Attach 3 Schedule of Items Quote Sheet.xlsx

XLSX spreadsheet 19 KB Posted

Attached to
Wrangell Cabin Maintenance 2022 Federal contract opportunity
Solicitation number
1240BF22Q0070
Issued by
Department of Agriculture Forest Service

View the file

Other files for this federal contract opportunity

Other files attached to Wrangell Cabin Maintenance 2022, newest first.
File Type Posted
1240BF22Q0070 RFQ Wrangell Cabin Maint 2022.pdf PDF
Attach 1 PWS Wrangell Cabin Maintenance 2022.pdf PDF
APPENDIX 1 Wrangell Cabin Location Map.pdf PDF
Attach 2 WD 2015-5685 R17 03.15.2022 SE AK.pdf PDF
APPENDIX 2 Cabin Inspection Form.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BID SUMMARY SHEET

ONLY FILL OUT THE YELLOW HIGHLIGHTED CELLS THROUGHOUT THIS QUOTE SHEET

Wrangell Cabin Maintenance Services 2022

1240BF22Q0070
Company Name:
Point of Contact (POC):
CAGE Code:
UEI Number:please start using this number
DUNS Number:this number will no longer be used
Address:
Phone:
E-mail:
Fax
Base Item NumberDescriptionQuantityUnit of IssueUnit PriceTotal
0001Deep Bay Cabin Services1Lump Sum$0.00
0002Steamer Cabin Services1Lump Sum$0.00
0003Frosty Cabin Services1Lump Sum$0.00
0004Harding Cabin Services1Lump Sum$0.00
0005Berg Bay Cabin Services1Lump Sum$0.00
0006Garnet Cabin Services1Lump Sum$0.00
0007Mount Rynd Cabin Services1Lump Sum$0.00
0008Twin Lake Cabin Services1Lump Sum$0.00
0009Shakes Slough Cabin #1 Services1Lump Sum$0.00
0010Shakes Slough Cabin #2 Services1Lump Sum$0.00
0011Mount Flemer Cabin Services1Lump Sum$0.00
0012Mallard Slough Cabin Services1Lump Sum$0.00
Option Item Number:
0013Sergief Cabin Services1Lump Sum$0.00
0014Little Dry Island Cabin Services1Lump Sum$0.00
0015Gut Island Cabin #1 Services1Lump Sum$0.00
0016Gut Island Cabin #2 Services1Lump Sum$0.00
0017Koknuk Cabin Services1Lump Sum$0.00
Grand Total:$0.00
Notes:

