ATT G E-Qaps.pdf

PDF 169 KB Posted

Attached to
1. 8J United Kingdom Purchase Program Federal contract opportunity
Solicitation number
SPE605-21-R-0204
Issued by
Defense Logistics Agency Energy

View the file

Other files for this federal contract opportunity

Other files attached to 1. 8J United Kingdom Purchase Program, newest first.
File Type Posted
ATT F - Kerosene CQAP.pdf PDF
ATT C - Requesting The OET Vendor Role.pdf PDF
ATT B - BRP and Escalators.pdf PDF
RFP SPE605-21-R-0204.pdf PDF
ATT F - Gasoline CQAP.pdf PDF
ATT F - Diesel CQAP.pdf PDF
ATT E - AMPS Role Guide.pdf PDF
ATT D - PCS OET Vendor Guide.pdf PDF
ATT A - Schedule B.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ENERGY QAP E1 CONTRACTOR INSPECTION RESPONSIBILITIES (SEP 2013)

(a) This contract provision applies to:

(1) All aviation fuel, lubricating oil, and additive shipments.

(2) All Bulk and Posts, Camps, and Stations non-aviation fuel shipments via pipeline or waterborne transport.

(b) QUALITY CONTROL PLAN.

(1) The Contractor is required to provide and maintain an inspection system, and a written description (Quality Control Plan (QCP)) of that system, acceptable to the Government. The Contractor has the option to provide and maintain an inspection system that, as a minimum, incorporates the requirements of ISO9001, Quality Management Systems. If the Contractor chooses to comply with the ISO9001 quality system requirements and format, all the specific Quality Assurance Provisions of this contract must be included in the resulting ISO9001 document that will serve as the QCP. A copy of the QCP, in English, shall be presented to the Government Quality Assurance Representative (QAR) for their review and acceptance prior to commencement of production or services. An acceptable QCP is required prior to Government inspection and acceptance of supplies or services. The QCP shall be reviewed and updated when deemed necessary by the Contractor or the Government, to include changes necessary to prevent the recurrence of quality problems. The Contractor must sign and date the original QCP, as well as each subsequent revision. Revisions shall also be presented to the QAR for review and acceptance prior to implementation. When acceptable to the Government, the original QCP, and any revisions, shall be signed and dated by the QAR.

(2) The Contractor shall require subcontractors to provide and maintain inspection systems adhere to all the requirements in this contract provision.

(3) The QCP shall include the identification of key operational positions, a schematic diagram of plant facilities pertinent to the inspection system, indicating all inspection points, and a description of the following operations related to the supplies or services to be furnished under the contract:

(i) RECEIVING, BLENDING AND COMPOUNDING. Procedures used to ensure the quality of additives blended into product supplied under this contract. Procedures to identify and ensure the quality of component base stocks used to produce finished product. Procedures to be used for adding, prior to batching, all required additives at all locations. When procedures for in-line blending of non-aviation products in accordance with the IN-LINE BLENDING OF NON- AVIATION PETROLEUM PRODUCTS contract provision are used, the QCP will provide for establishing blend ratios, and identify the responsible personnel within the Contractor's organization authorized to establish the blend ratios. When line injection of additives is required by the contract, the QCP will provide procedures for proportionately injecting additives throughout the entire loading process to ensure the additive is homogeneously blended into the product, as well as procedures for maintaining records evidencing the homogeneous blending of all line injected additives. In addition to the testing in (iii) below, a laboratory hand blend of jet fuel with all additives required by the contract shall be tested, prior to shipment, to verify compliance with the specification;

