This is a Scope of Work document for a federal construction project at the St. Cloud VA Health Care System. The project, identified as #656-12-223, requires the contractor to replace windows in Buildings 3 and Corridors, including complete removal and replacement of existing steel windows, removal of lead and asbestos-containing materials in compliance with local and national regulations, installation of new window frames and sashes, screens and storm windows, and restoration of walls, ceilings, trim, and millwork. The contractor must also handle all debris removal and restoration of the worksite to VA standards upon completion. The work will be performed in an occupied building behind proper construction barriers.
The anticipated cost range for this project is between $2,000,000 and $5,000,000. The project schedule begins with contract award (D), followed by a pre-construction conference (D+15), Notice to Proceed (D+30), badge process and construction start (D+60), and substantial completion within 445 calendar days after NTP, with final construction completion by D+475. Contract working hours are 8 a.m. to 4:30 p.m. Monday through Friday, excluding Federal Holidays, though weekend and night work in sensitive areas may be approved by the Contracting Officer's Representative. The anticipated contractor trades include general contractor, general laborer, demolition contractor, abatement contractor, and painting contractor, with no VA-furnished equipment provided.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCOPE OF WORK
“REPLACE WINDOWS BUILDINGS 3 AND CORRIDORS”
PROJECT #656-12-223
ST CLOUD VA HEALTH CARE SYSTEM
A. PART I – GENERAL
1. Base Project: The Contractor shall furnish all labor, materials, tools and equipment required to repair, remove, replace and completely refurbish all windows in Buildings 3 and Corridors. The contractor shall remove the existing internal and external window trim and wall finishes in order to successfully gain access to and cut out the existing steel windows. Incorporated into the demolition of the windows will be the safe removal of both lead and asbestos containing material as guided by the local and national rules and regulations of lead and asbestos remediation. Additionally, the contractor will be responsible for the complete and satisfactory installation of the new window frames and sashes, screens and storm windows. The window installation shall include the patching and painting of walls, ceiling installation and restoration, trim and millwork installation, and repair of all damaged items in place. This work will be completed in an occupied building; all construction activities shall be completed behind proper construction barriers as described in the specifications. The contractor shall return the worksite to the Veterans Affairs Health Care System after the work is completed, and all of the required work is satisfactorily completed and signed off by the assigned
Contracting Officer’s Representative. Refer to the contract specifications and drawings for details All work completed in accordance with the specifications and contract drawings.
2. Deducts:
a. None
3. Work includes, but is not limited to:
a. Demolition:
b. Contractor shall remove from the VA site and dispose of all equipment and materials not scheduled to be reused.
c. Contractor shall remove Lead and Asbestos materials associated with windows
d. Contractor trades anticipated:
• General contractor
• General laborer
• Demolition contractor
• Abatement contractor
• Painting contractor
1. No VA furnished equipment
2. New construction consists of but is not limited to windows, doors, general construction and abatement.
3. Contractor is responsible for the movement, adjustment and storage of all furnishings disturbed during construction.
4. Contract working hours are 8 am to 4:30 pm Monday through Friday, excluding Federal
Holidays. Weekend and night work may be necessary in sensitive areas and shall be approved by the COR.
5. Phasing will be as listed on the contract documents
B. Anticipated Schedule:
Contract award* D
Pre-construction conference D+15
Notice to Proceed D+30
Badge Process D+60
Construction starts D+60
Construction completion D+475
The anticipated substantial completion of this project is 445 calendar days after “Notice to
Proceed” (NTP).
C. Cost Range The anticipated cost range for this project is between $2,000,000 and $5,000,000.
- - - E N D - - -