Attach-2-Price_Sheet.xlsx

XLSX spreadsheet 21 KB Posted

Attached to
QUIVIRA CLEANOUT SIX WATER CANALS
Solicitation number
140F0121R0050
Issued by

View the file

Other files

File Type Posted
Attach-1-REVISED-SOW_0001.pdf PDF
Sol_140F0121R0050_Amd_0001.pdf PDF
Sol_140F0121R0050.pdf PDF
Attach-1-SOW.pdf PDF
Attach-3-SCA_Wage_Rates.pdf PDF
Attach-4-Past_Performance_and_Clauses.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Shingle Estimate

Project: Quarters Reroofing - Replacement Using Shingles
Prepared by: BRF 11/28/2008
Reference: Hurricane Dolly Estimates prepared by Staff
ITEM NO.DESCRIPTION OF OFFERED ITEMESTIMATED QUANTITYUNITUNIT PRICEESTIMATED AMOUNT
1Quarters 1: Shingle Replacement1700SF$ 2.00$ 3,400.00
2Quarters 1: Insulation replacement1700SF$ 1.00$ 1,700.00
3Quarters 1: Deck replacement1700SF$ 1.50$ 2,550.00
4Quarters 1: Insulation removal851CF$ 0.30$ 255.30
Subtotal$ 7,905.30
5Locality Adjustment @42%$ 3,320.23
6Mobilization and preparatory work @20%$ 1,581.06
SubTotal per Asset$ 12,806.59
7Engineering Services @10%$ 1,280.66
Asset Total$ 14,087.24
1Quarters 2: Shingle Replacement1700SF$ 2.00$ 3,400.00
2Quarters 2: Deck replacement1700SF$ 1.50$ 2,550.00
3Quarters 2: Insulation replacement1700SF$ 1.00$ 1,700.00
4Quarters 2: Insulation removal851CF$ 0.30$ 255.30
Subtotal$ 7,905.30
5Locality Adjustment @42%$ 3,320.23
6Mobilization and preparatory work @20%$ 1,581.06
SubTotal per Asset$ 12,806.59
7Engineering Services @10%$ 1,280.66
Asset Total$ 14,087.24
1Quarters 3: Shingle Replacement1700SF$ 2.00$ 3,400.00
2Quarters 3: Deck replacement1700SF$ 1.50$ 2,550.00
3Quarters 3: Insulation replacement1700SF$ 1.00$ 1,700.00
4Quarters 3: Insulation removal851CF$ 0.30$ 255.30
Subtotal$ 7,905.30
5Locality Adjustment @42%$ 3,320.23
6Mobilization and preparatory work @20%$ 1,581.06
SubTotal per Asset$ 12,806.59
7Engineering Services @10%$ 1,280.66
Asset Total$ 14,087.24
1Quarters 4-1 and 4-2: Shingle Replacement2568SF$ 2.00$ 5,136.00
2Quarters 4-1 and 4-2: Deck replacement2568SF$ 1.50$ 3,852.00
3Quarters 4-1 and 4-2: Insulation replacement2568SF$ 1.00$ 2,568.00
4Quarters 4-1 and 4-2: Insulation removal1284CF$ 0.30$ 385.20
Subtotal$ 11,941.20
5Locality Adjustment @42%$ 5,015.30
6Mobilization and preparatory work @20%$ 2,388.24
SubTotal per Asset$ 19,344.74
7Engineering Services @10%$ 1,934.47
Asset Total$ 21,279.22

TOTAL FOR SCHEDULE $ 63,540.95

&"Arial,Bold"&12Confidential Government Estimate

Prepared by Charles Caldwell &D

BUILDING

ATTACHMENT-2 PRICE SHEET
RFP 140F0121R0050-Quivera Clean Canals
ITEM NO.DescriptionQUANTITYUNITUNIT PRICEAMOUNT
1Mobilization1LS$ - 0$ - 0
2RC Canal9,900LF$ - 0$ - 0
3West Canal22,106LF$ - 0$ - 0
4Darrynane Canal18,867LF$ - 0$ - 0
5F-Line Canal3,300LF$ - 0$ - 0
6D-Line Canal1,410LF$ - 0$ - 0
7C-Line Canal3,388LF$ - 0$ - 0
Total Price

File details come from the government source that posted it. Updated .