(ii) SAMPLING. Procedures for sampling additives, blend tanks, shipping tanks, lines, and conveyances/containers in accordance with API Manual of Petroleum Measurement Standards (MPMS), Chapter 8, Section 1, (ASTM D 4057) Manual Sampling of Petroleum and Petroleum Products, and/or Section 2, (ASTM D 4177) Automatic Sampling of Liquid Petroleum and Petroleum Products. Procedures include sample location, frequency, quantity, and retention. For all tanker, barge, and pipeline shipments, a flow-proportional sample taken in accordance with MPMS Chapter 8, Section 2, is preferred at the custody transfer point. However, manual samples taken in accordance with MPMS Chapter 8, Section 1 are acceptable provided that they are taken hourly throughout the shipment and that the quantity of the composite sample meets the requirements in Table II of this contract provision. See Table I, Minimum Sampling and Testing Requirements, and Table II, Sample Retention;

(iii) TESTING. Types of test series and individual test methods/procedures to be performed on samples taken from each location identified in (ii) above. See Table I, Minimum Sampling and Testing Requirements, and Table III, Definitions of Test Series; (iv) CALIBRATION. Program for testing and measuring equipment in accordance with ISO 10012, Measurement Management Systems - Requirements for Measurement Processes and Measuring Equipment, or equivalent local regulation, as appropriate; and, a program for meters used to determine quantity complying with the API MPMS, Chapters 4, 5, and 6, or equivalent foreign standard. For items not covered by API, ASTM, or IP publications, the applicable manufacturer's recommended calibration method(s), outlined in the applicable industry publication, shall be used if acceptable to the Government;

(v) STORAGE AND HANDLING. Procedures for quality/quantity determination. Includes a description of storage and handling equipment, such as tanks, lines, valves, and manifolds; identification of dedicated/common product systems, including description of line segregation and controls to assure capability for proper gauging, sampling, draining of water, filtration, circulation, and drying; and identification of any other process/system used in maintaining product integrity during storage and handling;

(vi) LOADING AND SHIPPING - GENERAL. Procedures for product movement and related quality/quantity checks from shipping tank(s) to custody transfer point (CTP). Description of transfer system from shipping tank to CTP. A dedicated system, including lines, pumps, loading arms, and hoses, is preferred, but an isolated common system incorporating blind flanges, spectacle plates, or double valves between systems is acceptable. An isolated common system using single valves designed to ensure positive isolation, such as twin seal single valves, are also acceptable. Systems with single valve (other than twin seal) isolation require specific procedures be included in the QCP to ensure product integrity prior to the CTP. When single valves (other than twin seal) are present in the system, the Contractor shall provide their quality control procedures, from the first single valve to the CTP, at time of bid to the Contracting Officer for a determination of acceptability. Procedures for conditioning and testing of isolated systems that last carried a product other than that intended for movement under this contract. For in-line blending of non-aviation products, where approved in this contract, requirements must comply with the IN-LINE BLENDING OF NONAVIATION PETROLEUM PRODUCTS contract provision.

(vii) LOADING AND SHIPPING - TANK CARS, TANK TRUCKS, AND INTERMODAL CONTAINERS. For direct deliveries using Contractor-supplied tank cars and tank trucks in dedicated same grade aviation fuel service, refer to the section of API 1595 entitled “Loading of Road/Rail Cars” for loading and shipping procedures. All other tank car, tank truck, and intermodal container loadings shall be in accordance with the following procedures: Confirm all compartments have been prepared in accordance with Table IV, Conversion Chart for Tank Cars, Tank Trucks, and Intermodal Containers, below. Whenever possible, ensure the same preparation procedures used for compartments are applied to hoses, manifolds, etc. Ensure that conveyances carrying lubricating oil are dry and free from loose rust, scale, and dirt. Provide for investigation of discrepancies in either recorded quality or quantity. When required by the contract, seal conveyance and record seal numbers on the shipping document. Strainers and filters shall be located as near the loading or filling point as practicable and shall be used as outlined below for all deliveries except deliveries into tanker, barge, or pipeline.

(A) All aviation fuel shall be passed through strainers of 60 mesh or finer screen;

(B) All lubricating oil products, including preservatives, having a kinematic viscosity of 20.0 centistokes or less at 100 degrees Fahrenheit shall be passed through a 100 mesh or finer screen;

(C) All lubricating oil products, including preservatives, having a kinematic viscosity greater than 20.0 centistokes at 100 degrees Fahrenheit, but less than 22.0 centistokes at 210 degrees Fahrenheit, shall be passed through a 60 mesh or finer screen; and

(D) The Contractor shall furnish and periodically inspect strainers and filters pursuant to this paragraph to determine condition and perform maintenance as necessary, keeping a written record thereof.

