This document is a Section 01 56 00 specification for Environmental Requirements at Dobbins Air Reserve Base (DARB), dated 9 July 2025. The specification provides comprehensive environmental management guidelines for contractors working on the base, covering multiple areas of environmental compliance and waste management.

Key requirements include: managing solid waste with a minimum 50% recycling mandate for construction and demolition debris, strict hazardous materials handling protocols, universal waste management procedures, storm water pollution prevention, and specific guidelines for handling materials like batteries, fluorescent lamps, PCB ballasts, and mercury-containing devices. Contractors must obtain necessary environmental permits, submit detailed documentation, follow specific storage and disposal protocols, and comply with federal, state, and local environmental regulations. The document outlines precise tracking, labeling, and reporting requirements for various types of waste, emphasizing environmental protection, spill prevention, and proper waste disposal practices at Dobbins Air Reserve Base.

View the file

Other files for this federal contract opportunity

Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

9 July 2025

SECTION 01 56 00

DOBBINS ARB ENVIRONMENTAL REQUIREMENTS

05/25

PART 1 GENERAL

This Section describes the requirements placed upon the Contractor necessary for the prevention of environmental pollution generation, release, or damage on Dobbins Air Reserve Base (DARB), and to enable DARB to meet environmental compliance, reporting and tracking requirements set forth in local, State, and Federal laws, rules, and guidance documents due to work performed by the Contractor during the execution of this project.

1.1 COMPLIANCE WITH ENVIRONMENTAL REGULATIONS

The Contractor and his subcontractors shall comply with all applicable Federal, State, and local laws and regulations concerning environmental permitting, tracking, pollution control and protection, as well as the specific requirements stated elsewhere in the contract specifications.

1.2 SUBMITTALS

Submittal requirement details for each project are listed in an accompanying AF Form 66 identified for this specification section 01560, as well as in each respective subsection. The following submittals are always required:

1.2.1 Disposal Facility Information, reference section 3.2.2.1

1.2.2 Disposal/Recyclable Weight Receipts, reference section 3.2.2.2

1.2.3 Hazardous Material Safety Data Sheets and Material Information Sheet, reference section 3.3.2

1.3 ENVIRONMENTAL PERMITS AND CERTIFICATIONS

The Contractor is responsible for obtaining and holding current all applicable environmental permits and certifications necessary to accomplish all work. Requirements for specific permits and certifications are included in subsequent subsections when applicable.

1.4 ENVIRONMENTAL FINES AND PENALTIES

The Contractor agrees to indemnify the Government, its officers, agents, and employees against liability and costs associated with the intentional or negligent noncompliance of environmental laws, regulations, or requirements by the Contractor, its officers, agents, employees, or subcontractors to the extent such noncompliance arises out of the manufacture or delivery of supplies, services or construction by or for the account of the Government. The Contractor shall reimburse the Government for any fines and monetary penalties assessed by State or Government agencies against Dobbins Air Reserve Base due to intentional or negligent noncompliance with environmental laws, regulations, or requirements by the Contractor. The Contractor shall be responsible for making corrections necessary to comply with any environmental laws, regulations or requirements.

SECTION 01 56 00 Page 1

Attachment 5 FA670325B0005

1.5 REGULATORY INSPECTIONS

The Contractor shall immediately notify the Contracting Officer when contacted by a Federal, state or local environmental regulatory inspector(s). The Contractor cannot represent the Government during an inspection. The Contracting Officer, or designated government representative, will be responsible for meeting and escorting the inspector(s) at the job site.

1.6 DEFINITIONS

1.6.1 Hazardous Material (Hazmat): Any substance defined by OSHA as a hazardous substance requiring a Safety Data Sheet (SDS), including, but not limited to: chemicals, curing agents, joint sealers, ready-mix concrete, grout, paints, adhesives, sealing compounds, strippers, glues, petroleum products, natural or synthetic gases, pesticides, all aerosols, and all materials containing hazardous substances.

1.6.2 Solid Waste: Any material, liquid, gaseous or solid, that is deemed as waste by the generator because it is no longer needed, is excess, has exceeded its shelf life, is spill residue, has been abandoned, or is no longer usable for its intended purpose. Solid waste includes, but is not limited to: used or spilled chemicals; contaminated clothing and personal protective equipment (e.g. mask filters, gloves, coveralls);

contaminated wipes, rags and other equipment; empty containers; garbage;

packaging; construction and demolition debris; refuse; recyclable materials; and all other discarded materials that are generated during construction, residential, and commercial activities.

1.6.3 Hazardous Waste: Any solid waste that meets the Title 40 Code of Federal Regulations (CFR) Part 261 criteria for characterization as hazardous waste or is a listed waste (reference 40 CFR 261). Solid waste which is expected to exhibit any hazardous waste characteristics, or is a listed hazardous waste, based upon the information provided on the Safety Data Sheets (SDS) by the contractor per Section 3.2 of this specification for the original materials, is hazardous waste. Flashpoint, corrosivity, and constituents on the SDS are reviewed by the government to determine potential for solid wastes to be hazardous wastes.

1.6.4 Universal Waste: Any hazardous waste that is subject to the universal waste requirements found in Title 40 Code of Federal Regulations (CFR) Part 273, to include: batteries, pesticides, mercury-containing equipment, lamps and aerosol cans.

1.6.5 Empty containers of hazmat which meet the 40 CFR regulatory definition of "empty" are to be considered empty (reference 40 CFR 261.7(b)) and are allowed to be disposed of in a construction debris collection container as non-hazardous solid waste.

PART 2 PRODUCTS

Not Applicable

PART 3 EXECUTION

3.1 GENERAL ENVIRONMENTAL REQUIREMENTS

3.1.1 Prohibition against Open Burning. The Contractor is prohibited

SECTION 01 56 00 Page 2 from open burning on Dobbins Air Reserve Base.

