Scope of Work Summary – Fargo VA Healthcare System Project 437-24-101

This is a Scope of Work document for a federal construction contract to replace Underground Storage Tanks (USTs) and Aboveground Storage Tanks (ASTs) at the Fargo VA Healthcare System. The contractor shall furnish all labor, materials, and equipment to replace USTs #1, #2, #3, #4, #8 and ASTs #4, #5, along with interconnected below-grade piping systems (#1–#4, #8–#10). The work includes designing flexible spill containment liners, tertiary containment barriers, encasement barriers, waterproof manway covers, and Auto Tank Gauges with integrated monitoring and reporting. Additional scope encompasses environmental assessments, soil boring tests, and geotechnical drilling at four VA site locations. The project must comply with the Physical Security and Resiliency Design Manual (PSRDM), October 1, 2020 (Revised 05-01-2024), all applicable federal, state, and local codes, and NFPA requirements for critical facilities. The contractor must design a cathodic protection system, semi-automatic pump clarification systems, establish control points for future construction, and develop a phasing plan ensuring zero downtime for backup generators with temporary power solutions.

Work shall be performed between 6 AM–6 PM whenever possible to minimize disruption to hospital services, with all fuel and boiler shutdowns requiring three-week advance notification and approval. The project timeline is approximately 18 months (540 days; 525 days after Notice to Proceed) from pre-construction planning through environmental review, construction, remediation, and final reporting. Key milestone dates include Pre-construction Conference (D+10), Notice to Proceed (D+15), Submittals Due (D+45), Construction Start (D+60), and Construction Completion (D+540). Contractor shall submit daily logs to the Contracting Officer's Representative for progress tracking and provide comprehensive submittals including product data, samples, as-built drawings, certification reports, soil boring testing reports, warranties, and operation and maintenance manuals. Lock Out Tag Out (LOTO) procedures are required for all utility testing, and some work may require confined/enclosed space training. The contract shall not close until after the station's go-live date, with any additional equipment or needs identified during coordination subject to contract modification.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project # 437-24-101 Fargo VA Healthcare System

Scope of Work

Project Number: 437-24-101 Project Title: Replace UST and Leak Detection

A. General Intention

The Contractor shall furnish all labor, materials, and equipment to replace existing UST’s (Underground Storage Tank) #1, #2, #3, #4, #8, existing AST’s (Aboveground Storage Tank) #4, and #5, along with existing #1, #2, #3, #4, #8, #9 and #10 UST interconnected below-grade piping systems on the Fargo VA campus including designing flexible spill containment liners, tertiary containment barriers, encasement barriers, waterproof manway covers, and Auto Tank Gauges (ATG) with integrated monitoring and reporting. Environmental assessments, soil boring tests and geotechnical drilling at four VA site locations required, along with compliance with physical security and resiliency standards for intrusion and blast protection. A phasing plan to ensure zero downtime for existing backup generators with temporary power solutions shall be proposed & followed. Additional work includes cathodic protection system design, semi-automatic pump clarification systems, and establish control points for future construction.

B. Statement of Work

Description of Work: Work shall include, but shall not be limited to, providing all labor, materials, equipment, etc. necessary to complete Fargo VA Health Care System project 437-24-101, Replace UST’s & Leak Detection in accordance with this Scope of Work. The UST’s support Critical Facilities and will follow requirements for Critical facilities in accordance with the Physical Security and Resiliency Design Manual (PSRDM), October 1, 2020, Revised 05-01-2024, the contract documents, all applicable federal, state and local codes as well as the NFPA requirements.

The construction work schedule shall account for and ensure that the VA is Minimally impacted in terms of services provided to our customers, as well as any coordination with other contractors on site.

Work hours between 6 AM – 6 PM shall be preferred and required whenever possible to minimize disruptions to hospital services with Holidays as needed.

All fuel & boiler shutdowns shall have 3-week notification and approval prior to date of shutdown to allow for notification of affected staff. Preprint Total project timeline is estimated at approximately 18 months, encompassing pre-construction planning, environmental review, construction & remediation, and final reporting. Adjustments may be made based on site conditions, weather, permitting processes, and coordination with concurrent VA projects.

Lock Out Tag Out (LOTO) procedures shall be required for all utility testing, and some tests may require confined/enclosed space work conditions and training.

C. Civil

Refer to Cost-Free Design Analysis – Pages 4-5

D. Physical Security and Resiliency Refer to Cost-Free Design Analysis – Pages 5-10

E. Mechanical

Refer to Cost-Free Design Analysis – Pages 10-12

F. Electrical Refer to Cost-Free Design Analysis – Pages 12-13

G. Environmental/Geo Tech Refer to Cost-Free Design Analysis – Pages -13-15

H. Deviations from SOW

Refer to Cost-Free Design Analys – Pages 15-16

**See attachment G- Cost-Free Design Analysis for information on above.

I. Period of Performance

Coordinate work times with the COR. Submit daily logs to COR for progress tracking, see attachment for sample daily log reporting.

Below represents an approximate schedule for the Period of Performance.

Duration of Work: 540 days; 525 days after NTP.