(viii) LOADING AND SHIPPING - TANKERS AND BARGES.

(A) For f.o.b. destination Contractor-supplied tankers/barges. Procedures for the preparation of vessel cargo systems, in accordance with Energy Institute (EI) HM 50, Guidelines for the Cleaning of Tanks and Lines for Marine Tank Vessels Carrying Petroleum and Refined Products, that ensure the vessel is suitable to load the intended product(s).Particular attention should be given to vessels that previously carried a Fatty Acid Methyl Ester (FAME) cargo.

As a minimum, f.o.b. destination Contractors must ensure that all cargo systems on the vessel intended for loading product under this contract, to include tanks, lines, manifolds, and pumps, are washed, gas freed, and inspected. In the event a solvent de-greaser is utilized in the tank preparation process, a minimum of two rinses must be performed by the vessel prior to loading Aviation Turbine Fuel. Vessels that will be carrying JP8 will be allowed to load without cleaning based upon the following criteria: the last cargo prior to loading JP-8 is Jet A/A1, and the second and third to last cargoes were clean middle distillate or lighter petroleum products (no black oils, lubricating oils, vegetable oils, palm oils, biodiesel with FAME content greater than or equal to 15 % or other similar products). The vessel will drop all lines and strip dry all cargo tanks of the previously carried Jet A/Jet A1 prior to loading JP-8. These procedures, and others deemed necessary by the Contractor, shall be included to ensure that the product meets the specification requirements at the CTP.

(B) For f.o.b. origin Government-supplied tankers/barges. Procedures for maintaining a time log of all significant events/delays including vessel notice of readiness, vessel arrival, mooring, vessel deballasting, inerting and conditioning of cargo tanks, inspections, hose connections and disconnections, starts, stops, vessel release, or any other event that affects laytime of the vessel. Procedures for assuring condition of loading line (full of tested product, all air bled, and pressure packed) and gauging shore tanks, both before and after loading. In the event an automated metering system is to be used as the means of shore quantity determination, manual gauges of all storage tanks designated for shipment shall be taken prior to commencement of loading. Procedures for preload discussion between Contractor, vessel, and QAR to include, but not be limited to, prior two cargoes, cleaning procedures, loading plan, loading rates, sampling requirements, and after loading sampling and gauging. [Prior to loading - gauge, sample, and test in transit cargoes designated for load on top. Gauge and sample (1 gallon) any other product on board, except for JPTS, and retain those samples.] All cargo quantities shall be calculated and volume corrected both before and after loading. Procedures for commencement of loading into one tank (up to 3 feet), then switching to at most two other vessel tanks while first-in sampling and testing is being accomplished (Table I). Procedures for the transportation of samples from the vessel to the testing facility.

Monitoring the loading (including line blending and additive injection) from source to vessel, investigating irregularities immediately and stopping loading, if necessary. Procedures for investigating discrepancies in quality (mandated if off-specification or out of testing tolerance) and quantity (mandated if shore to ship variance is in excess of the following:

0.2% (0.002) for cargos not requiring cleaning, gas freeing, or drop/strip; 0.3% (0.003) for cargos requiring drop/strip; or 0.5% (0.005) for cargos requiring cleaning and gas freeing, or figures are suspect) on loaded conveyance.

(C) For both f.o.b. origin and destination tankers/barges. Procedures for immediately notifying the QAR when irregularities occur or are suspected, and on all occasions when loading is interrupted. Authority to release a Government-furnished vessel rests with the Government QAR after compliance and completion by the Contractor of all required operations, including the preparation of the DD Form 250-1.

