Y1DZ--437-24-101, Replace UST's & Leak Detection System Federal contract opportunity
Solicitation number
36C26326B0016_0001
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 23

About this file

This is a Questions and Answers document for federal contract 437-24-101 CON, which addresses the replacement of underground storage tanks (USTs) and leak detection systems at a VA Medical Center facility.

The document clarifies critical project requirements and constraints. Contractors must submit a detailed phasing plan with manpower levels and verifiable milestones prior to commencing work, maintaining one fuel oil tank operational at all times and keeping traffic access open. The work is not restricted to warm weather only; contractors may adjust sequencing or shift resources during unfavorable conditions. The Period of Performance accounts for badging and tank lead times, with additional time available only through contracting officer discretion via contract modification. The Superintendent, Site Safety and Health Officer (SSHO), and Quality Control Manager must be separate, independent personnel with no supervisory relationships between them, and Quality Control must report to a different company executive than the Superintendent. One tank down at a time is the preferred phasing approach. All service interruptions must be scheduled and coordinated with the Contracting Officer's Representative (COR), with major system interruptions requiring written request at least 21 calendar days in advance. UST #8 and AST #3 are descoped and addressed under a separate project. The VA will consider alternative UST products such as Plasteel/Elutron if they meet specification requirements or equivalents. A critical correction note indicates sealed offers are due March 31, 2026 at 2:00 p.m., not March 10, 2026 as originally stated.

View the file

Other files for this federal contract opportunity

Other files attached to Y1DZ--437-24-101, Replace UST's & Leak Detection System, newest first.
File Type Posted
36C26326B0016 0001.pdf PDF
Attach B-Sign in sheet for the UST Project.pdf PDF
Attach C- Site Visit Agenda UST leak 1.pdf PDF
Attach D Solicitation sf 1442 fixed Box 13.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

437-24-101 CON Replace UST and Leak Detection questions and answers

1. Are there any project phasing requirements? As in, certain tank batches need to be done first, 2nd, 3rd?

- Phasing of Work: Comply with all requirements shown on contract documents.

Contractor shall submit a complete detailed phasing plan/schedule with manpower levels prior to commencing work. The phasing plan shall be detailed enough to provide milestones in the process that can be verified.

- Backup fuel source to be provided while working on tanks and leave traffic access open all time. These two issues are important phasing requirements to be considered.

2. Is this work considered “warm weather seasonal” only time frame for the earthwork portion of scope?

- Coordinate with the VA to adjust work sequencing or shift labor/resources to unaffected tasks. You can resume fieldwork once safety and environmental conditions are acceptable.

3. Does the Period of Performance account for badging & tank lead times? If not, can some additional time be included?

- Yes, it accounts for both badging and lead times. Additional time may only be added at the discretion of the contracting officer’s determination of reasonable request via a contract modification.

4. Can the Superintendent carry any other roles such as QC or SSHO?

- No; Superintendent, Site Safety & Health Officer (SSHO), and Quality Control functions may not be stacked in any configuration and must be independent positions with independent roles filled by individual personnel. Quality Control shall report to a different executive within the company than the Superintendent to maintain independence and neutrality. SSHO and Superintendent shall not be subordinate to each other (superintendent does not supervise SSHO, and vice-versa).

5. Can the QC also act as the SSHO? And/or vice versa

- The SSHO has to be a separate qualified individual from the Prime Contractor’s Superintendent and/or Quality Control Manager with duties only as the SSHO.

6. Will phasing 1 tank down at a time by the Boiler Plant an similar areas be preferred by the VA user to allow for semi-normal tank functions during construction?

- Yes, 1 tank down at a time is preferred. Per specs. Section 23 05 10 part 1.8.B;

“At all times, there shall be one fuel oil tank available to serve the boiler plant or generator available for serving the load demand. The fuel oil tank shall be capable of handling the loads that may be imposed for normal operations”.

7. Will the shutdowns and transfers/switch overs be allowable during normal business hours?

- The Medical Center must maintain its operation 24 hours a day 7 days a week.

Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks.

- Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.

- Major interruptions of any system must be requested, in writing, at least 21 calendar days prior to the desired time and shall be performed as directed by the

COR.

8. With there being a separate project addressing the UST by the North Loading Dock- Generator Room area, will this work under this UST project be modified and/or descoped in anyway?

- UST #8 and AST #3 are descoped from this project. They are addressed in another project.

9. Can the VA clarify who is to hold the CxA contract?

- The VA has engaged the CxA under a separate contract under the A/E.

10. Would the VA consider Plasteel/Elutron UST as they are becoming the more standard/typical installation product compared the currently speced product?

- Yes, we will consider if it meets the requirements in the specs or equivalent.

**Original 1442 has sealed offers due at 2:00pm March 10, 2026. This is INCORRECT. The sealed offers are due March 31, 2026 at 2:00pm.