J. Specifications

Item Day Contract Award D Pre-construction Conference D+10 Notice to Proceed D+15 Badging/Background Check Start D+30 Submittals Due D+45 Long-Lead Items Ordered D+57 Badging/Background Check Completion D+57 Mobilization D+57 Construction Start D+60 Construction Completion D+540

Division 00 – Special Sections 00 01 15 – List of Drawing Sheets Division 01 – General Requirements 01 00 00 – General Requirements 01 33 23 – Shop Drawings, Product Data, and Samples 01 35 26 – Safety Requirements for Major Projects 01 45 29 – Testing Laboratory Services 01 57 19 – Temporary Environmental Controls 01 74 19 – Construction Waste Management 01 81 13 – Sustainable Construction Requirements 01 91 00 – General Commissioning Requirements Division 02 – Existing Conditions 02 41 00 – Demolition 02 65 00 – Underground Storage Tank Removal Division 03 – Concrete 03 30 00 – Cast-in-Place Concrete Division 07 – Thermal and Moisture Protection 07 84 00 – Firestopping 07 92 00 – Joint Sealants Division 23 – Heating, Ventilating, and Air Conditioning (HVAC) 23 05 10 – Common Work Results for Boiler Plant and Steam Generation 23 08 00 – Commissioning of HVAC Systems 23 10 00 – Facility Fuel Systems Division 26 – Electrical 26 05 11 – Requirements for Electrical Installations 26 05 19 – Low-Voltage Electrical Power Conductors and Cables 26 05 26 – Grounding and Bonding for Electrical Systems 26 05 33 – Raceway and Boxes for Electrical Systems 26 05 41 – Underground Electrical Construction 26 08 00 – Commissioning of Electrical Systems

26 27 26 – Wiring Devices 26 42 00 – Cathodic Protection

Division 27 – Communications 27 05 11 – Requirements for Electrical Installations 27 05 26 – Grounding and Bonding for Electrical Systems 27 05 33 – Raceway and Boxes for Electrical Systems 27 08 00 – Commissioning of Communications Systems 27 10 00 – Control, Communication and Signal Wiring

Division 31 – Earthwork 31 20 00 – Earthwork Division 32 – Exterior Improvements 32 05 23 – Cement and Concrete for Exterior Improvements 32 12 16 – Asphalt Paving 32 17 23 – Pavement Markings

K. Drawings

437-24-101 Preliminary Drawings G-0.00 Cover Page G-0.02 Location Map and Contractor Staging Plan G-1.00 PCRA Plan G-2.00 UST 1, 2 & 3 Contamination Area Plan & Profile C-1.0 Existing Condition / Utility Plan C-2.0 Erosion control / Utility Plan C-3.0 Grading Plan C-4.0 Paving Plan C-5.0 Details S-1.00 Retaining Wall and Sidewalk Plans M-0.00 Mechanical Cover Sheet M-0.10 Site Plan M-0.20 Mechanical Schedules & Details M-0.30 Mechanical Details MD-1.00 Underground Storage Tanks 1, 2 &3 Demolition Plan MD-1.01 Underground Storage Tank 4 Demolition Plan MD-1.02 Underground Storage Tank 8 & AST 3 Demolition Plan MD-1.03 Aboveground Storage Tanks 4 & 5 Demolition Plan M-1.00 Underground Storage Tanks 1, 2 & 3 New Plan M-1.01 Underground Storage Tank 4 New Plan M-1.02 Underground Storage Tank 8 & AST 3 New Plan M-1.03 Aboveground Storage Tanks 4 & 5 New Plan E-0.0 Electrical Legends and Abbreviations E-0.1 Electrical Schedules and Details E-1.0 Electrical Floor Plans E-1.1 UST 6 and 8 Electrical Floor Plan Details E-1.2 UST 9 and 10 Electrical Floor Plan Details E-1.3 Boiler Plant Electrical Floor Plan Details E-1.4 Cathodic Protection

L. Submittals

a. Daily Logs

b. Submittals for all associated Scope of work

i. Product Data

ii. Product Samples (e.g. cables, fuses, breakers)

iii. As-built drawings (e.g. one-line diagrams, locations, and labels for equipment)

iv. Certification Report(s)

v. Testing Reports (including deficiencies) – Soil Borings

vi. Progress Documentation (see example below)

vii. Warranties of installation and equipment

viii. Operation and Maintenance Manuals

M. Project Completion

The contract shall not be closed by the Contracting Officer until after the station’s go-live date if additional equipment or needs are identified through coordination with the COR.

If additional equipment or needs are identified, a modification shall be negotiated for the additional work.

The above paragraphs constitute a basic outline of the work to be accomplished and in no way comprises all the details for this project. Contractor shall refer to drawings and specifications for comprehensive construction requirements.

End of SOW

A. General Intention
B. Statement of Work
C. Civil
D. Physical Security and Resiliency
E. Mechanical
F. Electrical
G. Environmental/Geo Tech
H. Deviations from SOW
I. Period of Performance
J. Specifications
K. Drawings
L. Submittals
M. Project Completion