(ix) RECORDS AND REPORTS. Procedures for completing and distributing required documentation both prior to and after the release of the vessel. Documentation shall include, as a minimum, test reports for all products and additives, additive blending and/or injection records, vessel notice of readiness, customs documents, bills of lading, vessel ullage reports, and the DD Form 250/DD Form 250- 1 and continuation sheet(s) (or the Paperless Ordering and Receipt Transaction System [PORTS] or equivalent). Other documentation maybe required on an as needed basis, such as vessel port logs, calibration records, and results of quality or quantity discrepancy investigations. These records and reports will include by whom, where, and how they were prepared, as well as retention information. The DD Form 250- 1 and DD Form 250-1 continuation sheet(s) will be signed by the Contractor and the vessel representative in the appropriate blocks before presenting them to the QAR for signature. The DD Form 250 and DD Form 250-1 shall identify the type, brand name, and amount of all additive(s).

(x) CORRECTIVE ACTION. Actions to be followed to effect correction of any deficiency affecting product quality or quantity, such as handling of off-specification product (waivers, conveyance rejections, etc.). The corrective action procedures shall include notification of the QAR.

(4) The QCP shall identify one individual to serve as a point of contact for quality/quantity matters relating to the inspection system description in the plan.

(5) The Contractor is responsible for all inspection systems, QCPs, and product quality and quantity.

(c) The Contractor shall perform all inspections and acceptance tests required by the specifications of the supplies to be furnished under this contract or, shall have such tests performed, in a laboratory acceptable to the Government. For f.o.b.

destination Contractor-supplied tankers/barges, the Contractor shall provide the QAR, prior to the first shipment, with the name and location of the laboratory to be used for testing at each discharge point. The Contractor shall also notify the QAR of any subsequent laboratory changes prior to the affected shipments. If any laboratory is determined to be unacceptable to the Government, the Contractor must designate another laboratory that is acceptable, before acceptance testing can take place. Acceptance tests will normally be performed at the acceptance point. However, when such tests are performed at origin on supplies to be accepted at destination, documentation that will enable verification of the original test results shall be provided to the Government prior to acceptance at destination. Regardless of the method of delivery, products furnished under this contract must meet all specification requirements at the CTP.

(d) Prior to loading, the Contractor shall inspect all shipping conveyances for suitability to load the supplies furnished under this contract, except for Government-furnished tankers and barges Authorization for the Contractor to participate in the inspection of Government-supplied tankers and barges rests with QAR. The QAR has the right to inspect any Government-supplied conveyance prior to loading and, in the event the Contractor and the QAR disagree on the suitability to load such a conveyance, the determination of the QAR shall govern. If the SHIPMENT AND ROUTING contract provision is included in the contract, Government-furnished transportation equipment that is unsatisfactory for loading shall be reported by the Contractor in accordance with the provisions contained in that contract provision.

Procedures to determine suitability to load tank trucks and tank cars shall include, but not be limited to, visual inspection of interior compartments to assure cleanliness and dryness. Manifolds and hoses must be drained and be clean and dry for the intended product. If the Contractor intends to witness operations at any point up to, and including, government acceptance, the Contractor is responsible for contacting the facilities to be visited and obtaining the required access.

(e) When requested by the U.S. Government, the Contractor shall furnish no more than five (ten in the case of jet fuel) 1-gallon samples of liquid product from any individual batch or lot of the supplies to be furnished under this contract. Such samples shall be furnished without charge to the Government and shall be packed, marked, and shipped by the Contractor, at their expense.

(f) The Contractor shall keep all quality and quantity records related to the performance of this contract complete and available to the Government during the performance of this contract and for three years after final payment under this contract. These records shall include, but not be limited to, DD Form 250-series documents, documentation of internal inspections of all conveyances, laboratory certificates for all required testing (including those for the shipping tanks for f.o.b. destination tankers/barges), and documentation of quantity determinations.

(g) When a common system is to be used for shipment in accordance with paragraph (a)(3)(vi) above, the Contractor shall provide a list of all products carried by that system during the past year to the Contracting Officer, at the time of offer, for a determination of acceptability.

