Attach 1 05. SOW Backup Generator Replacement.pdf
PDF 25 KB Posted
- Attached to
- Backup Generator Replacement WAPA DSW
- Solicitation number
- 89503120QWA000116
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attach 19 Day Tank10.jpg | JPG image | |
| Attach 17 Day Tank8.jpg | JPG image | |
| Questions Set 2.pdf | ||
| Attach 16 Day Tank7.jpg | JPG image | |
| Attach 18 Day Tank9.jpg | JPG image | |
| Attach 15 NEW SOW Backup Generator Replacement 18 May Revision.pdf | ||
| Questions Set 1.pdf | ||
| Attach 12 phs_3328.pdf | ||
| Attach 14 Gen_ATS Location.pdf | ||
| Attach 13 phs_3326.pdf | ||
| Attach 11 pic with dimensions.jpg | JPG image | |
| 17. Amd_0001 Sol_89503120QWA000116_.pdf | ||
| Attach 10 Drawing of generator building.pdf | ||
| 17. Sol_89503120QWA000116.pdf | ||
| Attach 5 05. Gen 7.jpg | JPG image | |
| Attach 7 05. Gen 15.jpg | JPG image | |
| Attach 3 05. Gen 1.jpg | JPG image | |
| Attach 2 05. Annotation 2020-04-21 145922.jpg | JPG image | |
| Attach 8 05. Gen 16.jpg | JPG image | |
| Attach 6 05. Gen 9.jpg | JPG image | |
| Attach 4 05. Gen 2.jpg | JPG image |
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIFICATIONS
FOR
PURCHASE AND INSTALL OF
BACKUP GENERATOR SYSTEM
United States Department of Energy Western Area Power Administration
Desert Southwest Region, Phoenix Office
615 South 43rd Avenue Phoenix, Arizona 85009
REQUIRED SCOPE OF WORK
WAPA DSW Phoenix Office Emergency Backup Generator
BACKGROUND
This project is for the replacement of the emergency backup generator (rated capacity of 500kW at 480V), 24V Float Battery Charger, GE Zenith 800 amp 3 pole bypass Transfer Switch and a 100 gallon Day Tank at the DSW Phoenix Office campus. In Dec 2020, the existing generator will be 30 years old and will be at the end of its expected lifecycle. This increases the chances that the unit will fail during an emergency when power has been lost. This generator powers DSW’s critical infrastructure however, it does not have the capacity to power the entire facility. The unit KW capability should be increased to handle the entire facilities load as to not interfere with their operation.
WORK LOCATION
The Desert Southwest Regional Office is located at 615 South 43rd Avenue, Phoenix, Arizona.
WAPA'S STANDARD SPECIFICATIONS AND DRAWINGS
WAPA uses Standard Specifications and Drawings, which are requirements for this specific contract. WAPA's Standards give details on material requirements and acceptable methods of installation. The Project Specifications and Drawings take precedence over the Standard Specifications and Drawings if a conflict exists.
WAPA's POINTS OF CONTACT WAPA's Facilities Manager is:
Chad Johnson G1070, Western Area Power Administration P.O. Box 6457, Phoenix, AZ 85005-6457 Phone: (602) 605-2637
ACCESS AND RESTRICTIONS
WAPA’s normal hours are Monday through Friday from 7:00 AM to 4:00 PM. Coordinate with the COR to work outside the normal work hours. Due to security at the site, access to the site shall also be coordinated with the COR. There are several Burrowing Owl habitats located on the property. Burrowing Owls are endangered species and care must be taken to avoid these sites during project.
USE OF LAND FOR CONSTRUCTION PURPOSES
Government land, controlled by Western, may be used for field offices, storage yards, shops and other facilities if such use will not interfere with work of other contractors or of the Government.
The COR’s approval shall be obtained prior to use of government land.
UTILITIES
1. Electric Power for Project Purposes:
Electric power is available up to 2-KVA for construction purposes and will be available without cost. Source of supply is receptacles located in the Building. Power made available by WAPA will be delivered as single phase 60 Hz, alternating current at approximately 120 volts.
2. Telephone Service for Project Purposes:
The Contractor shall furnish his own telephone and electronic communications means.
