This is a Performance Work Statement (PWS) for asbestos abatement services at Building 1300, Mountain Home Air Force Base (MHAFB), Idaho, with work to be completed within 30 days of contract award. The contractor must remove asbestos containing material (ACM) including: 192 square feet of ceramic floor tile with underlying grout/mortar/underlayment, 60 linear feet of residual Vinyl Composition Tile (VCT) with mastic and glue, eight 10-foot HVAC pipes, and insulation from one 10-foot water pipe (pipe must remain in place).
The contractor must provide all personnel, equipment, and materials necessary for the abatement work, which must comply with 40 CFR Part 61 standards for hazardous air pollutants. Key requirements include obtaining required permits/notifications 10 days before work begins, third-party clearance air sampling upon completion, and proper disposal documentation for hazardous waste. Work hours are Monday through Friday, 7:00 AM to 4:30 PM MST. The contractor must maintain quality control records and coordinate with base security for installation access. Photos included show the current condition of the work areas, including exposed pipes, damaged walls, and flooring requiring abatement.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| PWS Attach 1 - B231878e - MHAFB Building 1300 Pre-renovation Survey ACM.pdf | ||
| FA489725QC011 Oral Solicitation Asbestos Abatement.pdf | ||
| Attach 2 - WD 2015-5513 22 July 2024.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA489725QC011
Performance Work Statement
(PWS)
For
Asbestos Abatement (Bldg. 1300)
Mountain Home AFB (MHAFB), ID
10 December 2024
1. GENERAL INFORMATION.
1.1. Description of Work. The contractor shall provide all personnel, labor, supervision, management, supplies, tools, equipment, parts, materials, transportation, shipping & delivery, and all other items and services necessary to abate and remove asbestos containing material (ACM) from the existing construction site located at building 1300, Mountain Home AFB, Idaho. All work shall be accomplished in accordance with this Performance Work Statement (PWS), all applicable federal, state, local laws, regulations, manufacturer’s specifications, and commercial practices.
1.2. Background. There is currently an ongoing construction project to renovate Bldg 1300.
Walls have been removed and opened to expose the Asbestos Containing Material (ACM).
Abatement needed includes 8 ea 10’ HVAC pipes that can be cut and removed. Also, a 10’ water insulated water pipe needs insulation removed from the pipe, the pipe must remain in place. Stick framed walls were removed and left approximately 60’ x 4” residual VCT needing abatement. Hiding beneath a layer of sheet vinyl we discovered 192 sq ft of ceramic tile that also needs abatement. Attachment 1 shows the testing report and a floor plan of the area in renovation.
1.3. Contract Changes/Additional Work. At future dates, the government reserves the right to incorporate, add, remove, and/or modify quantities of work within the scope of this requirement.
At times, due to the nature of work, it may be necessary to modify this requirement on an as-needed basis. Additionally, there may be a need for ‘one-time’ requirements or special sub-contracting opportunities in order to fulfill the requirement needs. Any future changes to this requirement will be negotiated and incorporated in the contact via contract modification, whether by negotiation, or based on priced line items currently incorporated within the contract.
1.4. Hours of Operation. The contractor shall be available between Monday through Friday 7:00 am to 4:30 pm (local) time (MST). These are the “normal” hours of operation. Weekends or holidays shall not be counted as a business day.
1.4.1. Holidays. The contractor shall not be required to provide normal services/work during federal holidays. Federal holidays are defined as follows:
New Year’s Day Juneteenth Veteran’s Day Martin Luther King’s Birthday Independence Day (July 4th) Thanksgiving Day President’s Day Labor Day Christmas Day Memorial Day Columbus Day
NOTE: Holidays occurring on Saturday will be observed the preceding Friday. Those occurring on Sunday will be observed the following Monday
2. REQUIREMENTS. The contractor shall abate/remove all Asbestos Containing Material (ACM) located in Building 1300: (Reference/See pictures attached). All work shall be performed in accordance with 40 CFR Part 61 – National Emission Standards for Hazardous Air Pollutants, Subpart M – National Emission Standard for Asbestos.
PERIOD OF PERFORMANCE (PoP): All work shall be completed within / Not Later Than Thirty (30) Days from the date of contract award.
2.1. CERAMIC FLOOR TILE REMOVAL. The contractor will remove 192 sq. ft. of ceramic floor tile and all grout/underlayment/mortar to the concrete base floor. There is a layer of sheet vinyl/ linoleum flooring covering the tiles, which will also require disposal.