(h) The inspection system and related operations provided or performed pursuant to this provision shall be subject to surveillance by the QAR.

(i) The contractor may provide transportation to/from/between contractor facilities and operations to the QAR or DLA Energy representative performing official duties relating to the administration of the contract and the contract price shall include the cost of any such transportation.

ENERGY QAP E4 INSPECTION (DLA ENERGY DEC 2011)

(a) This QAP only applies to PC&S deliveries by tanker or barge.

(b) INSPECTION. When Government inspection is required, it will be performed by the Quality Representative assigned responsibility over the location where loading takes place. In order that such inspection can be accomplished, the Contractor will provide the responsible Inspection Office, upon receipt of an order, with the following information, at least 5 days prior to shipment for domestic items and at least 14 days prior to shipment for overseas items:

(1) Contract number, line item number, and order number;

(2) Nomenclature and specification of product;

(3) Date and time of shipment;

(4) Name and location of facility where loading will take place;

(5) Identity of conveyance and consignee; and

(6) Quantity to be shipped.

NOTE: For overseas shipments, more than 14 days notice may be required for some locations. If so, the responsible inspection office shall notify the Contractor, in writing, how much notice is required at such locations, and the Contractor shall provide that notice for the duration of the contract.

(c) INSPECTION OFFICES. The name and location of the responsible Inspection Office(s) will be furnished to successful offerors. A specific office may be designated for each loading location or a list of inspection offices and their areas of responsibility may be provided.

ENERGY QAP E12 (JUL 2015) POINT OF ACCEPTANCE

(a) For f.o.b. origin contract items, acceptance of the supplies furnished hereunder shall take place at origin.

(b) For f.o.b. destination contract items, acceptance of the supplies furnished hereunder shall take place at destination.

(c) Acceptance shall take place as stated above, unless specifically stated otherwise in the contract.

ENERGY QAP E18.01 SAMPLE SUBMISSION (DLA ENERGY AUG 2009)

The Contractor shall furnish hereunder, from time to time, samples of each product or grade of product to be furnished under this contract at the request of, and in the manner and to the place designated by, the Quality Representative;

PROVIDED, however, that in no event shall the Contractor be required to furnish during the period of this contract more than five 1-gallon samples under each contract line item. Such samples shall be furnished without charge to the Government and shall be packed, marked, and shipped by the Contractor, shipping expense prepaid, in containers and shipping boxes furnished by the Contractor.

ENERGY QAP E21.01 (JUN 2015) POINT OF INSPECTION

(a) This Energy QAP applies to the Bulk Fuel, Bulk FSII, Bulk Lube Oil and Posts, Camps, and Stations Programs.

(b) When government inspection is deemed necessary, it shall be performed, prior to acceptance, by the office specified in the LIST OF INSPECTION OFFICES FOR DLA ENERGY CONTRACTS or the QUALITY REPRESENTATIVE Energy QAP of this contract, whichever is applicable.

(1) For f.o.b. origin contract items, inspection will normally be performed at origin, however, the Government reserves the right to perform an inspection at any point prior to acceptance.

(2) For f.o.b. destination contract items, inspection will normally be performed at destination, however, the Government reserves the right to perform an inspection at any point prior to acceptance.

(3) For f.o.b. destination contract items for aviation fuels delivered via waterborne transport, pipeline, rail car, tank truck, tank wagon and Bulk Fuel Container (BFC) and non-aviation fuels delivered by waterborne transport, a preliminary inspection for product quality will normally be performed at origin, with final inspection normally being at destination.

However, the Government reserves the right to perform an inspection at any point prior to acceptance.

(4) On contract items for delivery of drummed or packaged products, f.o.b. origin or f.o.b. destination, a preliminary inspection for product quality will normally be performed at the point of manufacturing or blending, with final inspection normally being at the f.o.b. point. However, the Government reserves the right to perform an inspection at any point prior to acceptance.