3. Water for Project Purposes:
Potable and non-potable water is available at the site. The Contractor shall coordinate water usage with the COR.
SAFETY
1.In performing the work required by this contract, the Contractor shall comply with all applicable Federal, State, or local safety, health, or industrial safety codes including the latest effective standards promulgated by the Secretary of Labor for the Department of Labor and Health Administration, Safety and Health Standards (29 CFR 1910) and the Construction Safety and Health regulations promulgated under Section 107 of the Contract Work Hours and Safety Standards Act (29 CFR 1926). If there is a conflict between the requirements of the applicable Federal, State, or local safety, health, or industrial safety codes, the more stringent requirements shall prevail. The United States is liable only for negligence on the part of its employees in accordance with the Federal Government Claims Act, as amended.
2. Prior to commencing work, an onsite safety meeting shall be held with Western’s representative to address and discuss safety procedures related to the work required, and to discuss potential hazards and their mitigation. Additionally, WAPA has the right to remove any Contractor employee that does not adhere to safety requirements.
SUBMITTALS
1. Provide and submit manufacturers’ product data, and warranties for all Contractor furnished material. The contractor shall follow all of WAPA Specifications.
a. The contractor shall submit the following submittals:
i. Schedule
ii. Safety Plan
iii. Electrical
iv. Fall Protection
2. Send all transmittals to the COR. Include Contractor’s or supplier’s title and WAPA’s specifications number and title, submittals may either be sent by mail or electronic to the address listed below:
Facility Manager Attn: G1070 P.O. Box 6457 Phoenix, AZ 85005-6457 Email- cajohnson@wapa.gov
3. WAPA’s Review: Except as otherwise provided for specific submittals, WAPA will require 10 calendar days for review of drawings or data submitted for approval. This review time will apply to each separate submittal or re-submittal whether drawings or data are approved, not approved, or returned for revision.
SCOPE
1. Project Planning
a. Preparation of a detailed project plan and timeline with WAPA
2. Decommissioning and Removal of Existing Emergency Standby Generator, 24V Float Battery Charger, GE Zenith Automatic Transfer Switch and 100 gallon Day Tank:
a. Disconnect, removal and disposal of:
mailto:cajohnson@wapa.gov
i. Existing feed;
ii. Existing generator piping and associated supports;
iii. Existing standby generator, Cummins Onan Model 500DFFB 39478F, 3 phase 480V 500 KVW, Onan 24V Battery Float Charger Model 305-081301, GE Zenith Automatic Transfer Switch Model Entelli-Switch 250 and Tramont 100 gal Day Tank Model System 2000 plus ECM;
iv. Existing vertical exhaust
b. Contractor is responsible for proper disposal of all chemical waste, including, all fluids and lubricants (i.e. all petroleum products, antifreeze, coolant, etc.).
c. Contractor is responsible for coordinating, planning and sourcing a lift/crane for removal of existing generator unit. The roof of the generator building is removable, once generator is removed the roof must be reinstalled and must be tested to ensure its functionality.
d. Contractor is to provide temporary backup power while removing and installing new backup generator.
3. Temporary Back-Up Power
a. Facility must stay in operation at all times;
b. Provide the emergency backup power while transitioning from the existing generator configuration to the new generator
4. Installation of New Electrical Set-up
a. Furnish and install emergency shunt trip push button station;
b. Route new feeds to existing automatic transfer switch
5. Acquisition, Installation and Testing of New Emergency Standby Generator
a. Acquire and deliver a new 500 KVW standby emergency generator and ancillary equipment, to include a 24V Float Battery Charger, GE Zenith Transfer Switch and 100 gallon Day Tank;
b. New equipment must meet or exceed the capabilities of the existing equipment;
b. Setup and connect the new generator to WAPA’s electrical network;
c. Conduct testing and acceptance testing of the new generator
6. Coordination with Operations / Working Hours
a. All work shall be performed between the hours of 7:00 a.m. and 4:00 p.m., Monday through Friday; however, when given prior approval by the COR (at least 48 hours prior to commencing work).
b. No routine or scheduled work is to be performed on weekends or U.S. Federal Holidays.