This solicitation requests proposals to replace metal siding on Building 4 and optional buildings at the Northern Great Plains Research Laboratory in Mandan, North Dakota. The Department of Agriculture Agricultural Research Service Field Research Implementation and Information Delivery Plains Area seeks a contractor to remove and dispose of existing metal siding and install new metal siding on the specified buildings. Proposals are due by April 15, 2023. The period of performance is 120 calendar days from award. The contractor will furnish all labor, materials, equipment, tools, supervision and incidentals to complete the work in accordance with the performance work statement.

View the file

Other files

File Type Posted
12805B23Q0650 RFQ rev 1.pdf PDF
12805B23Q0650 RFQ.pdf PDF
Attach 04 Fill In Biobased Statement Letter.docx DOCX document
Attach 03 Schedule Fillable.xlsx XLSX spreadsheet
Attach 02 Wage Determination.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

United States Department of Agriculture Agricultural Research Service

REPLACE METAL SIDING ON BUILDING #4 PERFORMANCE WORK

STATEMENT WITH ADD OPTION BUILDINGS #9, 10, 11, 12A, 12B, 12C, 4F, 5F, &

7F.

USDA, ARS, PA, Northern Great Plains Agricultural Research Laboratory

(NGPRL)

1701 10th Avenue SW Mandan, ND.

DATE: 6/26/2023

STATEMENT OF WORK

TABLE OF CONTENTS

1.0 Project Information

2.0 Project Contact Persons

3.0 Scope of Services

4.0 Technical Project Requirements

5.0 Background and Site Description

6.0 Technical Cost Proposal

7.0 Special Requirements

8.0 Performance Schedule

9.0 Government Furnished Equipment

10.0 General Requirements

11.0 Warranties

12.0 JPG’s and Approximate measurements

1.0 Project Information:

A. Project Number: TBD

B. Project Title: REPLACE METAL SIDING ON BUILDING 4.

WITH ADD OPTIONAL BUILDINGS #9, 10, 11, 12A, 12B, 12C,

4F, 5F, & 7F.

C. Project Location:

USDA, ARS, PA, Northern Great Plains Agricultural Research Laboratory

1701 10th Ave SW.

Mandan, ND 58554

2.0 Project Contact Persons:

A. MBA, FAC-C LEVEL III

Josh Keadle – Section Head PA Phone: 970-492-7003 2150 Centre Avenue, Building D.

Fort Collins, CO 80526 Email: joshua.keadle@usda.gov

B. ENGINEERING PROJECT MANAGER (EPM):

Mark McWilliams USDA, ARS, WBSC Phone: 970-631-7513 2150 Centre Avenue, Building D, Suite 300 Fort Collins, CO 80526 Email: mark.mcwilliams@usda.gov

C. RESEARCH PROGRAM REPRESENTATIVES (RPR):

David Archer Phone: 701-667-3048 USDA, ARS, PA, NGPRL Email: david.archer@usda.gov Northern Great Plains Agricultural Research Laboratory

D. LOCATION ADMINISTRATIVE OFFICER (LAO):

Jeremy Will Phone: 701-667-3014 USDA, ARS, PA, NGPRL Email: jeremy.will@usda.gov Northern Great Plains Agricultural Research Laboratory

E. LOCATION MONITOR (LM):

Mike Eberle Phone: 701-667-3075 USDA, ARS, PA, NGPRL Email: michael.eberle@usda.gov Northern Great Plains Agricultural Research Laboratory

F. COLLATERAL DUTY SAFETY OFFICER (CDSO):

Holly Johnson Phone: 701-667-3003 USDA, ARS, PA, NGPRL Email: holly.johnson@usda.gov Northern Great Plains Agricultural Research Laboratory

3.0 Scope of services:

mailto:mark.mcwilliams@usda.gov

The Contractor shall provide all professional services necessary for the accomplishment of each project and such required services shall be in accordance with requirements as described herein.

A. The Contractor shall provide services for the following tasks marked by an

“X”:

[X] Provide a cost proposal and a technical proposal to complete the project as per project requirements.

[X] Provide a cost proposal for each building listed separately for budgeting purposes.