3.1.2 Historical and Archeological Findings. If the Contractor believes he/ she has discovered any item or area of historical or archaeological interest not specified in the contract during the completing of work, the Contractor shall leave the area undisturbed and immediately report the finding to the Contracting Officer.

3.1.3 Diversion of Construction and Demolition debris from Landfill. At least 50% of all construction and demolition debris (C&D) shall be recycled either onsite (within the project) or at an appropriate off base recycling facility. Recyclable C&D debris is prohibited from being landfilled. Recyclable C&D includes , but is not limited to: asphalt, concrete, scrap metal, metal piping, metal fixtures, lumber, ceiling tiles, gypsum, carpeting, fluorescent lamps, batteries, cardboard, paper, and fiberboard. Additional requirements for C&D are detailed in Sections

3.2 and 3.10 of this specification.

3.1.4 Erosion and Sediment Control. Best management practices, including sound conservation and engineering practices must be implemented by the Contractor to prevent and minimize erosion and resultant sedimentation, and must be consistent with practices contained in the Manual for Erosion and Sediment Control in Georgia, published by the State Soil and Water Conservation Commission. Any project that disturbs the soil shall require protection of the surrounding land against sediment runoff.

Requirements for this protection are detailed in Section 3.4 of this specification. All excavated soils shall be disposed of at an off-base state permitted landfill if not needed for reuse within this same project. Disposal on base is prohibited, unless otherwise provided in writing by the Contracting Officer.

3.1.5 Unanticipated Materials of Concern

3.1.5.1 Asbestos Containing Material (ACM): If the Contractor discovers ACM not specified in the contract during the execution of work, the Contractor shall stop work on the site immediately and notify the Contracting Officer. The Contractor shall not install or use any ACM on Dobbins ARB.

3.1.5.2 Lead-Based Paint (LBP): If the Contractor discovers LBP not specified in the contract during the execution of work, the Contractor shall stop work on the site immediately and notify the Contracting Officer. The Contractor shall not install or use lead-based paint for any work on Dobbins ARB.

3.1.5.3 Polychlorinated Biphenyls (PCBs): If the Contractor discovers a PCB containing item not specified in the contract during the execution of work, the Contractor shall stop work on the site immediately and notify the Contracting Officer. The Contractor shall not use nor install any equipment containing PCBs on Dobbins ARB.

3.2 SOLID WASTE MANAGEMENT

The Contractor is authorized to generate or dispose of solid waste under the scope of this contract in accordance with the requirements of this Section. Solid waste refers to any municipal waste, construction and demolition debris, non-hazardous debris, regulated wastes, and recyclable materials generated by the Contractor while performing the work under this contract. Excess clean soil free of solid waste, and routine personal

SECTION 01 56 00 Page 3 waste (food and drink containers that are carried off-base at the end of the work day), are excluded from this definition in this Section.

3.2.1 References

3.2.1.1 Georgia Department of Natural Resources Environmental Protection Division, Chapter 391-3-4, Solid Waste Management

3.2.2 Submittals

3.2.2.1 Landfill and Recycling Facility Information. The Contractor shall only use state-permitted solid waste landfills and recycling facilities for all solid waste generated on Dobbins ARB. The Contractor shall submit a document which lists the name(s), address (es), phone number(s) and point(s) of contact for each landfill or recycling facility intended to be used for the disposal and/or recycling of solid wastes generated by the Contractor during the course of this contract. This document must be approved by the Contracting Officer prior to beginning any work resulting in the generation of any solid waste or recyclables.

3.2.2.2 Weight Receipts for solid waste disposed and materials recycled. Weight receipts are landfill receipts or recycling receipts provided to the Contractor by the recycling and/or disposal facility which indicate: the date of service (drop off); the type of the waste dropped off, and the weight of the waste (in pounds or tons). Clearly legible Weight Receipts shall be submitted for approval within 5 days of the service date.

3.2.2.3 Disposal Weight Summary. The Contractor shall submit a document which summarizes the disposition of waste generated during the course of the whole project. This document shall include: the total weight of C&D generated, the total weight of other solid waste generated, the total weight of solid waste taken to a landfill, the total weight of C&D taken to a landfill, and the total weight of recyclable C&D taken to a recycling facility. All costs associated with the disposal of C&D, disposal of solid waste, and recycling shall be included in the monthly summary and broken down by each waste type.

3.2.3 Construction And Demolition Debris

3.2.3.1 All recyclable construction and demolition debris (C&D) shall be collected and transported off base to a C&D recycling facility.

Recyclable C&D debris is prohibited from being landfilled. Recyclable C&D includes, but is not limited to: asphalt, concrete, scrap metal, metal piping, metal fixtures, lumber, ceiling tiles, gypsum, carpeting, cardboard, paper and fiberboard. The Contractor shall ensure that a minimum of 50% of the total recyclable C&D generates from work on this project is diverted to recycling or reuse. The Contractor shall document this diversion by submitting the Disposal Weight Summary at 3.2.2.3 above.

3.2.3.2 The Contractor shall segregate recyclable C&D from

non-recyclable C&D, in accordance with the recycling facility requirements. Small quantities of some scrap metals may be recycled at the base Recycling Center, Building 560, upon Contractor request and approval from the Contracting Officer. Non-recyclable C&D shall be disposed of at a state permitted landfill that is permitted for, and is currently accepting, C&D waste.

3.2.3.3 The Contractor shall collect all cardboard, fiberboard and

SECTION 01 56 00 Page 4 standard wooden pallets generated by any Contractor shipping and packaging activities (e.g. receipt of furniture, receipt of shipments of hazmats, etc.) in order to recycle them, per Section 3.2.3.1 above.

