructions. Use only this form; other forms of submission are unacceptable.

3.03 SUBSTITUTION PROCEDURES DURING CONSTRUCTION

A. Submittal Form (after award of contract):

1. Submit substitution requests by completing the form in Section 00 6325; see this section for additional information and instructions. Use only this form; other forms of submission are unacceptable.

B. Submit request for Substitution for Cause immediately upon discovery of need for substitution, but not later than 14 days prior to time required for review and approval by Architect, in order to stay on approved project schedule.

C. Submit request for Substitution for Convenience immediately upon discovery of its potential advantage to the project, but not later than 14 days prior to time required for review and approval by Architect, in order to stay on approved project schedule.

1. In addition to meeting general documentation requirements, document how the requested substitution benefits the Owner through cost savings, time savings, greater energy conservation, or in other specific ways.

2. Document means of coordinating of substitution item with other portions of the work, including work by affected subcontractors.

3. Bear the costs engendered by proposed substitution of:

a. Owner's compensation to the Architect for any required redesign, time spent processing and evaluating the request.

b. Other construction by Owner.

c. Other unanticipated project considerations.

D. Substitutions will not be considered under one or more of the following circumstances:

1. When they are indicated or implied on shop drawing or product data submittals, without having received prior approval.

2. Without a separate written request.

3.04 RESOLUTION

A. Architect may request additional information and documentation prior to rendering a decision.

Provide this data in an expeditious manner.

B. Architect will notify Contractor in writing of decision to accept or reject request.

1. Architect's decision following review of proposed substitution will be noted on the submitted form.

3.05 ACCEPTANCE

A. Accepted substitutions change the work of the Project. They will be documented and incorporated into work of the project by Change Order, Construction Change Directive, Architectural Supplementary Instructions, or similar instruments provided for in the Conditions of the Contract.

3.06 CLOSEOUT ACTIVITIES

A. See Section 01 7800 - Closeout Submittals, for closeout submittals.

B. Include completed Substitution Request Forms as part of the Project record. Include both approved and rejected Requests.

01 3000

Veterans' Home, Lebanon 01 3000 - 1 Administrative Requirements

SECTION 01 3000

ADMINISTRATIVE REQUIREMENTS

PART 1 GENERAL

1.01 SECTION INCLUDES

A. General administrative requirements.

B. Preconstruction meeting.

C. Site mobilization meeting.

D. Progress meetings.

E. Construction progress schedule.

F. Progress photographs.

G. Number of copies of submittals.

H. Requests for Interpretation (RFI) procedures.

I. Submittal procedures.

1.02 RELATED REQUIREMENTS

A. Section 01 6000 - Product Requirements: General product requirements.

B. Section 01 7000 - Execution and Closeout Requirements: Additional coordination requirements.

C. Section 01 7800 - Closeout Submittals: Project record documents; operation and maintenance data; warranties and bonds.

D. Section 01 9113 - General Commissioning Requirements: Additional procedures for submittals relating to commissioning.

1. Where submittals are indicated for review by both Architect and the Commissioning

Provider (CxP), submit one extra and route to Architect first for forwarding to the Commissioning Provider.

2. Where submittals are not indicated to be reviewed by Architect, submit directly to the Commissioning Provider (CxP); otherwise, the procedures specified in this section apply to commissioning submittals.

1.03 GENERAL ADMINISTRATIVE REQUIREMENTS

A. Comply with requirements of Section 01 7000 - Execution and Closeout Requirements for coordination of execution of administrative tasks with timing of construction activities.

B. All documents transmitted for purposes of administration of the contract are to be in electronic

(PDF, MS Word, or MS Excel) format, as appropriate to the document.