[X] The contractor shall furnish all the skilled labor, materials, equipment, tools, transportation, and supervision necessary to remove and replace the old siding, soffits, fasciae, and metal wrapped doors and replace it with new, Rollex, Double 5” Dutchlap horizontal 28 gauge (minimum) steel galvanized siding that is a deep embossed design normally designated as wood grain that is white in color(Snowmist). Siding design and color approval is required before installation as shown in these documents.

4.0 Technical Project Requirements:

The Contractor will work with site personnel to ensure each task is accomplished in a timely manner.

A. The Contractor’s work shall adhere to the criteria stated within these project requirements, drawings, and specifications. All construction shall comply with applicable federal, state, and local code requirements as well as current industry standards, (i.e.: EPA, ASTM, GSA, AASHTO, etc.) and health and safety codes, in effect at the time of contract award.

B. All work to meet all pertinent Unified Facilities Guide Specifications (UFGS) and ARS 242.1M standards. UFGS available at http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs.

ARS 242.1M available at https://www.afm.ars.usda.gov/ppweb/pps-and-manuals/.

5.0 Background & Site Description:

A. Existing building #4 is approximately 96ft x 86ft x 15ft side walls.

B. Existing Gable ends are approximately 32ft to the peak. 36ft wide x 16’ in height.

C. Existing overhead and service doors will remain. The contractor must trim with new metal wrap to match the new color-snowmist. The contractor will provide and install new overhead door moldings and weatherstripping for all the doors. The one existing wooden loft door must be custom metal wrapped color matched to the new siding and weatherstripping installed.

D. Existing windows will remain but the trim around the windows must be replaced with new j-channel.

http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs https://www.afm.ars.usda.gov/ppweb/pps-and-manuals/ https://www.afm.ars.usda.gov/ppweb/pps-and-manuals/

E. Existing penetrations will be trimmed out with new color matched trim metal.

F. The contractor will replace all vents and venting in all the buildings with new venting color matched and approved by the COR. The contractor shall provide and install all venting required.

G. Additional detail notes listed below in specific requirements for all buildings.

H. Attached within these documents are jpg. Photos of building #4 and add optional buildings with approximate dimensions.

I. A site visit is strongly recommended: Contact Mike Eberle 701-527- 1524 or Scott Jensen at 701-805-1222

6.0 Technical Cost Proposal: Base Bid for this contract and add options separately.

7.0 Specific Requirements

A. Siding Improvements

1. Remove and dispose of existing metal siding, wood siding, fascia, soffits, J-channel, trim metal, and metal wrap. It will be replaced with new matching siding, fascia, soffits, J-channel, trim metal, and metal wrap.

2. It is the Contractor’s responsibility to inspect all sheeting, fasciae boards, and surfaces for defects and/or rotted wood. Any defects, rot, or damage shall be replaced and restored to new condition at the Contractors cost.

3. The contractor shall ensure that all surfaces are flat, smooth, free from nails, and any other imperfections that would hamper the installation of the new siding, soffits, and fasciae. As stated, it is the responsibility of the contractor to replace such defects to the satisfaction of the COR.

4. The contractor shall use a TYVEK wrap insulation on all exterior surfaces and seal according to the manufacturer’s specifications.

5. The contractor will provide all the labor, materials, and incidental work as required to remove the old materials and replace it with new.

6. All materials shall be new, unused, and free from defect and of American Manufacturer. Where manufacturer’s products are specified, approved equal products of another manufacturer’s may be accepted according to CO approval.

B. Materials

1. Steel siding shall be: Rollex Double 5” Dutch lap siding and shall have a deep embossed design normally designated as wood grain.

Materials shall be 28-guage steel galvanized. Panel lengths shall be furnished in lengths that are a minimum of 12ft. in length.

2. Accessories shall be Rollex color matched to the new siding. J-channels, flashing strips, sill trim, continuous internal corner pieces, backer plates, individual outside corners, and all other necessary accessories.

3. Soffits and Fasciae: The contractor shall provide new preformed, Rollex Steel fasciae, and aluminum soffit. Soffit shall be center vented. Soffit and fasciae shall be screwed and not nailed.

4. All service doors, overhead garage doors, and windows shall be wrapped with new coil stock wrap, that is matched to the color and type of the new siding.