2.2. Vinyl Composition Tile (VCT). The contractor will remove 60 linear feet of residual Vinyl Composition Tile (VCT). Removal shall include the mastic and glue to the concrete flooring.
2.3. HVAC PIPE REMOVAL. The contractor will remove eight (8) each 10 ft HVAC pipes and remove the insulation from One (1) 10 ft water pipe. Totaling 90 LF of pipe insulation. The government shall remove all wall coverings to expose all pipes requiring abatement.
2.4. AIR SAMPLE/TESTING. Upon completion of abatement, the contractor shall have a third-party testing firm to provide Clearance Air Sampling. The firm shall provide a report to the government upon completion.
2.5. Permits & Notifications. The Contractor shall identify and obtain all required permits/notifications per 40 CFR Part 61 – National Emission Standards for Hazardous Air Pollutants, Subpart M – National Emission Standard for Asbestos for demolition and renovation prior to conducting any work on Mountain Home AFB.
The Contractor shall provide a copy of all regulatory notifications to the Government in accordance with federal, state, and local regulations. All regulatory notifications shall be provided at least 10-Days prior to commencement of work activities.
Typically, regulatory notifications must be provided for the following (this listing is not all-inclusive): demolition, renovation, NPDES defined site work, construction, removal or use of a permitted air emissions source, and remediation of controlled substances (asbestos, hazardous waste, lead paint).
The contractor shall provide Disposal Documentation for Hazardous and Regulated Waste/waste manifests.
3. SURVEILLANCE & QUALITY ASSURANCE.
3.1. SERVICE SUMMARY
3.2. Quality Control. The contractor shall employ their commercial quality control program and procedures to identify, prevent, and ensure non-recurrence of defective services. Through implementation of the contractor’s quality control program/procedures, the Government shall receive quality services meeting the requirements of this contract. All quality control records shall be kept and made available to the Government throughout the contract performance period and for the period after contract completion until final settlement of any claims under this contract.
3.3. Quality Assurance. The Government may use various quality assurance methods to determine the contractor’s compliance with the PWS and the contract requirements in accordance with FAR Clause 52.212-4, Contract Terms and Conditions – Commercial Items (a) Inspection/Acceptance.
3.4. Re-Performance of Non-Conforming Work. Upon inspection of work, any work found to not be in accordance with this PWS/contract shall be re-performed by the contractor at no additional cost to the government.
4. CONTRACT ADMINISTRATION. During performance under contract, the contractor shall participate in administrative tasks inherent to the administration, surveillance, and oversight of contract performance.
4.1. Contract Employees. All contract personnel must be able to read, write, speak, and understand English fluently. Contract personnel shall present a neat appearance and be easily identified as a contract employee. The contractor shall obtain base identification and vehicle passes for all employees who make frequent visits to, or perform work on Mountain Home AFB in accordance with the current installation access/entry requirements. Contractor personnel are required to wear or prominently display installation identification while visiting or performing work on the installation. The contractor shall not employ persons for work on this contract identified to the contractor by the CO as a potential threat to the health, safety, security, general well-being, or operational mission of the installation and its population. Each employee will be easily identified by wearing distinctive clothing bearing the name of the company or by wearing appropriate badges that contain the company name and employee name(s). The contractor shall not employ any person who is an employee of the Government, if employing that person would create a conflict of interest. The contractor is cautioned that off-duty active military personnel hired under this contract may be subject to permanent change of station, change in duty hours, or deployment. Military Reservists and National Guard members may be subject to recall to active duty. The abrupt absence of these personnel could adversely affect the service provider’s ability to perform; however, their absence at any time shall not constitute an excuse for non-performance under this contract.
4.2. Interferences. The contractor shall not unduly interfere with regular scheduled government operational activities in the performance of contract requirements. In the event a government supervisor so requests, the contractor shall temporarily cease work in the area and report the issue, to include the name of the government personnel involved to Contracting Officer immediately. The contractor shall notify the Contracting Officer verbally of disputes with customers or other base contractors and follow-up in writing.
4.3. Records Management. The contractor shall create, handle, and maintain records for the Air Force, regardless of medium, in accordance with the requirements established in AFRIMS Records Disposition Schedule (RDS), AFI 33-322, Records Manage Program, AFI 33-364, Records Disposition Procedures and Responsibilities, and AFM 33-363, Management of
Records. Full text versions of these publications are available for free download at http://www.e-publishing.af.mil. Inquiries as to the specific actions necessary to meet the requirements established in the above referenced publication may be directed to the Mountain Home Records Management Office at 366 CS/SCOKR, Bldg. 512, Mountain Home AFB, ID, 83648.