C. Make the following types of submittals to Architect:

1. Requests for Information (RFI).

2. Requests for substitution.

3. Shop drawings, product data, and samples.

4. Test and inspection reports.

5. Design data.

6. Manufacturer's instructions and field reports.

7. Applications for payment and change order requests.

8. Progress schedules.

9. Coordination drawings.

10. Correction Punch List and Final Correction Punch List for Substantial Completion.

11. Closeout submittals.

Veterans' Home, Lebanon 01 3000 - 2 Administrative Requirements

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION

3.01 PRECONSTRUCTION MEETING

A. Owner will schedule a meeting after Notice of Award.

B. Attendance Required:

1. Owner.

2. Architect.

3. Contractor.

C. Agenda:

1. Execution of Owner-Contractor Agreement.

2. Submission of executed bonds and insurance certificates.

3. Distribution of Contract Documents.

4. Submission of list of subcontractors, list of products, schedule of values, and progress schedule.

5. Submission of initial Submittal schedule.

6. Designation of personnel representing the parties to Contract and Architect.

7. Procedures and processing of field decisions, submittals, substitutions, applications for payments, proposal request, Change Orders, and Contract closeout procedures.

8. Scheduling.

D. Record minutes and distribute copies within two days after meeting to participants, with copies to Architect, Owner, participants, and those affected by decisions made.

3.02 SITE MOBILIZATION MEETING

A. Owner will schedule meeting at the Project site prior to Contractor occupancy.

B. Attendance Required:

1. Contractor.

2. Owner.

3. Architect.

4. Special consultants.

5. Contractor's superintendent.

6. Major subcontractors.

C. Agenda:

1. Use of premises by Owner and Contractor.

2. Owner's requirements.

3. Construction facilities and controls provided by Owner.

4. Temporary utilities provided by Owner.

5. Survey and building layout.

6. Security and housekeeping procedures.

7. Schedules.

8. Application for payment procedures.

9. Procedures for testing.

10. Procedures for maintaining record documents.

11. Requirements for start-up of equipment.

12. Inspection and acceptance of equipment put into service during construction period.

D. Record minutes and distribute copies within two days after meeting to participants, with copies to Architect, Owner, participants, and those affected by decisions made.

3.03 PROGRESS MEETINGS

A. Make arrangements for meetings, prepare agenda with copies for participants, preside at meetings.

B. Attendance Required:

Veterans' Home, Lebanon 01 3000 - 3 Administrative Requirements

1. Contractor.

2. Owner.

3. Architect.

4. Special consultants.

5. Contractor's superintendent.

6. Major subcontractors.

C. Agenda:

1. Review minutes of previous meetings.

2. Review of work progress.

3. Field observations, problems, and decisions.

4. Identification of problems that impede, or will impede, planned progress.

5. Review of submittals schedule and status of submittals.

6. Review of RFIs log and status of responses.

7. Maintenance of progress schedule.

8. Corrective measures to regain projected schedules.

9. Planned progress during succeeding work period.

10. Maintenance of quality and work standards.

11. Effect of proposed changes on progress schedule and coordination.

12. Other business relating to work.

D. Record minutes and distribute copies within two days after meeting to participants, with copies to Architect, Owner, participants, and those affected by decisions made.

3.04 CONSTRUCTION PROGRESS SCHEDULE

A. Within 10 days after date of the Agreement, submit preliminary schedule defining planned operations for the first 60 days of work, with a general outline for remainder of work.

B. If preliminary schedule requires revision after review, submit revised schedule within 10 days.

C. Within 20 days after review of preliminary schedule, submit draft of proposed complete schedule for review.

1. Include written certification that major Subcontractors have reviewed and accepted proposed schedule.

D. Within 10 days after joint review, submit complete schedule.

E. Submit updated schedule with each Application for Payment.

3.05 PROGRESS PHOTOGRAPHS

A. Submit photographs with each application for payment, taken not more than 3 days prior to submission of application for payment.

B. Photography Type: Digital; electronic files.

C. Provide photographs of site and construction throughout progress of work produced by an experienced photographer, acceptable to Architect.

D. In addition to periodic, recurring views, take photographs of each of the following events:

1. Final completion, minimum of ten (10) photos.

E. Views:

1. Provide non-aerial photographs from four cardinal views at each specified time, until date of Substantial Completion.

2. Consult with Architect for instructions on views required.

3. Provide factual presentation.

4. Provide correct exposure and focus, high resolution and sharpness, maximum depth of field, and minimum distortion.

F. Digital Photographs: 24 bit color, minimum resolution of 1024 by 768, in JPG format; provide files unaltered by photo editing software.