C. Caulking, Weather-stripping, and ventilation

1. All caulking required shall be an exterior high-grade elastomeric 100 percent silicone for maximum flexibility and adhesion. Sealant shall be applied where required as specified by manufacturer’s written instructions and according to industry standards and practices.

2. All service and overhead garage doors shall have new color matched weather-stripping installed by the contractor.

3. Ventilation must be provided to comply with the specifications for minimum property structures for moisture condensation.

D. Penetrations, conduit, gas lines, vents

1. Any penetrations, conduit, gas lines, vents, or other obstructions will be sided according to industry standards and to the satisfaction of the

COR.

2. Any old vents shall be replaced with new vents that are color matched to the new siding with COR approval.

3. This includes penetrations for lights, speakers, pipes, other boxes.

E. Gutters, material storage, and clean up

1. Any gutters and downspouts on the buildings need to be removed and reinstalled after work is completed to the satisfaction of the COR. Any damage to the gutters and downspouts will be replaced with new at the Contractors cost.

2. Materials must be stored off the ground with suitable covers to keep them from getting damaged. They must be stored in a location approved by the COR.

3. The contractor shall keep all the premises clean of garbage, debris, materials, nails, old siding, soffit, fasciae, etc., during the performance of work period. The debris/garbage shall be removed from the site weekly or when the COR deems it appropriate. All materials must be removed from the premises and taken to the appropriate recycle location.

4. At the completion of the project the contractor shall remove all materials from around the buildings and shall use whatever means to recover any metal, nails, screws, and any other debris to the satisfaction of the COR.

5. Any deficiencies shall be corrected before the work is deemed complete.

8.0 Performance Schedule: When weather is appropriate, project should be completed 120 days after Notice to Proceed or sooner.

9.0 Government Furnished Equipment\Services

A. None provided.

10.0 General Requirements:

A. Permits: Where governing regulations and imposed codes and standards require notices, permits, licenses, inspections, tests, and similar items or actions in order to lawfully proceed with the required work, the Design Contractor shall obtain items and take those actions in accordance with the regulations of the governing authority. The costs of construction permits, licenses, inspections, etc., are the obligation of the future Construction Contractor.

B. Schedules shall be updated and furnished with each submittal.

C. Submittals shall be made as scheduled in the Special Requirements section. Each submittal shall be distributed electronically in Adobe for review, to the Location Monitor at the facility, Engineering Project Manager, and Contracting Officer. Each submittal shall contain the previous submittal's Excel comment sheet with responses, notes of meetings held with ARS personnel, design notes, calculations, and construction progress bi-weekly meetings during construction.

D. Changes in the scope of work or the task order that affect the level of effort of the Contractor must be pre-approved by the CO.

E. Disputes or questions that arise after the task order has been negotiated will be resolved by the CO.

F. Contractor shall provide proper protection for the walls, windows, doors siding, exterior and surrounding buildings against damage from falling materials while removal of siding, fascia, soffit and any other materials.

Any damage to the building that occurs during the removal or replacement siding will be the responsibility of the contractor to repair and return to original order to the approval of the COR.

It is the responsibility of the contractor to ensure that the building is covered and protected against the weather elements to prevent leakage and interior damage that could result from different weather factors. Any interior damage that results is the liability of the contractor and must be replaced in-order to return to original condition with the approval of the

COR.

Contractor shall assume all liabilities and responsibilities for the proper and appropriate tools, equipment, and rigging required to account for the working height and steep pitches of some of the buildings. The contractor assumes the liabilities and responsibilities for the personal safety of his workers and ensures that they have the appropriate safety equipment to complete the job. All precautions must be taken to protect all persons and property from injury or damage during the performance of this work. The contractor shall assume all liabilities and responsibilities for the storage of their tools and any equipment at the jobsite.

11.0 Warranties:

A.

Warranty on product and workmanship shall be for 35 years from the date of the of installation. Please provide the supplier’s address, phone numbers’ and internet information the manufacturer’s order number.