(c) When the Contractor is informed by the responsible Inspection Office that government inspection is deemed necessary, the Contractor shall ensure that the Inspection Office is provided with sufficient information and advance notification to facilitate such inspection. When government inspection is necessary at a contractor or subcontractor (commercial or government) facility, the Contractor shall notify the Inspection Office of the necessary requirements to access those facilities and shall help facilitate such access. After initial notification, the Contractor shall keep the Inspection Office informed of any changes that may affect that inspection.

ENERGY QAP E22 LIST OF INSPECTION OFFICES FOR DLA ENERGY CONTRACTS (DLA ENERGY

APR 2016)

The following lists shall be used to identify the Government inspection office assigned inspection responsibility for DLA Energy contracts in a particular geographic area. These contracts include, but are not limited to, those for bulk petroleum products and additives, into-plane refueling, petroleum storage and laboratory services, coal, aerospace energy (including compressed gases), and posts, camps, and stations. The area of inspection responsibility and corresponding office code are assigned in paragraphs (a) and (b). The address and phone number of each inspection office by office code is provided in paragraph (c). Unless a particular inspection office is identified in another part of the contract, the assignments in this contract provision shall apply.

(a) AREAS OF RESPONSIBILITY AND OFFICE CODES WITHIN THE CONTINENTAL UNITED STATES

(CONUS):

Alabama 110 Maine 110 Oklahoma 110 Arizona 120 Maryland 110 Oregon 120 Arkansas 110 Massachusetts 110 Pennsylvania 110 California 120 Michigan 110 Rhode Island 110 Colorado 120 Minnesota 110 South Carolina 110 Connecticut 110 Mississippi 110 South Dakota 110 Delaware 110 Missouri 110 Tennessee 110 District of Columbia 110 Montana 120 Texas 110 Florida 110 Nebraska 110 Utah 120 Georgia 110 Nevada 120 Vermont 110 Idaho 120 New Hampshire 110 Virginia 110 Illinois 110 New Jersey 110 Washington 120 Indiana 110 New Mexico 120 West Virginia 110 Iowa 110 New York 110 Wisconsin 110 Kansas 110 North Carolina 110 Wyoming 120 Kentucky 110 North Dakota 110 Louisiana 110 Ohio 110

EXCEPTIONS:

1 The El Paso, Texas, area is assigned to Code 120 (DLA Energy Americas – West).

2 The Newcastle, Wyoming, area is assigned to Code 110 (DLA Energy Americas – East).

(b) AREAS OF RESPONSIBILITY AND OFFICE CODES OUTSIDE THE CONTINENTAL UNITED

STATES (OCONUS) (INCLUDING ALASKA AND HAWAII):

Afghanistan 400 Cyprus 200 Malaysia 300 Singapore 300

Africa 200 Egypt 400 Maldives 300 South America 110 Alaska 300 Europe (Continental) 200 Malta 200 South Korea 300

Antarctica 300 Georgia 200 Mauritius 200 Sri Lanka 300 Armenia 200 Greenland 200 Mexico 110 Syria 400 Ascension Island 110 Hawaiian Islands 300 Midway Island 300 Taiwan 300 Australia 300 Hong Kong 300 Mongolia 300 Tajikistan 400

Azerbaijan 200 Iceland 200 Myanmar 300 Thailand 300 Azores 200 India 300 Nepal 300 Turkey 200 Bahrain 400 Indonesia 300 New Zealand 300 Turkmenistan 400 Bangladesh 300 Ireland 200 North Korea 300 United Arab Bermuda 110 Iran 400 Oman 400 United Emirates 400 Bhutan 300 Iraq 400 Pacific Islands United Kingdom 200 Brunei 300 Israel 200 (Central & South) 300 Uzbekistan 400 Cambodia 300 Japan 300 Pakistan 400 Vietnam 300 Canada 110/120 Jordan 400 Papua New Guinea 300 Wake Island 300 Canary Island 200 Kazakhstan 400 Philippines 300 Yemen 400 Caribbean Islands 110 Kuwait 400 Qatar 400