3.2.3.4 Any materials approved by the Contracting Officer to be recycled at the base Recycling Center which are taken to this facility do not require weight receipts to be submitted (ref. submittal 3.2.2.2).

3.2.4 Collection And Storage Of Recyclable C&D and Solid Wastes

3.2.4.1 The Contractor shall provide all appropriate containers, bags, liners, trays, roll offs and other equipment required for the proper collection of solid wastes and recyclable C&D. The Contractor shall not use any base dumpsters or other base trash receptacles for collecting or storing solid waste.

3.2.4.2 All solid wastes shall be reclaimed, recycled or disposed of prior to completion of work under this project.

3.2.4.3 The Contractor shall not generate any waste as a result of cleaning Contractor tools, vehicles, containers or other equipment on base. Cleaning of Contractor tools, vehicles, containers or other equipment on base is prohibited.

3.2.5 Excavated Soils. Any excavated soils shall be disposed of at an off base state permitted landfill, unless the Contractor is specifically instructed to reuse the soils within the project in accordance with the project specifications, or otherwise authorized by the Contracting Officer.

3.3 HAZARDOUS MATERIALS (Hazmat) MANAGEMENT

The Contractor is authorized to use hazardous materials under the scope of this contract in accordance with this section. Hazardous Material (Hazmat) is any hazardous substance required by the Occupation Safety and Health Administration (OSHA) to have a manufacturer's Safety Data Sheet (SDS), not including OSHA "articles" such as tape, fabric, batteries, mesh, mechanical fasteners, etc.

3.3.1 References

3.3.1.1 Air Force Manual 32-7002, Environmental Compliance and Pollution Prevention, , Chapter 3, Hazardous Materials Management, 4 Feb 2020

3.3.1.2 Base Instruction 94 AWI 32-7086, 9February 2022

3.3.2 Submittals

3.3.2.1 Contractor's Hazmat Storage Location Sketch

3.3.2.2 Safety Data Sheets (SDSs)

3.3.2.3 Material Information Sheet (MIS)

3.3.2.4 Substantiating Documentation for Use of Prohibited Hazmat

3.3.2.5 Product Data Sheets (PDSs)

3.3.3 EPCRA Compliance. Reference FAR 52.223-5: The Contractor needs to provide all information needed by Dobbins ARB to comply with EPCRA.

SECTION 01 56 00 Page 5

Contractor shall provide the following submittals for government approval:

3.3.3.1 Contractor's Hazmat Storage Location Sketch (ref. submittal 3.3.2.1), a document which identifies exactly where Hazmats are intended to be stored on base when not in use, if overnight storage is required;

3.3.3.2 Safety Data Sheet (SDS) (ref. submittal 3.3.2.2), a

manufacturer's material document which describes the physical and chemical characteristics of a hazmat, to be submitted by the Contractor for each and every different Hazmat listed on the MIS, submitted concurrently with the MIS. SDSs shall be obtained directly from the manufacturer, shall be current, and shall be in compliance with the OSHA and DOT global harmonization standards.

3.3.3.3 Material Information Sheet (MIS) (ref. submittal 3.3.2.3), the document completed and submitted by the Contractor (see Atch 1) which lists individual specific Hazmat intended to be used by the Contractor under the scope of the project, detailing data needed, including:

container type, container size, estimated quantity to be used, and application method. The MIS shall be accompanied by the current SDS for each listed Hazmat intended to be used. The MIS shall be deemed "incomplete" if submitted without all the required SDSs.

3.3.3.4 Substantiating Documentation (ref. submittal 3.3.2.4).

Substantiating documentation shall be submitted by the Contractor concurrently with the MIS and SDSs if a prohibited Hazmat or chemical constituent is requested for use by the Contractor. Documents must identify which specific engineering criteria or specification will not be met unless the prohibited Hazmat or chemical constituent is used, and shall contain the statement that alternate commercially available products are not available which will meet the specific engineering criteria or specification. Prohibited Hazmats or chemical constituents will not be authorized for use by the government without substantiating documentation. Prohibited hazmats and chemical constituents prohibited from use on Dobbins include, but are not limited to: all EPA-17 listed chemicals (see Atch 2); all Class I Ozone Depleting Substances (see Atch

2) ; heavy metals (see Atch 2); carcinogenic constituents; cyanide and cyanide compounds; phosphate compounds; SARA Title III Extremely Hazardous Substances (see Atch 2) ; and any hazardous material that has physical characteristics meeting hazardous waste thresholds (i.e. has a flashpoint less than 140 degrees Fahrenheit; has a pH of 2 or less or of 12.5 or greater; is reactive; or is a listed toxic chemical).

3.3.3.4.1 No substantiated prohibited hazmat or chemical constituent will be approved for use in excess of 3000 pounds cumulatively over the entire contract period.

3.3.3.4.2 No substantiated prohibited hazmat or chemical constituent will be approved for use that will generate hazardous waste by nature of its use, unless the Contractor is authorized to generate hazardous waste in accordance with paragraph 3.7 of this section 01560.

3.3.3.4.3 No Class I Ozone Depleting Substance will be authorized for purchase or reimbursement under any circumstances. All Class I Ozone Depleting Substances identified as necessary by engineering to meet an engineering criteria or specification shall only be obtained through the Defense Reserve with SAF authorization and approval.

3.3.3.4.4 No hazmat containing lead (e.g. lead solder, lead flux, lead

SECTION 01 56 00 Page 6 wool, leaded paint, etc.) will be authorized for use under any circumstances. No substantiation is acceptable.

