Attach 1 SOW Rivercane_Assessment.pdf
PDF 326 KB Posted
- Solicitation number
- 12445026Q0065
- Issued by
-
Department of Agriculture Forest Service
About this file
This is a Statement of Work (SOW) issued by the USDA Forest Service, Southern Research Station (SRS) in Asheville, North Carolina for a rivercane site suitability assessment supporting post-Hurricane Helene disaster recovery efforts in western North Carolina.
The project focuses on rivercane (Arundinaria gigantea), a woody bamboo relative, with two primary assessment objectives: (1) determining whether the presence or absence of rivercane mitigated bank erosion and streambank damage during Hurricane Helene by examining at least 10 study sites where rivercane was present and absent along geomorphically similar stream reaches, plus exploring leaf-off infrared imagery for selection of at least five additional sites; and (2) assessing physical characteristics of a minimum of 10 existing rivercane sites to identify common characteristics and make restoration site recommendations. Work includes using existing Forest Service remote-sensed data products (HiForm), comparing pre- and post-Helene LiDAR data, field verification using standard classification systems, and evaluating vegetation indices over two growing seasons. The contractor must provide a PhD-level scientist with expertise in biology, forestry, ecology, or natural resource management; three years of forest resources statistical application experience specific to rivercane; and demonstrated experience advising scientists on research study designs and data analysis for peer-reviewed publication.
The project timeline extends from October 2026 through September 2028, with an optional extension through September 2029. Deliverables include project methods (October 2026), draft and final reports on restoration site suitability (November 2026–July 2027), streambank assessment workflows (December 2026–May 2027), vegetative impact analysis (February–July 2027), and final reports on stream and biological productivity impacts (June 2028). Payment is milestone-based with 15 percent retainage, ranging from 5 to 15 percent per deliverable, with invoicing through www.ipp.gov. Contractor travel is estimated at 40 days to field sites in western North Carolina, including both day trips and overnight stays. All collected data shall be owned by USDA Forest Service and kept confidential, with no reporting, manuscripts, or presentations permitted without research team consent.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
Statement of Work
USDA FS, Southern Research Station
SRS HQ – RWU 4952
200 WT Weaver Blvd
Asheville NC, 28804
Rivercane Site Suitability Assessment for Post-Hurricane Helene Recovery
August 18, 2026
Contents Project General Information
1.0 Scope of Work
2.0 Background
Contractor Requirements
3.0 Technical Requirements / Tasks
4.0 Government Furnished
5.0 Deliverables / Schedule
6.0 Travel
7.0 Contractor’s Key Personnel
8.0 Security Requirements
9.0 Data Rights
10.0 Section 508 – Electronic and Information Technology Standards Attachment
Project Rivercane Site Suitability Assessment for Post-Hurricane Helene Recovery
General Information
1.0 Scope of Work
This contract supports a Congressionally funding allocation for Hurricane Helene disaster recovery assessment. This project focuses on rivercane (Arundinaria gigantea - a woody bamboo relative), to assess 1) its contribution to streambank stability, 2) persistence through historical high-water events, and 3) its potential as a restoration tool. The project assesses damage to riparian areas and site suitability for restoration efforts.
2.0 Background
Hurricane Helene caused devastating flooding across western North Carolina, significantly impacting river corridors across the region. Damage to riparian systems resulted in major economic impacts to the built environment, water-based recreation, and the local business that support this sector. The increasing frequency and intensity of flood events, such as those caused by Hurricane Helene, underscore the urgent need to understand the role of native vegetation in mitigating the impacts of natural disasters, and supporting recovery efforts. Rivercane ecosystems were historically widespread throughout the region but have been dramatically reduced in the past two centuries due to shifts in land use. Preliminary observations of damage to riparian systems suggest greater scouring impacts in areas without rivercane, whose dense rhizomatous networks aid in bank stabilization. Rivercane provides numerous ecosystem services and is also an important non-timber forest product (NTFP), contributing to economic livelihoods of Tribal Nations across the Southeast. Post-Helene, Western NC has experienced an upsurge in interest in restoring riparian corridors with rivercane. However, best science is needed to assess the impacts of flooding on extant populations of rivercane, and to guide successful, targeted restoration efforts.