Lifetime Warranty A Limited and Transferable Warranty ROLLEX Corporation Navigator Steel Building Products Warranty Registration Certificate Certificate No. ASBP Coverage Rollex Corporation (“Rollex”), subject to the limitations and conditions set forth below, warrants to the original homeowner that Rollex’s Navigator steel building products are free from manufacturing defects and when used as intended under conditions of ordinary wear and weathering will not peel, chip, crack, split, flake or blister or have manufacturing defects which cause deterioration of the steel substrate due to rust.

Rollex warrants that, for a period of thirty-five years from the original date of installation, Rollex’s Navigator steel building products will not (a) fade or change color in excess of 5 color difference units when measured in accordance with A.S.T.M. D2244-68 or (b) chalk in excess of a numerical rating of 8 when measured in accordance with A.S.T.M. D4214-07. This warranty does not cover non-uniform color changes resulting from unequal exposure to sunlight. If a covered product fails to perform in accordance with the above standards, after written notification and validation of the condition by inspection, Rollex will repair or replace at its option, any defective product, assuming 100% of the cost (subject to the allocations applicable to second and institutional homeowners as set forth in the last section of this warranty). In the event of damage caused by hail during the warranty period, it is the homeowner’s responsibility to first pursue the costs related to replacement or repair of the damaged material through the homeowner’s insurance coverage, or other applicable insurance coverage. Should the homeowner incur costs that exceed such insurance coverage (excluding any insurance deductible), Rollex will reimburse the homeowner for any hail-damaged material cost incurred in excess of the available insurance coverage. Rollex will not be responsible for the cost of labor required to install the new siding which replaces any hail-damaged material. In no case will Rollex’s cost exceed the value of the replacement material required to replace the hail-damaged material. All warranty claims shall be settled between the homeowner and Rollex. Rollex may direct and pay a contractor to perform any remedial work under this warranty. If any corrective work on or replacement of warranted products is performed by the homeowner or anyone engaged by homeowner prior to receiving written permission to do so from Rollex, such action will be at homeowner’s expense and will void homeowner’s coverage under this warranty. Rollex’s liability for a claim under this warranty shall in no event exceed the homeowner’s original purchase price —including labor and taxes —for the product involved. It shall be the homeowner’s obligation to provide reasonable documentation and/or other evidence of such original costs.

Duration 1 Original Owner: This warranty is in effect for the lifetime of the original homeowner so long as such original homeowner continues to own the home where the Rollex Navigator products have been installed.

2. Second Owner: This warranty can be transferred by the original owner to whom it is issued to the next owner of the property provided this warranty is still in effect at the time of such transfer. Upon completion of the transfer, (a) the warranty period shall be limited to 50 years from the date of installation of the Rollex Navigator products and (b) Rollex and the second homeowner shall share the cost of repair or replacement of any defective Rollex Navigator products, including labor and materials, in accordance with the below section entitled “Allocation of Warranty Costs When Applicable.”

3. Institutional Owner: For an owner such as a corporation, partnership, group, governmental agency, association, or other organization capable of enduring for generations, (a) this warranty is limited to a period of 50 years from the original date of installation of the Rollex Navigator products and (b) Rollex and the institutional homeowner shall share the cost of repair or replacement of any defective Rollex Navigator products, including labor and materials, in accordance with the below section entitled “Allocation of Warranty Costs When Applicable.”

Warranty Registration The registration card should be completed by the Rollex building products dealer, signed by the original homeowner and mailed to Rollex within 30 days after installation has been completed. Failure to register within the 30-day period set forth above will not void the warranty, but registration will confirm the date of purchase and will assist Rollex in processing any warranty claim that might arise in the future. This confirmation is a benefit to the homeowner in case original proof of purchase cannot be found. If registration has not been completed by the original homeowner or if Rollex has not received timely written notification of the transfer of this warranty to a second homeowner, the burden will be on the homeowner asserting the claim to provide adequate documentation to clearly establish its right to make a claim under this warranty.

