Attach-3-Price Sheet.xlsx

XLSX spreadsheet 21 KB Posted

Attached to
SANTA ANA NWR URGENT VC ROOF REPLACE
Solicitation number
140F0220R0041
Issued by

About this file

This document contains a price sheet for roof replacement services at the Santa Ana National Wildlife Refuge in California. The solicitation requests pricing for insurance and bonds, mobilization, trimming trees around the site, cleaning the existing roof, installing tapered insulation, substrate board, and PVC membrane on approximately 14,853 square feet of roof area. Pricing is to be provided as lump sums for various line items as well as overhead and profit percentages. The solicitation number is 140F0220R0041 and was issued by the Department of the Interior Fish and Wildlife Service Region 2 for an urgent roof replacement project at the refuge headquarters building. No pricing or cost data is included in the confidential government estimate attached.

View the file

Other files

File Type Posted
Attach-1-Drawings.pdf PDF
Sol_140F0220R0041.pdf PDF
Attach-2-Specifications.pdf PDF
Attach-4-DBA Min Wage Rates.pdf PDF
Attach-5-Past Performance and Clause.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Shingle Estimate

Project: Quarters Reroofing - Replacement Using Shingles
Prepared by: BRF 11/28/2008
Reference: Hurricane Dolly Estimates prepared by Staff
ITEM NO.DESCRIPTION OF OFFERED ITEMESTIMATED QUANTITYUNITUNIT PRICEESTIMATED AMOUNT
1Quarters 1: Shingle Replacement1700SF$ 2.00$ 3,400.00
2Quarters 1: Insulation replacement1700SF$ 1.00$ 1,700.00
3Quarters 1: Deck replacement1700SF$ 1.50$ 2,550.00
4Quarters 1: Insulation removal851CF$ 0.30$ 255.30
Subtotal$ 7,905.30
5Locality Adjustment @42%$ 3,320.23
6Mobilization and preparatory work @20%$ 1,581.06
SubTotal per Asset$ 12,806.59
7Engineering Services @10%$ 1,280.66
Asset Total$ 14,087.24
1Quarters 2: Shingle Replacement1700SF$ 2.00$ 3,400.00
2Quarters 2: Deck replacement1700SF$ 1.50$ 2,550.00
3Quarters 2: Insulation replacement1700SF$ 1.00$ 1,700.00
4Quarters 2: Insulation removal851CF$ 0.30$ 255.30
Subtotal$ 7,905.30
5Locality Adjustment @42%$ 3,320.23
6Mobilization and preparatory work @20%$ 1,581.06
SubTotal per Asset$ 12,806.59
7Engineering Services @10%$ 1,280.66
Asset Total$ 14,087.24
1Quarters 3: Shingle Replacement1700SF$ 2.00$ 3,400.00
2Quarters 3: Deck replacement1700SF$ 1.50$ 2,550.00
3Quarters 3: Insulation replacement1700SF$ 1.00$ 1,700.00
4Quarters 3: Insulation removal851CF$ 0.30$ 255.30
Subtotal$ 7,905.30
5Locality Adjustment @42%$ 3,320.23
6Mobilization and preparatory work @20%$ 1,581.06
SubTotal per Asset$ 12,806.59
7Engineering Services @10%$ 1,280.66
Asset Total$ 14,087.24
1Quarters 4-1 and 4-2: Shingle Replacement2568SF$ 2.00$ 5,136.00
2Quarters 4-1 and 4-2: Deck replacement2568SF$ 1.50$ 3,852.00
3Quarters 4-1 and 4-2: Insulation replacement2568SF$ 1.00$ 2,568.00
4Quarters 4-1 and 4-2: Insulation removal1284CF$ 0.30$ 385.20
Subtotal$ 11,941.20
5Locality Adjustment @42%$ 5,015.30
6Mobilization and preparatory work @20%$ 2,388.24
SubTotal per Asset$ 19,344.74
7Engineering Services @10%$ 1,934.47
Asset Total$ 21,279.22

TOTAL FOR SCHEDULE $ 63,540.95

&"Arial,Bold"&12Confidential Government Estimate

Prepared by Charles Caldwell &D

BUILDING

Project: SANTA ANA HQ RE-ROOF 2020

: Drawings 2R-TX-386-40.0
ATTACHMENT-3 PRICE SHEET
RFP 140f0220R0041
ITEM NO.DescriptionQUANTITYUNITUNIT PRICEAMOUNT
1Insurance & Bonds1LS$ - 0

2 Mobilization 1 Job $ - 0

3Trim Trees48Hrs$ - 0
$ - 0
4Clean Roof14,853SF$ - 0

5 Tapered insulation 5,196 SF $ - 0

6 Substrate Board 14,853 SF $ - 0

7 PVC Membrane 14,853 SF $ - 0

SUBTOTAL COST$ - 0
8%$ - 0

9 O/H % % $ - 0

10 Profit % % $ - 0

TOTAL PRICE $ - 0