Contractor Requirements
3.0 Technical Requirements / Tasks
This contract addresses two assessment objectives: 1) to determine if presence or absence of rivercane on the landscape mitigated Helene-related negative impacts on streambank stability and biological productivity and 2) to describe physical landscape characteristics of ideal restoration sites. Our approach will leverage existing remote-sensed data products produced by the FS Southern Research Station combined with rivercane patch polygon and point data to evaluate the contribution of rivercane to landscape resilience. The contractor will work with a Forest Service project lead, additional Southern Research Station scientists along with other technical professionals. The following tasks are required:
Goal One: To determine if presence or absence of rivercane mitigated bank erosion and damage, the contractor will examine impacts at locations where rivercane was present and absent along geomorphically similar reaches of the same stream in Helene-impacted watersheds of Western North Carolina. The contractor, in cooperation with the research team will use previously published rivercane patch location data to select at least 10 study sites and will explore a leaf-off IR imagery technique for selection of at least five additional sites. The contractor will employ existing, publicly available USFS Southern Research Station HiForm products to evaluate negative impacts to biological productivity and quantify vegetation indices for rivercane over the two growing seasons of the project. We will evaluate streambank impacts by comparing pre and post-Helene LiDAR data, using standard descriptors (e.g. Rosgen Stream Classification System, NRCS Stream Visual Assessment) and field verification.
Goal Two: The contractor will assess physical characteristics of a minimum of 10 existing rivercane sites using existing publicly available location datasets and determine common characteristics (e.g. geomorphic position, stream energy, watershed characteristics, stream sinuosity, distance to stream, flow accumulation) and make recommendations for restoration sites.
4.0 Government Furnished
N/A
5.0 Deliverables / Schedule. Timely submission of deliverables is essential to successfully completing this requirement.
Payment Procedures The Contractor shall be responsible for the preparation and submission of invoices in wwww.ipp.gov Payment shall be made based on completion of milestones and at percentages shown below based on total contract value. Contractor shall invoice only for work satisfactorily completed and accepted by the COR.
6.0 Travel
The contractor will be expected to travel to field sites within Western North Carolina. The travel does not need to be continuous, but on an as-needed basis across the duration of the project to fulfill objectives. Estimated travel days = 40.
Travel will involve day trips, and several overnight trips.
Delivery date Milestones & Deliverables Maximum Payment % / Due Date
From contract beginning to final data delivery
Bi-weekly or monthly virtual meetings with USFS and other research team members (timing TBD by research team)
5% / monthly
October 2026 Project methods developed. 5% / Due 30 days from issuance of award.
Nov 2026 – Jan. 2027
Field data collection initiated. Draft Report of ideal restoration site analysis.
15% / 10 days after analysis ends.
Dec. 2026-May 2027 Develop workflow for streambank assessment with existing Forest Service imagery products.
10% / 10 days after analysis ends.
February 2027 – July 2027 Field data evaluated; draft report on vegetative impacts through 2026 growing season completed
15% / 10 days after analysis ends.
July 2027-November 2027 Final Report on Ideal Rivercane Restoration Site Suitability completed
10% / 30 days after analysis ends.
November 2027 – March 2028 Second field data collection effort implemented. 10% / 10 days after analysis ends.
June 2028-August 2028 Final Report on Impacts to Streams and Biological Productivity completed
5% / within 30 days
September 2028 Final reporting and publication drafts completed 10% / within 30 days
Final Report Final report after completion of all contract rents (15% retainage required per Customary Progress Payments regulations FAR 32.501-1(a))
15% / within 30 days
Option Line for additional work if Necessary For following Period Oct 2028 – Sep 2029
Field data collection. Draft Report of ideal restoration site analysis. And Final Report FY29.
within 30 days
7.0 Contractor’s Key Personnel
- Provide Resume, demonstrating is a Scientists with PhD in Biologist with a concentration in forestry, ecology, and/or natural resource management.
- Fieldwork and data collection
- Three (3) years’ work experience in forest resources statistical applications. In Rivercane Site(Arundinaria gigantea - a woody bamboo relative)
- The offeror resume demonstrated how many years, and how many consultations per year, they advised scientists on research study designs, data analysis, and reviewing and improving their manuscripts before the scientist published their results in a peer-reviewed scientific journal.
8.0 Security Requirements
All data collected are to be kept strictly confidential and made available only to the research team. No reporting, manuscripts, or presentations can be made without the consent of the research team.
9.0 Data Rights
If data is to be produced, furnished, acquired, or used in meeting contract requirements, delineate the respective rights and obligations of the government and the contractor regarding the use, production, and disclosure of that data.
Insert Data Rights Here. The data shall be owned by the USDA Forest Service, Southern Research Station.
10.0 Section 508 – Electronic and Information Technology Standards N/A
Attachment N/A
| Project |
| General Information |
| 1.0 Scope of Work |
| 2.0 Background |
| Contractor Requirements |
| 3.0 Technical Requirements / Tasks |
| 4.0 Government Furnished |
| 5.0 Deliverables / Schedule. Timely submission of deliverables is essential to successfully completing this requirement. |
| 6.0 Travel |
| 7.0 Contractor’s Key Personnel |
| 8.0 Security Requirements |
| 9.0 Data Rights |
| 10.0 Section 508 – Electronic and Information Technology Standards |
| Attachment |
File details come from the government source that posted it. Updated .