3.3.3.5 Product Data Sheet (PDS) (ref. submittal 3.3.2.5), a document provided by the manufacturer of a hazmat that provides detailed usage information about the hazmat including usage conditions and proper application methods. The Contractor shall submit a PDS for each Hazmat listed on the MIS concurrently with the MIS.

3.3.4 Limited overnight storage of any single Hazmat on base (less than 5,000 pounds) will be authorized in accordance with any storage conditions provided by the Government during hazmat approval review.

3.3.5 Use of approved and authorized Hazmats are restricted to the methods of application and quantities identified on the corresponding MIS;

if quantities needed exceed the estimates provided on the MIS, the Contractor must identify the additional quantity needed to the project inspector as soon as the need is identified. Additional quantities are authorized as long as no cumulative quantity limitations (reference

3.3.3.4.1 and 3.3.4 above) are exceeded.

3.3.6 The Contractor will implement the following Best Management Practices (BMPs) to prevent spills and other releases to the environment, and to meet NFPA, OSHA, and RCRA requirements:

3.3.6.1 The Contractor shall store all Hazmat only in the designated Hazmat storage area approved by the Contracting Officer, per submittal 3.3.2.1., protected from precipitation and direct sunlight.

3.3.6.2 The Contractor shall provide secondary containment for all Hazmat being stored on base. Secondary containment shall be chemically inert to the Hazmat being stored and impervious to absorption of the Hazmat (spilled, dripped or leaked). The secondary containment volume shall not be less than 10% of the total quantity being stored or the equal quantity of the largest container being stored, whichever is greater in volume. Separate secondary containment shall be provided for incompatible Hazmats, such as acids and bases, flammables and corrosives, flammables and oxidizers, etc.

3.3.6.3 The preservation of the landscape shall be an imperative consideration in the selection of all sites. No activity shall be conducted or storage permitted within the dripline of any tree without being depicted on the drawings and being approved by the Contracting Officer.

3.3.6.4 The Contractor shall be responsible for the cleanup and disposal of all spilled Hazmats, including any spilled, leaking or dripping hydraulic fluid and other fluids from equipment and vehicles.

3.3.6.4.1 Spills have no size limit; any amount spilled shall be cleaned up by the Contractor. The Contractor shall provide all materials use to contain and absorb any spill, and shall provide appropriate and proper containers into which the spill debris shall be placed. Spill absorbents used shall be picked up immediately and placed in the disposal container.

3.3.6.4.2 Disposal of spilled wastes generated from spill cleanup shall be the Contractor's responsibility and shall meet all federal, state and other regulations regarding storage, shipment and disposal.

SECTION 01 56 00 Page 7

3.3.6.5 The Contractor shall use NFPA and OSHA required or specified flammable material and corrosive material storage lockers for the storage of all Hazmats.

3.3.6.6 The Contractor shall segregate incompatible materials at all times in his or her field office, storage, staging and work areas.

3.3.6.7 The Contractor shall use protective measures, such as drop cloths and tarpaulins, when using Hazmats, in order to keep the work and storage areas free from drips and spills and to protect unimproved surfaces from environmental contamination.

3.3.6.8 The Contractor shall keep all containers closed at all times when not in use. At any time when a hazmat is finished being used for the day, the hazmat container shall be returned to the designated storage area.

3.3.6.9 The Contractor shall not store Hazmat outdoors where it may be exposed to sun, rain, wind or other elements and precipitation. The Contractor shall follow all manufacturers' recommendations for storage of Hazmat, according to the PDS.

3.3.6.10 The Contractor shall ensure that Hazmats are never poured out onto grass or soil, and are never drained to or dispose of on the ground, in a water way or via the storm sewer system. Mixtures of water and/or Hazmats shall never be dumped onto the ground.

3.3.6.11 The Contractor shall ensure that all employees are given proper training in the use and storage of the Hazmats onsite, and in the use of any personal protective equipment necessary for the proper use of Hazmat on Dobbins ARB.

3.3.7 The Contractor shall not generate any waste as a result of cleaning Contractor tools, vehicles, containers or other equipment on base; cleaning contaminated equipment is prohibited. The Contractor shall plan to clean used equipment off base.

3.4 STORM WATER POLLUTION PREVENTION

The Contractor is authorized to perform land disturbing activities and exterior facility work under the scope of this project. The project requires coverage under Georgia National Pollutant Discharge Elimination Standard (NPDES) general permit for construction activity GAR100001.

Further, federal (USACE) permits may be needed for impacts to wetlands, streams or other Waters of the United States.

3.4.1 References

3.4.2 Code of Federal Regulations 32 CFR 332 - Permits for Discharges of Dredged or Fill Material into Waters of the United States.

3.4.2.1 GA Rule 391-3-03k: Water Quality Standards

3.4.2.2 GA Rule 391-3-7: Erosion and Sedimentation Control

3.4.2.3 Cobb County, Article VIII: Soil Erosion and Sedimentation Control

3.4.2.4 Erosion Control Manual: Manual for Erosion and Sediment Control in Georgia (2016 Edition)

SECTION 01 56 00 Page 8

3.4.2.5 Storm Water Pollution Prevention Plan: Dobbins ARB Storm Water Pollution Prevention Plan (Most current)

3.4.2.6 General NPDES Permit Number GAR050000: Authorization to Discharge Under the National Pollutant Discharge Elimination System (NPDES) Storm Water Discharges Associated with Industrial Activities

3.4.3 Submittals

3.4.3.1 Draft Notice of Intent (NOI)

3.4.3.2 Final NOI Submission Package

3.4.3.3 Cobb County Land Disturbance Permit (LDP)

3.4.3.4 ESPCP Plan Changes

3.4.3.5 ESPCP Initial Inspection Report

3.4.3.6 ESPCP Monthly Report

3.4.3.7 Notice of Termination (NOT)

3.4.4 NPDES and Land Disturbance Permit

3.4.4.1 The Contractor shall prepare the draft Notice of Intent (Submittal 3.4.2.1) for Georgia NPDES permit GAR100001. The NOI along with all supporting documents shall be submitted to the Government for review at least 30 days prior to starting land disturbing activities. The contractor shall be listed as the Primary Permittee (operator) of the site. The contractor is fully responsible for ensuring the project complies with the requirements of Georgia permit GAR100001 and the Erosion, Sedimentation, and Pollution Control Plan executing this permit under the scope of this project.