1. Delivery Medium: Via email.

Veterans' Home, Lebanon 01 3000 - 4 Administrative Requirements

2. File Naming: Include project identification, date and time of view, and view identification.

3. PDF File: Assemble all photos into printable pages in PDF format, with 2 to 3 photos per page, each photo labeled with file name; one PDF file per submittal.

3.06 REQUESTS FOR INFORMATION (RFI)

A. Definition: A request seeking one of the following:

1. An interpretation, amplification, or clarification of some requirement of Contract

Documents arising from inability to determine from them the exact material, process, or system to be installed; or when the elements of construction are required to occupy the same space (interference); or when an item of work is described differently at more than one place in Contract Documents.

2. A resolution to an issue which has arisen due to field conditions and affects design intent.

B. Whenever possible, request clarifications at the next appropriate project progress meeting, with response entered into meeting minutes, rendering unnecessary the issuance of a formal RFI.

C. Preparation: Prepare an RFI immediately upon discovery of a need for interpretation of

Contract Documents. Failure to submit a RFI in a timely manner is not a legitimate cause for claiming additional costs or delays in execution of the work.

1. Prepare a separate RFI for each specific item.

a. Review, coordinate, and comment on requests originating with subcontractors and/or materials suppliers.

2. Prepare in a format and with content acceptable to Owner.

3. Combine RFI and its attachments into a single electronic file. PDF format is preferred.

D. Reason for the RFI: Prior to initiation of an RFI, carefully study all Contract Documents to confirm that information sufficient for their interpretation is definitely not included.

1. Unacceptable Uses for RFIs: Do not use RFIs to request the following::

a. Approval of submittals (use procedures specified elsewhere in this section).

b. Approval of substitutions (see Section - 01 6000 - Product Requirements)

c. Changes that entail change in Contract Time and Contract Sum (comply with provisions of the Conditions of the Contract).

d. Different methods of performing work than those indicated in the Contract Drawings and Specifications (comply with provisions of the Conditions of the Contract).

2. Improper RFIs: Requests not prepared in compliance with requirements of this section, and/or missing key information required to render an actionable response. They will be returned without a response.

3. Frivolous RFIs: Requests regarding information that is clearly indicated on, or reasonably inferable from, Contract Documents, with no additional input required to clarify the question. They will be returned without a response.

a. The Owner reserves the right to assess the Contractor for the costs (on time-and-materials basis) incurred by the Architect, and any of its consultants, due to processing of such RFIs.

E. Content: Include identifiers necessary for tracking the status of each RFI, and information necessary to provide an actionable response.

1. Official Project name and number, and any additional required identifiers established in

Contract Documents.

2. Owner's, Architect's, and Contractor's names.

3. Discrete and consecutive RFI number, and descriptive subject/title.

4. Issue date, and requested reply date.

5. Reference to particular Contract Document(s) requiring additional information/interpretation. Identify pertinent drawing and detail number and/or specification section number, title, and paragraph(s).

6. Annotations: Field dimensions and/or description of conditions which have engendered the request.

Veterans' Home, Lebanon 01 3000 - 5 Administrative Requirements

7. Contractor's suggested resolution: A written and/or a graphic solution, to scale, is required in cases where clarification of coordination issues is involved, for example;

routing, clearances, and/or specific locations of work shown diagrammatically in Contract Documents. If applicable, state the likely impact of the suggested resolution on Contract Time or the Contract Sum.

F. Attachments: Include sketches, coordination drawings, descriptions, photos, submittals, and other information necessary to substantiate the reason for the request.

G. RFI Log: Prepare and maintain a tabular log of RFIs for the duration of the project.

1. Indicate current status of every RFI. Update log promptly and on a regular basis.

2. Note dates of when each request is made, and when a response is received.

3. Highlight items requiring priority or expedited response.

4. Highlight items for which a timely response has not been received to date.

H. Review Time: Architect will respond and return RFIs to Contractor within seven calendar days of receipt. For the purpose of establishing the start of the mandated response period, RFIs received after 12:00 noon will be considered as having been received on the following regular working day.

I. Responses: Content of answered RFIs will not constitute in any manner a directive or authorization to perform extra work or delay the project. If in Contractor's belief it is likely to lead to a change to Contract Sum or Contract Time, promptly issue a notice to this effect, and follow up with an appropriate Change Order request to Owner.

