Attach-3-Price Sheet.xlsx
XLSX spreadsheet 21 KB Posted
- Attached to
- SANTA ANA NWR URGENT VC ROOF REPLACE
- Solicitation number
- 140F0220R0041
About this file
This document contains a price sheet for roof replacement services at the Santa Ana National Wildlife Refuge in California. The solicitation requests pricing for insurance and bonds, mobilization, trimming trees around the site, cleaning the existing roof, installing tapered insulation, substrate board, and PVC membrane on approximately 14,853 square feet of roof area. Pricing is to be provided as lump sums for various line items as well as overhead and profit percentages. The solicitation number is 140F0220R0041 and was issued by the Department of the Interior Fish and Wildlife Service Region 2 for an urgent roof replacement project at the refuge headquarters building. No pricing or cost data is included in the confidential government estimate attached.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attach-1-Drawings.pdf | ||
| Sol_140F0220R0041.pdf | ||
| Attach-2-Specifications.pdf | ||
| Attach-4-DBA Min Wage Rates.pdf | ||
| Attach-5-Past Performance and Clause.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Shingle Estimate
| Project: Quarters Reroofing - Replacement Using Shingles | |||||
| Prepared by: BRF 11/28/2008 | |||||
| Reference: Hurricane Dolly Estimates prepared by Staff | |||||
| ITEM NO. | DESCRIPTION OF OFFERED ITEM | ESTIMATED QUANTITY | UNIT | UNIT PRICE | ESTIMATED AMOUNT |
| 1 | Quarters 1: Shingle Replacement | 1700 | SF | $ 2.00 | $ 3,400.00 |
| 2 | Quarters 1: Insulation replacement | 1700 | SF | $ 1.00 | $ 1,700.00 |
| 3 | Quarters 1: Deck replacement | 1700 | SF | $ 1.50 | $ 2,550.00 |
| 4 | Quarters 1: Insulation removal | 851 | CF | $ 0.30 | $ 255.30 |
| Subtotal | $ 7,905.30 | ||||
| 5 | Locality Adjustment @42% | $ 3,320.23 | |||
| 6 | Mobilization and preparatory work @20% | $ 1,581.06 | |||
| SubTotal per Asset | $ 12,806.59 | ||||
| 7 | Engineering Services @10% | $ 1,280.66 | |||
| Asset Total | $ 14,087.24 |
| 1 | Quarters 2: Shingle Replacement | 1700 | SF | $ 2.00 | $ 3,400.00 |
| 2 | Quarters 2: Deck replacement | 1700 | SF | $ 1.50 | $ 2,550.00 |
| 3 | Quarters 2: Insulation replacement | 1700 | SF | $ 1.00 | $ 1,700.00 |
| 4 | Quarters 2: Insulation removal | 851 | CF | $ 0.30 | $ 255.30 |
| Subtotal | $ 7,905.30 | ||||
| 5 | Locality Adjustment @42% | $ 3,320.23 | |||
| 6 | Mobilization and preparatory work @20% | $ 1,581.06 | |||
| SubTotal per Asset | $ 12,806.59 | ||||
| 7 | Engineering Services @10% | $ 1,280.66 | |||
| Asset Total | $ 14,087.24 |
| 1 | Quarters 3: Shingle Replacement | 1700 | SF | $ 2.00 | $ 3,400.00 |
| 2 | Quarters 3: Deck replacement | 1700 | SF | $ 1.50 | $ 2,550.00 |
| 3 | Quarters 3: Insulation replacement | 1700 | SF | $ 1.00 | $ 1,700.00 |
| 4 | Quarters 3: Insulation removal | 851 | CF | $ 0.30 | $ 255.30 |
| Subtotal | $ 7,905.30 | ||||
| 5 | Locality Adjustment @42% | $ 3,320.23 | |||
| 6 | Mobilization and preparatory work @20% | $ 1,581.06 | |||
| SubTotal per Asset | $ 12,806.59 | ||||
| 7 | Engineering Services @10% | $ 1,280.66 | |||
| Asset Total | $ 14,087.24 |
| 1 | Quarters 4-1 and 4-2: Shingle Replacement | 2568 | SF | $ 2.00 | $ 5,136.00 |
| 2 | Quarters 4-1 and 4-2: Deck replacement | 2568 | SF | $ 1.50 | $ 3,852.00 |
| 3 | Quarters 4-1 and 4-2: Insulation replacement | 2568 | SF | $ 1.00 | $ 2,568.00 |
| 4 | Quarters 4-1 and 4-2: Insulation removal | 1284 | CF | $ 0.30 | $ 385.20 |
| Subtotal | $ 11,941.20 | ||||
| 5 | Locality Adjustment @42% | $ 5,015.30 | |||
| 6 | Mobilization and preparatory work @20% | $ 2,388.24 | |||
| SubTotal per Asset | $ 19,344.74 | ||||
| 7 | Engineering Services @10% | $ 1,934.47 | |||
| Asset Total | $ 21,279.22 |
TOTAL FOR SCHEDULE $ 63,540.95
&"Arial,Bold"&12Confidential Government Estimate
Prepared by Charles Caldwell &D
BUILDING
Project: SANTA ANA HQ RE-ROOF 2020
| : Drawings 2R-TX-386-40.0 | |||||
| ATTACHMENT-3 PRICE SHEET | |||||
| RFP 140f0220R0041 | |||||
| ITEM NO. | Description | QUANTITY | UNIT | UNIT PRICE | AMOUNT |
| 1 | Insurance & Bonds | 1 | LS | $ - 0 |
2 Mobilization 1 Job $ - 0
| 3 | Trim Trees | 48 | Hrs | $ - 0 |
| $ - 0 | ||||
| 4 | Clean Roof | 14,853 | SF | $ - 0 |
5 Tapered insulation 5,196 SF $ - 0
6 Substrate Board 14,853 SF $ - 0
7 PVC Membrane 14,853 SF $ - 0
| SUBTOTAL COST | $ - 0 | ||
| 8 | % | $ - 0 |
9 O/H % % $ - 0
10 Profit % % $ - 0
TOTAL PRICE $ - 0