Exclusions and Limitations This warranty does not cover damage resulting from any of the following: faulty installation (including but not limited to waving and/or buckling caused by improper installation); “oil canning” (perceived waviness in the flat areas of metal siding panels), fire, lightning, hurricane, tornado, cyclone, wind storm, storm, earthquake or other acts of God; accidental damage or vandalism; impact of foreign objects; structural settlement, cracking, shrinkage or distortion; lap abrasion; harmful chemicals, pesticides, fumes or vapors; direct contact with and water run-off from dissimilar metals or other materials (e.g., metals such as copper, zinc and steel, or other materials such as concrete, blacktop, stucco, asbestos siding, pressure treated or pre-treated lumber, roofing materials or roofing systems containing metallic granules or strips, or other corrosive non-metallic materials); damage resulting from painting, varnishing, coating or otherwise altering the surface of the products except in strict accordance with Rollex’s instructions or guidelines; distortion or warping caused by excessive heat sources such as window reflection, skylights, outdoor grills and other items which can cause products to distort or change color due to excessive heat buildup; surface deterioration due to air pollution and airborne stains; misuse or abuse; normal weathering; acid rain;

salt spray directly applied or in the atmosphere; mildew accumulation; homeowner’s failure to provide normal cleaning and maintenance of the product; and/or other causes beyond the control of Rollex. Rollex Navigator products are not intended for and this warranty will not apply to products that are used or installed (a) on any structure built within one mile of any body of saltwater or (b) on any motor, modular, mobile or transportable structure.

This is the homeowner’s exclusive warranty and is in lieu of all other warranties, express or implied, except as may be required by applicable law. Without limiting the generality of the foregoing, Rollex shall not be liable for any breach of any other written or oral warranties given to the homeowner by any third party(ies) such as those (if any) given to the homeowner by dealers, contractors, applicators or distributors of the products.

ROLLEX IS NOT LIABLE FOR INCIDENTAL, SPECIAL OR

CONSEQUENTIAL DAMAGES FOR THE PRODUCTS COVERED BY THIS

WARRANTY. REPAIR OR REPLACEMENT IS THE EXCLUSIVE REMEDY

AVAILABLE UNDER THIS WARRANTY.

Rollex reserves the right to discontinue or make changes in any of its products. If the products covered by this warranty are not available, Rollex has the right to substitute a product of equal or greater quality or value as determined by Rollex in its reasonable judgment. Rollex does not hereby undertake to repair or replace non-defective Rollex Navigator products. Rather, Rollex may elect to repair or replace only the particular portion(s) of such Rollex Navigator products that is/are defective and/or excessively faded (as per the terms of this warranty) and Rollex cannot and does not guarantee an exact color match with regard to the replacement product(s) as compared to the adjacent non-replaced products. Color variance may occur between replacement products in comparison with the original products due to normal weathering and aging of the original products, and this is not indicative of a defect in either the replacement products or the original products. This warranty gives you specific legal rights;

you may also have other rights which may vary from state to state. Pertinent state law shall also control for what period of time following the sale a homeowner/consumer may seek a remedy under the implied warranty of merchantability or fitness for a particular purpose. Some states do not allow the exclusion or limitation of incidental or consequential damages so the above limitation or exclusion may not apply to you.

Claims Procedure A claim under this warranty must be presented in writing within 30 days following the discovery of any warranted defects to Rollex Corporation, 800 Chase Ave, Elk Grove Village, Illinois 60007 Attention: Warranty Service Department. The claim should be accompanied by a copy of this warranty certificate, and a description of the defect.

Ultimate determination of the existence and extent of any claimed manufacturing defect hereunder shall be made by Rollex in its sole discretion. As noted above, corrective work on warranted products may not be started prior to receiving permission to do so from Rollex, and Rollex reserves the right to perform such corrective work itself or through others retained by it. The homeowner shall cooperate with Rollex and its contractors in connection with the scheduling and performance of any corrective or replacement work hereunder. In the case of second and institutional owners, after five years of the warranty period have elapsed, a claim under this warranty must be accompanied by a $50 payment to Rollex. Checks should be made payable to Rollex Corporation and mailed to the above address.

Warranty Transfer This warranty may be transferred from the original homeowner to whom it was issued to the next homeowner of the property provided Rollex receives written notice within 30 days of the date of the transfer. Notice must include the original homeowner’s name as shown on the warranty certificate, the name of the new homeowner, the warranty certificate registration number and the date the Rollex Navigator products were installed on the property. Any further attempted transfer of this warranty by a second or subsequent homeowner is prohibited and will be null, void and of no force or effect.