3.4.4.2 The Government will review the draft and return it to the Contractor within 10 days after receipt. Within 7 days after receiving the Government review comments, the Contractor shall then finalize and sign the NOI and submit the completed NOI, required supporting documents, and applicable permit fees to the Georgia Environmental Protection Division (EPD). This mailing shall be certified return receipt requested. The Contractor is authorized to begin land disturbing activities 14 days after the date the NOI is submitted. The Contractor will submit a copy of the final NOI Submission Package (Submittal 3.4.2.2) including the return receipt to the Government prior to land disturbing activities.

3.4.4.3 The Contractor shall obtain a Cobb County Land Disturbance Permit (LDP) prior to land disturbing activities. Under an agreement with Cobb County, a LDP can be obtained by the Contractor after providing a copy of the signed NOI package submitted to the State, a copy of the Erosion and Sedimentation Control plan from the drawings, and payment of any applicable permit fees to Cobb County. The contractor shall submit the LDP (Submittal 3.2.4.3) to the Contracting Officer prior to land disturbing activities.

3.4.4.4 The Contractor will be provided an Erosion, Sedimentation, and Pollution Control Plan (ESPCP) as part of the design package. The ESPCP

SECTION 01 56 00 Page 9 is required pursuant to permit GAR 100001. The Contractor is required to execute fully the ESPCP as part of this contract. It is the Contractors responsibility to ensure the ESPCP is up to date and any changes of the project are incorporated into the plan in accordance with permit requirements. Changes to the ESPCP shall be submitted (Submittal 3.4.2.4) to the Contracting Officer and CEV for their records.

3.4.4.5 The Contractor is required to perform an initial site inspection within seven days after installation of initial sediment storage and perimeter control BMPs. Pursuant to Part IV-A-5 of the permit, the Contractor shall retain the original design professional who prepared the ESPCP to perform this inspection. The design professional has seven days to submit a report to the contractor who has two days to correct deficiencies. The contractor shall submit (Submittal 3.4.2.5) a copy of the design professional's initial inspection report to the government upon receipt.

3.4.4.6 The Contractor shall submit ESPCP Monthly Reports (Submittal 3.4.2.6) to the Contracting Officer no later than 5 calendar days after the end of each month for every month beginning when the NOI is submitted including the last month when the NOT is submitted. The ESPCP Monthly report shall include:

3.4.4.6.1 All daily inspections performed during the previous month;

3.4.4.6.2 All weekly inspections performed during the previous month;

3.4.4.6.3 All post storm event inspections performed during the previous month;

3.4.4.6.4 The Monthly Inspection report for the previous Month;

3.4.4.6.5 Laboratory results of any storm water samples taken during the previous month

3.4.4.7 The Government shall be responsible for sending any required reports under the NPDES permit to the State of Georgia. Copies of any such reports will be provided to the Contractor for recordkeeping purposes.

3.4.4.8 Once land disturbing activities are concluded, final grade and vegetation is established, the Contractor shall prepare, initial, and sign and submit the Notice of Termination (Submittal 3.4.2.7) for GAR100001.

The NOT shall be submitted to the Government when final stabilization of the site has been established. Once the submittal is approved, the Government shall sign the NOT as the owner and submit the notice to the State of Georgia. The Government shall provide a copy of the signed NOT back to the Contractor. The Contractor shall continue to follow the ESPCP until they receive written or e-mail notice from the Government, the NOT has been submitted to the State.

3.4.4.9 The Contractor is required to keep the ESPCP including all inspections, reports, and notifications for at least three years after the Notice of Termination is submitted to the State of Georgia.

3.4.5 Dobbins ARB Storm Water Protection Requirements

3.4.5.1 No fuels, oils, acids, wastes, or other materials shall be permitted to enter these water resources directly or through storm drain inlets in accordance with Georgia Rule 391-3-03kWater Quality Standards.

SECTION 01 56 00 Page 10

3.4.5.2 The Contractor is prohibited from pouring ANY material down a storm drain. Exceptions to this requirement may be granted by the Contracting Officer after a written request for the discharge is approved by the Government and is consistent with permit requirements.

3.4.5.3 If the Contractor believes he/she has encountered federally protected floodplains or wetlands not specified in the contract during the execution of work, the Contractor shall stop work on the site immediately and notify the Contracting Officer.

3.4.5.4 The Contractor is responsible for obtaining all necessary and appropriate federal (U.S. Army Corps of Engineers) and state (Georgia Environmental Protection Division) waivers and/or permits for land disturbing activities occurring within twenty-five (25) feet of designated Waters of the State of Georgia and any impacts or discharges of fill material to Waters of the United States or that involve wetland, stream bed or bank disturbance. Designated Waters of the State and/or United States present on Dobbins ARB include multiple wetlands, Rottenwood Creek, Poorhouse Creek, Big Lake, Little Lake, and their respective tributaries.

CEV will provide the most recent aquatic resource delineation report upon request.

3.5 PETROLEUM OIL AND LUBRICANT (POL) USE AND MANAGEMENT

The Contractor is permitted to: fill vehicles or equipment on Dobbins with fuel; add oil or lubricant to vehicles or equipment; and to store and use gasoline, diesel, oil or hydraulic fluid under the scope of this project.

