ATTACH_4_-_Contractor_Construction_Schedule.pdf

PDF 548 KB Posted

Attached to
Cougar Mountain AML Construction WA-24-003
Solicitation number
140S0324B0001
Issued by

About this file

This document appears to be a Contractor Construction Schedule for the Cougar Mountain AML Construction WA-24-003 contract opportunity. The schedule outlines the key activities and timeline for the construction work, including mobilization, site preparation, concrete placement, monument installation, restoration, and demobilization. The work is divided into several feature items (CC-064, CC-102a, CC-0102b, CC-322, CC-333c, and CC-118) with detailed day-by-day activities specified over a 42-day period. The construction schedule is part of the overall solicitation for the Cougar Mountain AML Construction project, which is being procured by the Department of the Interior's Office of Surface Mining Reclamation and Enforcement. The solicitation number is 140S0324B0001.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Cougar Mountain Regional Wildland Park Reclamation Engineers Estimate

OSMRE WA-24-003, H&A 0202993-014

Date

Features Item Work Day 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42

Date Feature Item Work Day 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42

CC-064

Date

Feature Item Work Day 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42

CC-102a

Date Feature Item Work Day 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42

CC-0102b

CC-048,

CC-049,

CC-050,

CC-051,

CC-052,

CC-056,

CC-057, and

CC-060,

Deliver sanitary facilities and mobilize

Access site and prepare work area

Repair existing monuments

Restore site

Abandon site and demobilize

Deliver sanitary facilities and mobilize

Access site and prepare work area

Lay concrete line for pumping

Place first phase of structural concrete as backfill

Place optional second phase of structural concrete

Place monument

Grade subsidence edges, construct drainage features

Break down concrete line

Restore site

Abandon site and demobilize

Abandon site and demobilize

Deliver sanitary facilities and mobilize

Access site and prepare work area

Lay concrete line for pumping

Install temporary bulkhead at OSMRE's discretion

Install rebar reinforcement at OSMRE's discrection

Place first phase of structural concrete as backfill

Potential second phase of structural concrete placement (see Section 01 20 00)

Place monument

Grade subsidence edges, construct drainage features

Break down concrete line

Restore site

Deliver sanitary facilities and mobilize

Access site and prepare work area

Lay concrete line for pumping

Install temporary bulkhead at OSMRE's discretion

Place first phase of structural concrete as backfill

Potential second phase of structural concrete placement

Place monument

Grade subsidence edges, construct drainage features

Break down concrete line

Restore site

Abandon site and demobilize

Hart Crowser 772292/Table 01 10 00-1_Construction Schedule_Blank.xlsx - Table 01 10 00-1_Blank

Date

Feature Item Work Day 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42

CC-322

Date

Feature Item Work Day 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42

CC-333c

Date

Feature Item Work Day 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42

CC-118

Abandon site and demobilize

Deliver sanitary facilities and mobilize

Access site and prepare work area

Lay concrete line for pumping

Install temporary bulkhead at OSMRE's discretion

Install rebar reinforcement at OSMRE's discretion

Place first phase of structural concrete as backfill

Potential second phase of structural concrete placement (see Section 01 20 00)

Place monument

Grade subsidence edges, construct drainage features

Breakdown concrete line

Restore site

Deliver sanitary facilities and mobilize

Deliver sanitary facilities and mobilize

Access site and prepare work area

Lay concrete line for pumping

Install temporary bulkhead

Place structural concrete as backfill

Place monument

Grade subsidence edges, construct drainage features

Breakdown concrete line

Restore site

Abandon site and demobilize

Access site and prepare work area

Weld replacement rebar on grate

Restore site

Abandon site and demobilize

Hart Crowser 772292/Table 01 10 00-1_Construction Schedule_Blank.xlsx - Table 01 10 00-1_Blank