3.07 SUBMITTAL SCHEDULE

A. Submit to Architect for review a schedule for submittals in tabular format.

1. Coordinate with Contractor's construction schedule and schedule of values.

2. Format schedule to allow tracking of status of submittals throughout duration of construction.

3. Arrange information to include scheduled date for initial submittal, specification number and title, submittal category (for review or for information), description of item of work covered, and role and name of subcontractor.

4. Account for time required for preparation, review, manufacturing, fabrication and delivery when establishing submittal delivery and review deadline dates.

a. For assemblies, equipment, systems comprised of multiple components and/or requiring detailed coordination with other work, allow for additional time to make corrections or revisions to initial submittals, and time for their review.

3.08 SUBMITTALS FOR REVIEW

A. When the following are specified in individual sections, submit them for review:

1. Product data.

2. Shop drawings.

3. Samples for selection.

4. Samples for verification.

B. Submit to Architect for review for the limited purpose of checking for compliance with information given and the design concept expressed in Contract Documents.

C. Samples will be reviewed for aesthetic, color, or finish selection.

D. After review, provide copies and distribute in accordance with SUBMITTAL PROCEDURES article below and for record documents purposes described in Section 01 7800 - Closeout Submittals.

3.09 SUBMITTALS FOR INFORMATION

A. When the following are specified in individual sections, submit them for information:

1. Design data.

2. Certificates.

3. Test reports.

Veterans' Home, Lebanon 01 3000 - 6 Administrative Requirements

4. Inspection reports.

5. Manufacturer's instructions.

6. Manufacturer's field reports.

7. Other types indicated.

B. Submit for Architect's knowledge as contract administrator or for Owner.

3.10 SUBMITTALS FOR PROJECT CLOSEOUT

A. Submit Correction Punch List for Substantial Completion.

B. Submit Final Correction Punch List for Substantial Completion.

C. When the following are specified in individual sections, submit them at project closeout in compliance with requirements of Section 01 7800 - Closeout Submittals:

1. Project record documents.

2. Operation and maintenance data.

3. Warranties.

4. Bonds.

5. Other types as indicated.

D. Submit for Owner's benefit during and after project completion.

3.11 NUMBER OF COPIES OF SUBMITTALS

A. Electronic Documents: Submit one electronic copy in PDF format; an electronically-marked up file will be returned. Create PDFs at native size and right-side up; illegible files will be rejected.

B. Samples: Submit the number specified in individual specification sections; one of which will be retained by Architect.

1. After review, produce duplicates.

2. Retained samples will not be returned to Contractor unless specifically so stated.

3.12 SUBMITTAL PROCEDURES

A. General Requirements:

1. Use a single transmittal for related items.

2. Transmit using approved form.

a. Use Contractor's form, subject to prior approval by Architect.

3. Sequentially identify each item. For revised submittals use original number and a sequential numerical suffix.

4. Identify: Project; Contractor; subcontractor or supplier; pertinent drawing and detail number; and specification section number and article/paragraph, as appropriate on each copy.

5. Apply Contractor's stamp, signed or initialed certifying that review, approval, verification of products required, field dimensions, adjacent construction work, and coordination of information is in accordance with the requirements of the work and Contract Documents.

a. Submittals from sources other than the Contractor, or without Contractor's stamp will not be acknowledged, reviewed, or returned.

6. Deliver each submittal on date noted in submittal schedule, unless an earlier date has been agreed to by all affected parties, and is of the benefit to the project.

a. Send submittals in electronic format via email to Architect.

7. Schedule submittals to expedite the Project, and coordinate submission of related items.

a. For each submittal for review, allow 15 days excluding delivery time to and from the

Contractor.

b. For sequential reviews involving Architect's consultants, Owner, or another affected party, allow an additional 7 days.

8. Identify variations from Contract Documents and product or system limitations that may be detrimental to successful performance of the completed work.

9. When revised for resubmission, identify all changes made since previous submission.

10. Submittals not requested will be recognized, and will be returned "Not Reviewed", Veterans' Home, Lebanon 01 3000 - 7 Administrative Requirements

B. Product Data Procedures:

1. Submit only information required by individual specification sections.

2. Collect required information into a single submittal.

3. Submit concurrently with related shop drawing submittal.

4. Do not submit (Material) Safety Data Sheets for materials or products.

C. Shop Drawing Procedures:

1. Prepare accurate, drawn-to-scale, original shop drawing documentation by interpreting

Contract Documents and coordinating related work.