3.5.1 References

3.5.1.1 Dobbins HAZMAT Plan: Dobbins Air Reserve Base Hazardous Materials Emergency Response (HAZMAT) Plan (April 2013 or Current)

3.5.2 Hazardous Material Requirements . The Contractor is required to follow hazardous material requirements outlined in Paragraph 3.3 in addition to POL requirements outlined in this subsection for the following POL products:

3.5.2.1 Gasoline

3.5.2.2 Jet Fuel (JP-8)

3.5.2.3 Diesel Fuel

3.5.3 Storage

3.5.3.1 The Contractor shall not store any quantity of fuel or other petroleum products in tanks or bladders larger than 5 gallons without government approval.

3.5.3.2 The Contractor shall provide and use secondary containment for storage of fuel and other petroleum products. Material used in the establishment of secondary containment shall be inert and impervious to the material being stored. Secondary containment shall be able to contain at least the contents of the largest container for which it is employed plus ten percent. Separate containment shall be provided for incompatible materials. If the tank and secondary containment are exposed to rainfall, SECTION 01 56 00 Page 11 the following additional requirements apply:

3.5.3.2.1 Sufficient freeboard shall be incorporated to ensure the containment will hold the complete contents of the tank plus ten percent plus 6" of rainfall.

3.5.3.2.2 Storm water drained off the secondary containment must be inspected and monitored before draining out of the containment. If POL is present, the water must be disposed of as petroleum contact water and cannot be discharged to the environment.

3.5.3.2.3 Inspection and draining of any accumulated water shall be conducted at least once a week or after rain fall events.

3.5.4 Transfer Operations. In all transfer activities, the Contractor shall maintain segregation of incompatible materials.

3.5.5 Vehicle Capacity. The Contractor is prohibited from using any vehicle for the transportation of fuel or other POL products on Dobbins ARB with a total tank capacity of greater than 2,000 gallons per storage compartment.

3.5.6 Spill Control and Cleanup. The Contractor shall be responsible for the cleanup and disposal of all spilled POL products, including all materials use to contain and absorb the spill. The Contractor shall maintain a stock of spill cleanup material, e.g. absorbent material, on hand at all locations where fuel or petroleum products are stored and transferred. The Contractor's stock of spill cleanup materials shall be adequate to clean up the total amount of products being stored by the Contractor or the total amount being transferred by the Contractor.

Disposal of wastes generated from spill cleanup shall be the contractor's responsibility and be in accordance with this section.

3.6 LANDSCAPE PROTECTION

The Contractor is prohibited from performing exterior work that can harm or threaten trees, shrubs, grass, and landscaping on Dobbins. The Contractor is prohibited from driving on any surface other than paved or graveled roads on Dobbins ARB. If the project requires exterior work, the Contractor shall immediately notify the Contracting Officer.

3.7 HAZARDOUS WASTE MANAGEMENT

The Contractor is permitted to generate Hazardous Waste (HW) under the scope of this project within the conditions set forth in this section.

The Contractor shall comply with federal, state and local regulations with regard to Hazardous Waste management and disposal under all circumstances. Hazardous waste characterization shall be determined by the Government during review of the hazardous materials submitted by the Contractor.

3.7.1 References

3.7.1.1 Resource Conservation and Recovery Act (RCRA), 40 Code of Federal Regulations, Parts 260-271, Hazardous Waste Management

3.7.1.2 Georgia Department of Natural Resources, Environmental Protection Division, Georgia Rule 391-3-11, Hazardous Waste Management

SECTION 01 56 00 Page 12

3.7.2 Submittals

3.7.2.1 Project specific Hazardous Waste Management Plan (HWMP)

3.7.2.2 Accumulation log for waste container

3.7.2.3 Wastestream profile document

3.7.2.4 Analytical results documents for waste sample analysis

3.7.2.5 Weekly inspection checklist for hazardous waste storage site

3.7.2.6 Generator's copy of initial EPA Form 8700-22, Uniform Waste Manifest

3.7.2.7 Generator's return copy of EPA Form 8700-22 signed by receiving Treatment, Storage and Disposal Facility (TSDF)

3.7.3 Definitions

3.7.3.1 Hazardous Waste shall be defined as any solid waste that exhibits hazardous characteristics or is listed as defined by RCRA. Any solid waste intended to be discarded by the Contractor shall have a waste determination made as to whether or not the waste meets these hazardous characteristics or is listed. The physical properties of hazmats used by the Contractor shall be used by the government to initially determine whether or not hazardous waste can be expected to be generated by the use of a hazmat. The Contractor shall sample and analyze any wastestream in accordance with RCRA sampling requirements if the Contractor disputes any government waste determinations.

3.7.3.2 Empty Containers shall be defined by RCRA as containing less than one inch of residue in the bottom of a 55-gallon drum, as containing no more than film residue in smaller containers, and, for aerosol cans, as containing no propellant or product. Empty containers, by definition, are not hazardous waste. Some containers, by virtue of their shape and the properties of the hazmat contained, cannot be emptied (i.e. cartridges, tubes, etc.), but those that can be emptied shall be emptied through physical means by the Contractor so that all material is used.

3.7.4 Project Specific Hazardous Waste Management Plan (HWMP)

3.7.4.1 Prior to the use of any hazmat identified through submittal approval as potentially generating hazardous waste, the Contractor shall submit for approval to the Contracting Officer a project specific Hazardous Waste Management Plan (HWMP) (ref. submittal 3.7.2.1) describing how the Contractor plans to meet regulatory requirements for the proper collection, storage, labeling, secondary spill containment, signage, accumulation time, inspection schedules, transportation, and disposal of hazardous waste generated by the Contractor during the performance of the work under this project / task order, under this contract.