Sheet1

BASE YEAR
CLIN #DESCRIPTIONQTYUNITUNIT PRICETOTAL COST
0002Category I Administrative Buildings
The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated.
Period of Performance: 11 months (Base Year)
QTYUNITUNIT PRICETOTAL COST
0002AACategory I Administrative Buildings Rest Room Cleans2,620,889sq. ft$ 0.0408$ 106,932.25*55,026x47.63= 2,620,888.58 SF (11month period)55026.0041990342522,861,352.22
The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated. The quantity represents the square footage to be cleaned over an 11 month period.0520.00
Period of Performance: 11 months (Base Year)0520.00
QTYUNITUNIT PRICETOTAL COSTERROR:#VALUE!52ERROR:#VALUE!
0002ABCategory I Administrative Buildings Hard Floor Cleans6,586,752sq. ft$ 0.0231$ 152,153.97*94,515x47.63= 4,501,749.45 SF138289.986773042527,191,079.31
The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated. The quantity represents the square footage to be cleaned over an 11 month period.0520.00
Period of Performance: 11 months (Base Year)0520.00
QTYUNITUNIT PRICETOTAL COSTERROR:#VALUE!52ERROR:#VALUE!
0002ACCategory I Administrative Buildings Carpet Floor Cleans1,204,420sq. ft$ 0.0192$ 23,124.87*19,831x47.63= 944,550.53 SF25287.0098677304521,314,924.51
The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated. The quantity represents the square footage to be cleaned over an 11 month period.$ 282,211.100520.00
Period of Performance: 11 months (Base Year)0520.00
0520.00
CLIN #DESCRIPTIONQTYUNITUNIT PRICETOTAL COST520.00
0003Category II Child Development Facilities520.00
The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated.52
Period of Performance: 11 months (Base Year).
QTYUNITUNIT PRICETOTAL COST
0003AACategory II Child Development Facilities Hard Floor Cleans11,485,212sq. ft$ 0.0252$ 289,427.35*390,060x238.15weeks = 9,302,139 SFTOTAL: 11,485,212.42 SF
The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated. The quantity represents the square footage to be cleaned over an 11 month period.*7,639x285.78 weeks = 2,183,073 SF
Period of Performance: 11 months (Base Year)
QTYUNITUNIT PRICETOTAL COST
0003ABCategory II Child Development Facilities Carpet Floor Cleans685,729sq. ft$ 0.0194$ 13,303.14*1113x238.15 weeks = 265,060.95 SFTOTAL: 685,729.11
The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated. The quantity represents the square footage to be cleaned over an 11 month period.*1472x285.78 weeks = 420,668.16 SF
Period of Performance: 11 months (Base Year)$ 302,730.50
CLIN #DESCRIPTIONQTYUNITUNIT PRICETOTAL COST
0004Category III Physical Fitness Centers
The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated.
Period of Performance: 11 months (Base Year).
QTYUNITUNIT PRICETOTAL COST
0004AACategory III Physical Fitness Centers Hard Floor Cleans3,010,146sq. ft$ 0.0344$ 103,549.02Bldg 3452(6W) 1,330,305.90 SF1W*Hockey 1,323x17.32 = 22,914.36 SF1,330,305.90
The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated. The quantity represents the square footage to be cleaned over an 11 month period.Bldg 3709 (7W) 1,416,325.68 SF6W*Hockey 1,323x30.31= 240,600.00 SF1,416,325.68
Period of Performance: 11 months (Base Year).22,914.36
QTYUNITUNIT PRICETOTAL COST240,600.00
0004ABCategory III Continuous Cleaning Physical Fitness Center Bldg 370911monthly$ 4,322.26$ 47,544.86Total Hours 1,657.05Provide locker room cleaning from 13:00-15:30 daily 1Male/1Female 2-1/2 hours each.3,010,145.94
The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated.
Period of Performance: 11 months (Base Year).
CLIN #DESCRIPTIONQTYUNITUNIT PRICETOTAL COST
0005Special /Emergency/Bio-Hazard Cleans
The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated.
Period of Performance: 11 months (Base Year).
QTYUNITUNIT PRICETOTAL COST
0005AASpecial Cleaning40,538per sq. ft$ 0.28$ 11,472.25
The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated. The quantity of square footage reserved for the Special Cleaning CLIN represents 20% of the total square footage for the contract.
Period of Performance: 11 months (Base Year).
QTYUNITUNIT PRICETOTAL COST
0005ABEmergency Cleaning22,296per sq. ft$ 0.38$ 8,405.59
The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated. The quantity of square footage reserved for the Emergency Cleaning CLIN represents 11% of the total square footage for the contract.
Period of Performance: 11 months (Base Year).
QTYUNITUNIT PRICETOTAL COST
0005ACBio-Hazard Cleaning10,134per sq. ft$ 1.13$ 11,471.69
The Contractor shall furnish all supplies, equipment and services required to perform work under this contract that are not listed under Section 3 of the PWS. Technical Exhibit 1, Performance Requirements Summary, in the Performance Work Statement outlines the cleaning standards and references the specific paragraph(s) associated. The quantity of square footage reserved for the Special Cleaning CLIN represents 5% of the total square footage for the contract.
Period of Performance: 11 months (Base Year).
CLIN #DESCRIPTIONQTYUNITUNIT PRICETOTAL COST
0006CONTRACT MANPOWER REPORTING1EA$ 100.0000$ 100.0000
Contractor Manpower Reporting Costs: 1 May 2016 to 30 March 2017. The Contractor Manpower Reporting requirement is associated with the Office of the Assistant Secretary of the Army (Manpower and Reserve Affairs) requirement to obtain better visibility of the Contractor service workforce.
The Contractor is required to enter data into the Contractor Manpower Reporting Application (CMRA) system as outlined in local information titled Contractor Manpower Reporting located with the clauses incorporated into the contract. Reporting period will be the period of performance not to exceed 12 months ending 30 September of each Government fiscal year and must be reported by 31 October of each calendar year. Data must be accurate and complete and entered into CMRA during the data gathering period of every year, or part of a year, for which the contract is in force. NOTE: If the reporting of Manpower Equivalents is not separately priced, insert “NSP in the blank shown.
BASE YEAR TOTAL COST:$ 767,485.01

File details come from the government source that posted it. Updated .