Upon transfer of the property to a second homeowner, to the extent this warranty is still in effect, the warranty period shall be limited to 50 years from the date of original installation.

Rollex and the new homeowner shall share in the cost of repair or replacement of any defective product, including labor and materials as described below.

Allocation of Warranty Cost When Applicable For second and institutional owners the cost, including labor and materials, to repair or replace defective products shall be allocated between the homeowner and Rollex according to the following schedule: Rollex will assume 100% of such costs for validated claims made during the first five years of the warranty period.

During the sixth year, Rollex’s share of such cost will be 90%, and the homeowner’s share will be 10%.

Each year thereafter, through the thirteenth year, Rollex’s share of such costs will cumulatively decrease from 90% by 10% per year. Starting with the fourteenth year of the warranty period, and for the balance of the warranty period, Rollex’s share will be 10% and the homeowner’s share will be 90% of such costs.

Effective Only for Rollex Navigator products Purchased on or after January 1, 1 Determination of color changes and chalking will be made by comparing an unexposed panel to an exposed panel after removal of foreign surface deposits, dirt and chalk. Color changes are determined in Delta E Units. Numerical chalk erosion ratings are determined by standard methods of evaluating degree of chalking.

Issued To:

NAME OF TITLE HOLDER(S) OF PROPERTY ON DATE OF

INSTALLATION

ADDRESS OF PROPERTY WHERE PRODUCTS HAVE BEEN

INSTALLED

CITY STATE ZIP DATE OF COMPLETED INSTALLATION

This is to certify that on , 20 the Rollex Navigator Steel Siding Building Products checked below were installed on the property at CITY STATE ZIP STREET owned by , said ROLLEX products purchased from or installed by DEALER NAME at Warranty registration is hereby made for the following Rollex products. _ Navigator Steel Siding AUTHORIZED DEALER SIGNATURE SIGNATURE OF OWNER To be valid this registration certificate must be filled out completely and signed by the owner and dealer and mailed to Rollex Corporation within thirty (30) days from the date of installation.

12.0 Approximate Building Measurements: Building# 4

Eave height: 15ft. Apex: 32ft.

Service doors 4 Overhead doors: 3 Windows: 7 Length x Width: 96L x 84W

North view

South view

East view

South-East view

West view

12.0 Approximate Building Measurements: Building# 9

Eave height: 10ft. Apex: 19ft.

Service doors 2 Overhead doors: 7 Windows: 9 Length x Width: 134L x 24W

North View

South View

East View

West View

12.0 Approximate Building Measurements: Building# 10

Eave height: 14ft. Apex: 25ft.

Service doors 2 Overhead doors: 0 Windows: 10 Length x Width: 52L x 30W

12.0 Approximate Building Measurements: Building# 11

Eave height: 7ft. Apex: 16ft.

Service doors 1 Overhead doors: 3 Windows: 1 Length x Width: 44L x 32W

12.0 Approximate Building Measurements: Building# 12A

Eave height: 8ft. Apex: 11ft.

Service doors 1 Overhead doors: 0 Windows: 3 Length x Width: 18L x 12W

12.0 Approximate Building Measurements: Building# 12B

Eave height: 8ft. Apex: 14ft.

Windows: 2 Length x Width: 16L x 14W

12.0 Approximate Building Measurements: Building# 12C

Eave height: 8ft. Apex: 9ft.

Windows: 0 Length x Width: 10L x 7W

12.0 Approximate Building Measurements: Building# 4F

Eave height: 8ft. Apex: 12ft.

Service doors 0 Overhead doors: 0 Windows: 0 Length x Width: 40L x 20W

12.0 Approximate Building Measurements: Building# 5F

Eave height: 8ft. Apex: 10ft.

Windows: 0 Length x Width: 10L x 10W

12.0 Approximate Building Measurements: Building# 7F

Eave height: 8ft. Apex: 14ft.

Service doors 2 Overhead doors: 2 Windows: 4 Length x Width: 40L x 39W

United States Department of Agriculture
Agricultural Research Service

File details come from the government source that posted it. Updated .