3.7.4.2 This Plan shall include:

3.7.4.2.1 the location and layout of the site to be established for the temporary storage of HW (hereafter referred to as a Satellite Accumulation Point ( SAP) ) - the site shall be located at or near the point of generation where waste initially accumulates, and under the control of the operator of the process generating the waste, in accordance with RCRA

SECTION 01 56 00 Page 13 regulation ( 40 CFR262.15(a) ) ;

3.7.4.2.2 the name of the designated person responsible for waste management activities and inspections of the SAP and container(s) within the SAP (to be known as the SAP site manager) and a current certificate of training indicating that the designated person has had RCRA Hazardous Waste training (reference 40 CFR 262.16(b)(9)(iii));

3.7.4.2.3 the specific procedures to be followed by Contractor personnel to collect, store, label, transport and dispose of hazardous waste (and the personnel training thereof);

3.7.4.2.4 the procedures to be followed by Contractor personnel to respond to a spill of hazardous waste, either from a container or from the SAP area;

3.7.4.2.5 the name, address, phone number and EPA ID number of the permitted Treatment, Storage and Disposal Facility (TSDF) to be used for the disposal of the hazardous waste, and a point of contact name and phone number; the chosen TSDF shall not be under consent order, cleanup order or have a recent history of operational violations, as recorded by the EPA database ECHO (Contractor may choose to use the same TSDF as the government, upon request, so that the government will provide this information to the Contractor);

3.7.4.2.6 the name, address, phone number and EPA ID number of the hazardous waste transporter to be used to transport the waste from Dobbins ARB to the TSDF, and a point of contact name and phone number (Contractor may choose to use the same hazardous waste transporter as the government, upon request, so that the government will provide this information to the Contractor);

3.7.5 Hazardous Waste Generation, Collection and Storage

3.7.5.1 No more than a cumulative total of 55 gallons of hazardous waste shall be allowed to be collected and stored in a SAP at any given time;

3.7.5.2 An accumulation log for each waste collection container stored within the SAP shall be used to record every addition of waste to each container, identifying the waste by name and description, the approximate amount added to the container, and the data added;

3.7.5.3 Every container stored within the SAP shall be uniquely numbered to enable its identification separately from other containers that may be stored concurrently;

3.7.5.4 Containers used to collect, store and transport hazardous waste shall be new, United Nations (UN)-certified hazardous waste shipping containers. Container materials shall be compatible with the hazardous waste being collected and stored within the container. Containers shall be filled to no more than 95% capacity to allow for headspace and expansion.

3.7.5.5 Containers shall be labeled "Hazardous Waste", and the label shall include the name of the wastestream and the applicable EPA Waste Codes. Container shall be labeled with an indication of the hazards of the contents ( e.g. OSHA GHS Pictograms; reference 40 CFR 262.15(a)(5) ) .No accumulation start date shall be recorded on the label until the container

SECTION 01 56 00 Page 14 reaches 55 gallons (therefore no date should be on the container at any time while stored in the SAP).

3.7.5.6 Containers shall be kept securely closed at all times when waste is not actively being added to the container. Rings shall be kept on drums, closed with drum bolt or locking ring. Screw top lids shall be screwed on firmly. No funnels shall be allowed to remain on top of a container when waste is not actively being added to the container.

3.7.6 Hazardous Waste Transfer.

3.7.6.1 The Contractor may use a transfer container to collect any hazardous waste being generated near the SAP during an operation where the SAP collection container is too cumbersome to use (i.e. roofing waste can be collected in a 5-gallon bucket transfer container, with the intention of emptying into the 55-gallon SAP collection container). The transfer container shall be emptied into the SAP collection container as soon as operation generating the hazardous waste ceases for the day.

3.7.6.2 The Contractor shall label any hazardous waste transfer container with the words "Hazardous Waste Transfer Container" and shall also have the corresponding EPA waste codes on the label as well. The transfer container shall be labeled with an indication of the hazards of the contents. This transfer container shall be empty at all times except during the time of day when collecting any waste generated during the operation.

3.7.7 Hazardous Waste Disposal

3.7.7.1 Documentation Signature: All documentation specifying the signature of the hazardous waste "Generator" must be signed only by the Base Environmental Coordinator (BEC). This includes waste characterization profiles, manifests and Land Disposal Restriction (LDR) forms which shall accompany any manifest. All TSDFs require a waste profile for each hazardous waste to be picked up and transported. All waste transportation requires a uniform hazardous waste manifest (EPA Form 8700-22) and LDR

3.7.7.2 Generator Identification Number. The government shall supply the generator identification number for each hazardous waste manifest.

3.7.7.3 Manifest Number. A unique manifest tracking number assigned in accordance with a numbering system approved by EPA must be pre-printed in Item 4 of the manifest. The tracking number must consist of a unique three-letter suffix following nine digits

3.7.7.4 Generator's Address and Phone Number. The Government shall supply this information for each hazardous waste manifest.

3.7.7.5 A copy of the partially completed manifest (with the appropriate DOT information and profile information completed) and a copy of the LDR shall be submitted to the Contract Administrator and Base Environmental at least ten (10) days prior to removal of HW from Dobbins ARB (Submittal 3.7.2.3) for review and approval.

3.7.7.6 The transporter shall sign the manifest at pickup time first.

The Contractor shall bring the manifest to Building 510 thereafter to have the BEC sign the manifest. The government shall retain the generator's copy of the manifest.

SECTION 01 56 00 Page 15

3.7.8 Hazardous Waste Spill Control And Cleanup. In the event of any spill of hazardous waste, the Contractor shall immediately notify the Base Fire Department (911 or x4840) in accordance with the Dobbins ARB HAZMAT Emergency Response Plan. The Contractor shall attempt to control the spill by limiting the spill area and by stopping the spill source if possible. The Contractor is responsible for all spills occurring at SAPs managed by the Contractor.