5.0. ENVIRONMENTAL CONTROLS.
5.1. Hazardous Material Inventory and Safety Data Sheets(SDS). SDS are required as specified in the latest version of Federal Standard No. 313 for all potentially hazardous materials. SDSs must be submitted by the Contractor upon contract award to the Hazardous Materials Program Manager (366 FW/A7IE) at 208-828-1684/6351 for a determination of whether or not a product is a HAZMAT and what additional requirements may be applicable/necessary. Approval is required before bringing any hazardous materials (HAZMAT) onto the installation. The government (HAZMART personnel) will inventory all chemicals that the Contractor brings on to Mountain Home AFB or any property under the control of Mountain Home AFB. Any products that meet the criteria of “Hazardous Waste” must be bar coded and tracked until permanently removed from government property. The inventory will be performed prior to commencement of work. Criteria for identifying hazardous waste, is contained in Subpart C of 40 CFR, Part 261.
5.2. Material Storage and Use. The contractor shall follow manufacturer's guidelines and professional recommendations for control of humidity, temperature, cleanliness, and materials handling. This includes hazardous materials.
5.3. Notification of Environmental Spills. If a spill occurs, the person discovering the spill will make every effort to stop the product flow (if possible), warn personnel, shut off ignition sources, contain the spill, make notifications, and begin cleanup. If the spill is considered an emergency and there is a potential life, health, fire, or other safety hazard, the MHAFB Fire Department will be notified IMMEDIATELY. Responsible units/activities will clean up small spills safety and within their capabilities to do so. Generally, a spill of only a few gallons will recovered by the responsible unit/activity using absorbent materials or a spill kit located by the site. Recovered product and contaminated materials will be packaged and staged for disposal in accordance with the installations hazardous waste procedures. Contact the Environmental Office (208-828-6351) for guidance. The liability for the spill or release of such substances rests solely with the contractor and its agent.
5.4. Waste. Identify, label, handle, store, and dispose of hazardous waste or debris in accordance with federal, state, and local regulations. Ensure all waste has undergone the appropriate hazardous waste determination and documentation is retained for these determinations. If hazardous wastes are generated the contractor will be required to setup and maintain a hazardous waste accumulation point. All hazardous waste generated must be disposed of at a RCRA permitted treatment storage or disposal facility. Do not dispose of hazardous waste on Government property. Do not discharge any waste to a sanitary sewer, storm drain, or to surface waters or conduct waste treatment or disposal on Government property without written approval of the Contracting Officer and Environmental. Consult with the Hazardous Waste Program Manager (366 FW/A7IE) at 208-828-1684/6351 prior to disposal of any waste.
5.5. Historic Preservation. MHAFB houses numerous historic properties (buildings, structures, objects, archaeological sites) managed in compliance with the National Historic Preservation Act (NHPA), and its implementing regulations at 36 CFR 800. In order to avoid inadvertent adverse effects to historic properties, coordination with 366FW A7IE Cultural Resources Manager, Ms.
Noelle Shaver (828-8003/6351) is required prior to implementation.
6. SECURITY, OPSEC, & ANTITERRORISM. The contractor shall comply with all requirements and procedures IAW AF FAR 5353.242-9000, Contractor Access to Air Force Installations included herein. All contract employees shall carry contractor photo identification at all times. Contractor employees shall comply with any base security measures implemented at all times. This includes, but is not limited to, vehicle and goods searches and identification checks during times of increased security.
6.1. Operations Security: The contractor shall comply with 366 FW OPSEC requirements and countermeasures to protect critical information as defined in AFI 10-701, Operations Security.
Contractors shall receive unit-specific OPSEC training within 90 days of assignment to a contract. Training documentation must be completed by the respective unit OPSEC coordinator.
The unit OPSEC personnel will provide guidance on protecting critical information, training materials and other instructions as needed. The contractor will comply with the 366 FW OPSEC Policy that imposes a 100% shred requirement of all government related paper products using NSA approved devices only.
6.2. Installation /Base Access. The contractor shall comply with all MHAFB Installation /Base access procedures, to include all required security/background checks, and submission of SF 30 Base access request forms for each employee.
Picture 1 – Sample picture of vinyl tile to be removed.
Picture 2 – The “Red Line” on wall is marked with 2-pipes behind the wall. The ceramic tile is under linoleum flooring.
Picture 3 – Picture of 4- HVAC pipes in walls flooring to be removed.
Picture 4 – grey insulated Pipe in wall needs to be removed. The government will remove the sheetrock to expose the full pipe.