2. Do not reproduce Contract Documents to create shop drawings.

3. Generic, non-project-specific information submitted as shop drawings do not meet the requirements for shop drawings.

D. Samples Procedures:

1. Transmit related items together as single package.

2. Identify each item to allow review for applicability in relation to shop drawings showing installation locations.

3. Include with transmittal high-resolution image files of samples to facilitate electronic review and approval. Provide separate submittal page for each item image.

3.13 SUBMITTAL REVIEW

A. Submittals for Review: Architect will review each submittal, and approve, or take other appropriate action.

B. Submittals for Information: Architect will acknowledge receipt, but will take no other action.

C. Architect's actions will be reflected by marking each returned submittal using virtual stamp on electronic submittals.

1. Notations may be made directly on submitted items and/or listed on appended Submittal

Review cover sheet.

D. Architect's and consultants' actions on items submitted for review:

1. Authorizing purchasing, fabrication, delivery, and installation:

a. "No Exceptions Taken", or language with same legal meaning.

b. "Exceptions Noted: No Re-Submittal Required", or language with same legal meaning.

1) At Contractor's option, submit corrected item, with review notations acknowledged and incorporated.

c. "Exceptions Noted: Revise and Re-Submit Specific Item(s) Noted", or language with same legal meaning.

1) Resubmit corrected item, with review notations acknowledged and incorporated.

Resubmit separately, or as part of project record documents.

2. Not Authorizing fabrication, delivery, and installation:

a. "Revise and Resubmit".

1) Resubmit revised item, with review notations acknowledged and incorporated.

2) Non-responsive resubmittals may be rejected.

b. "Rejected".

1) Submit item complying with requirements of Contract Documents.

E. Architect's and consultants' actions on items submitted for information:

1. Items for which no action was taken:

a. "Received" - to notify the Contractor that the submittal has been received for record only.

2. Items for which action was taken:

a. "Reviewed" - no further action is required from Contractor.

Veterans' Home, Lebanon 01 3000 - 8 Administrative Requirements

01 3216

Veterans' Home, Lebanon 01 3216 - 1 Construction Progress Schedule

SECTION 01 3216

CONSTRUCTION PROGRESS SCHEDULE

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Preliminary schedule.

B. Construction progress schedule, bar chart type.

1.02 SUBMITTALS

A. Within 10 days after date established in Notice to Proceed, submit preliminary schedule.

B. If preliminary schedule requires revision after review, submit revised schedule within 10 days.

C. Within 10 days after joint review, submit complete schedule.

D. Submit updated schedule with each Application for Payment.

E. Submit in PDF format.

1.03 SCHEDULE FORMAT

A. Listings: In chronological order according to the start date for each activity. Identify each activity with the applicable specification section number.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION

3.01 PRELIMINARY SCHEDULE

A. Prepare preliminary schedule in the form of a horizontal bar chart.

3.02 CONTENT

A. Show complete sequence of construction by activity, with dates for beginning and completion of each element of construction.

B. Identify each item by specification section number.

C. Identify work of separate stages and other logically grouped activities.

D. Provide sub-schedules to define critical portions of the entire schedule.

E. Include conferences and meetings in schedule.

F. Show accumulated percentage of completion of each item, and total percentage of Work completed, as of the first day of each month.

G. Provide separate schedule of submittal dates for shop drawings, product data, and samples, owner-furnished products, products identified under Allowances, and dates reviewed submittals will be required from Architect. Indicate decision dates for selection of finishes.

H. Indicate delivery dates for owner-furnished products.

I. Provide legend for symbols and abbreviations used.

3.03 BAR CHARTS

A. Include a separate bar for each major portion of Work or operation.

B. Identify the first work day of each week.

3.04 REVIEW AND EVALUATION OF SCHEDULE

A. Participate in joint review and evaluation of schedule with Architect at each submittal.

B. Evaluate project status to determine work behind schedule and work ahead of schedule.

C.