3.7.9 If the Contractor generates hazardous waste not authorized under the scope of this contract, the Contracting Officer shall be notified immediately. The Contractor is responsible for management and disposal of such waste in accordance with federal, state, local, and base requirements.

3.8 PESTICIDES

Use of pesticides under the scope of this project is authorized provided the Contractor complies with requirements outlined within this paragraph.

3.8.1 References

3.8.1.1 Dobbins ARB approved pesticide list.

3.8.2 Submittals

3.8.2.1 Pesticide Applicator Certification (reference 3.8.4 below)

3.8.2.2 Completed Pesticide Application Tracking Form (reference 3.8.5 below)

3.8.3 Approval. Contractor shall only use pesticides already approved for use on Dobbins ARB. CEV will provide the list. Since all pesticides are also hazardous materials, the Contractor shall submit a current SDS and label for the product to be used along with a Material Information Sheet, per Section 3.3 of this specification prior to use.

3.8.4 Pesticide Applicator Certification. Application of all pesticides shall be accomplished by certified pest control personnel or under the supervision of a State of Georgia certified pest control operator. The Contractor shall submit personnel certification (Submittal 3.8.2.1) with HAZMAT Submittals 3.3.2.1 and 3.3.2.2. Applicator Certifications shall be valid, as a minimum, through to the completion of any applications to be accomplished under this contract.

3.8.5 Pesticide Application Tracking Form. The Contractor shall complete the Pesticide Application Tracking form each day for every pesticide application. Each Monday, the Contractor shall submit the completed tracking form via email to the Pest Management Program Manager (Submittal 3.8.2.2) .

3.8.6 Disposal. The Contractor is prohibited from disposing of excess pesticides on Dobbins ARB in base dumpsters or down sanitary, industrial, or storm drains. The Contractor is responsible for disposing of pesticides and pesticide waste off base in accordance with Georgia and federal requirements.

3.9 RADIOACTIVE MATERIAL (RAM)

The Contractor is prohibited from disturbing any radioactive materials or

SECTION 01 56 00 Page 16 using equipment or tools containing radioactive sources. This includes, but is not limited to: ionizing radiation emitters, non-ionizing radiation emitters, and lasers. Permission and instruction for use of such equipment must be obtained prior to beginning work from the Radiation Officer located in the Bioenvironmental Engineering office, Building 550.

3.10 UNIVERSAL WASTES

The disturbing, removing, replacing, and/or disposal of fluorescent or High Intensity Discharge (HID) lamps, ballasts, mercury-containing materials (e.g. thermostats, switches, etc.), batteries, or aerosol cans of any kind is authorized under the scope of this project provided the Contractor complies with all requirements outlined within this section.

3.10.1 References:

3.10.1.1 Georgia Environmental Protection Division Rule 391-3-11-18:

Standards for Universal Waste Management

3.10.1.2 Title 40 Code of Federal Regulations (CFR) Part 273 (40 CR 273)

3.10.2 Submittals

3.10.2.1 Universal Waste Tracking Log

3.10.2.2 Recycler and Transporter Information

3.10.2.3 Universal Waste Shipping Manifest

3.10.3 Batteries

3.10.3.1 Any batteries removed, replaced or disposed of as a result of this project shall be handled, collected and recycled as Universal Waste in accordance with this Section. Any leaking batteries shall be handled, collected and disposed of as Hazardous Waste in accordance with Section

3.7 of this specification.

3.10.3.2 The Contractor shall collect and store used batteries in plastic lidded U.N. certified shipping containers with the terminals taped with electrical tape. These containers shall be labeled "Universal Waste Batteries (fill in type)" and shall have the initial start date written on the container (the date the first battery was collected in the container). Lids shall remain securely closed on the collection containers at all times.

3.10.3.3 Batteries shall be separated by type, according to DOT shipping requirements. Containers shall not accumulate more than 60 pounds of batteries each. The Contractor shall keep track of the quantity of batteries (number) collected in each collection container, along with the date added to the container, on a Universal Waste Tracking Log (UWTL) (ref. Submittal 3.10.2.1) that shall be kept with each container. Each full container of batteries shall be weighed in pounds by the Contractor prior to shipment, and the weight of each container shall be recorded on the UWTL. The Contractor shall write a unique container number on each container, and record that number and its corresponding initial start date on the UWTL, which shall be kept wherever the containers are stored.

3.10.3.4 The Contractor shall submit for government review and approval the name, address, phone number, point of contact, and EPA ID number of

SECTION 01 56 00 Page 17 the recycling facility and hazmat transporter to be used to transport and receive collected batteries (ref. Submittal 3.10.2.2) PRIOR to beginning removal or replacement of any batteries.

3.10.3.5 No battery collection/shipping container shall remain on Dobbins beyond contract completion and no longer than one calendar year from the initial start date. All batteries shall be manifested and shipped off base to the pre-approved Recycling facility prior to the completion of the contract. The manifest shall be signed by the Base Environmental Coordinator, shall list all containers and weights being shipping, and shall identify both the receiving facility and the transporter on the document. A copy of this shipping manifest shall be given to the government at the time of shipment (ref. Submittal 3.10.2.3).

3.10.4 Fluorescent Light Ballasts

3.10.4.1 Fluorescent light ballasts manufactured between 1 July 1978 and 1 July 1998 that do not contain PCBs are marked by the manufacturer with the words "No PCBs." If a fluorescent light ballast is discovered to be unmarked with these words "No PCBs", the contractor must use the manufacture date to determine if the ballast shall be considered a PCB ballast.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .