This document is a pricing schedule (Attachment J-2) for a federal contract opportunity related to the Air Traffic Organization (ATO) Program Management Organization (PMO) Enterprise Services Directorate (AJM-3) and the Enterprise Services & Fleet Modernization Program. The contract includes a base period from April 1, 2023 to March 31, 2024, with four one-year option periods. The contract pricing is based on time-and-materials/labor hour rates for various labor categories, with an estimated total not-to-exceed amount of $66,581.60 for the base period. The document also includes pricing instructions and details on escalation, fringe, overhead, G&A, and profit factors for the option periods. Other direct costs for travel are estimated at $10,000 per year. The contract opportunity is being solicited under Solicitation Number: UPDATE_NOTICE_{AMA-400-SIR}, with a proposal due date extended to April 25, 2024.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pricing Summary

CONTRACT PRICING

SUPPLIES OR SERVICES PRICES - SCHEDULE B

01 JULY 2024 - 31 JULY 2029 [*15 SEP 2029]

BASE PERIOD

Item No.DescriptionTotal
CLIN
0001 - 0009STRATEGIC PROGRAM MANAGEMENT & ADMINISTRATIVE SUPPORT

TYPE: Time & Material/Labor Hour In accordance with the Statement of Work (SOW), the Contractor must satisfactorily perform all services and technical support requirements as defined in individual Task Orders to the Air Traffic Organization (ATO) Program Management Organization (PMO) Enterprise Services Directorate (AJM-3) and the Enterprise Services & Enterprise Services & Fleet Modernization Program. Services will be purchased at the fully burdened (loaded) hourly labor rate for each labor category as specified in the "Labor Hour Price List" (Section J, Attachment 1).

Period of Performance:

01 APRIL 2023 – 31 MAR 2024BASE YEAR
Estimated Labor CostNTE:$ 16,581.60
CLIN 0001 Total EstimateNTE:$ 16,581.60
CLIN No.DescriptionTotal
CLIN
0010OTHER DIRECT COSTS (ODCs) - TRAVEL SUPPORT

TYPE: Cost

Contractor must perform all travel as required for services and support in accordance with the Statement of Work (SOW), "Enterprise Services & Fleet Modernization Program Management Support Services," Section C.6 (Section J, Att.1).

Period of Performance:

01 APRIL 2023 – 31 MAR 2024BASE YEAR
Estimated CostNTE:$ 10,000.00
CLIN 0002 Total EstimateNTE:$ 10,000.00
BASE YEAR
ESTIMATED TOTALNTE:$ 26,581.60

OPTION YEAR I [12 Months] (2nd Period of Performance)

Item No.DescriptionTotal
CLIN
1001 - 1009STRATEGIC PROGRAM MANAGEMENT & ADMINISTRATIVE SUPPORT

TYPE: Time & Material/Labor Hour

In accordance with the Statement of Work (SOW), the Contractor must satisfactorily perform all services and technical support requirements as defined in individual Task Orders to the Air Traffic Organization (ATO) Program Management Organization (PMO) Enterprise Services Directorate (AJM-3) and the Enterprise Services & Enterprise Services & Fleet Modernization Program. Services will be purchased at the fully burdened (loaded) hourly labor rate for each labor category as specified in the "Labor Hour Price List" (Section J, Attachment 1).

Period of Performance:

01 APRIL 2024 – 31 MAR 2025Estimated Labor CostNTE:$ - 0
CLIN 1001 Total EstimateNTE:$ - 0
CLIN No.DescriptionTotal
CLIN
1010OTHER DIRECT COSTS (ODCs) - TRAVEL SUPPORT

TYPE: Cost

Contractor must perform all travel as required for services and support in accordance with the Statement of Work (SOW), "Enterprise Services & Fleet Modernization Program Management Support Services," Section C.6 (Section J, Att.1).

Period of Performance:

01 APRIL 2024 – 31 MAR 2025Estimated CostNTE:$ 10,000.00
CLIN 1002 Total EstimateNTE:$ 10,000.00
OPT YEAR I
ESTIMATED TOTALNTE:$ 10,000.00

OPTION YEAR II 12 Months (3rd Period of Performance)

Item No.DescriptionTotal
CLIN
2001 - 2009STRATEGIC PROGRAM MANAGEMENT & ADMINISTRATIVE SUPPORT

TYPE: Time & Material/Labor Hour In accordance with the Statement of Work (SOW), the Contractor must satisfactorily perform all services and technical support requirements as defined in individual Task Orders to the Air Traffic Organization (ATO) Program Management Organization (PMO) Enterprise Services Directorate (AJM-3) and the Enterprise Services & Enterprise Services & Fleet Modernization Program. Services will be purchased at the fully burdened (loaded) hourly labor rate for each labor category as specified in the "Labor Hour Price List" (Section J, Attachment 1).

Period of Performance:

01 APRIL 2025 – 31 MAR 2026

Estimated Labor CostNTE:$ - 0
CLIN 2001 Total EstimateNTE:$ - 0
CLIN No.DescriptionTotal
CLIN
2010TRAVEL +SUPPORT

TYPE: Cost Contractor must perform all travel as required for services and support in accordance with the Statement of Work (SOW), "Enterprise Services & Fleet Modernization Program Management Support Services," Section C.6 (Section J, Att.1).

Period of Performance:

01 APRIL 2025 – 31 MAR 2026

Estimated CostNTE:$ 10,000.00
CLIN 2002 Total EstimateNTE:$ 10,000.00
OPT YEAR II
ESTIMATED TOTALNTE:$ 10,000.00

OPTION YEAR III

(4th Performance Period)

Item No.DescriptionTotal
CLIN
3001 - 3009STRATEGIC PROGRAM MANAGEMENT & ADMINISTRATIVE SUPPORT

TYPE: Time & Material/Labor Hour In accordance with the Statement of Work (SOW), the Contractor must satisfactorily perform all services and technical support requirements as defined in individual Task Orders to the Air Traffic Organization (ATO) Program Management Organization (PMO) Enterprise Services Directorate (AJM-3) and the Enterprise Services & Enterprise Services & Fleet Modernization Program. Services will be purchased at the fully burdened (loaded) hourly labor rate for each labor category as specified in the "Labor Hour Price List" (Section J, Attachment 1).

Period of Performance:

01 APRIL 2027 – 31 MAR 2028

Estimated Labor CostNTE:$ - 0
CLIN 4001 Total EstimateNTE:$ - 0
CLIN No.DescriptionTotal
CLIN
3010TRAVEL SUPPORT

TYPE: Cost Contractor must perform all travel as required for services and support in accordance with the Statement of Work (SOW), "Enterprise Services & Fleet Modernization Program Management Support Services," Section C.6 (Section J, Att.1).

Period of Performance:

01 APRIL 2027 – 31 MAR 2028

Estimated CostNTE:$ 10,000.00
CLIN 4002 Total EstimateNTE:$ 10,000.00
OPT YEAR III
ESTIMATED TOTALNTE:$ 10,000.00

OPTION YEAR IV

(5th Performance Period)

Item No.DescriptionTotal
CLIN
4001 - 4009STRATEGIC PROGRAM MANAGEMENT & ADMINISTRATIVE SUPPORT

TYPE: Time & Material/Labor Hour In accordance with the Statement of Work (SOW), the Contractor must satisfactorily perform all services and technical support requirements as defined in individual Task Orders to the Air Traffic Organization (ATO) Program Management Organization (PMO) Enterprise Services Directorate (AJM-3) and the Enterprise Services & Enterprise Services & Fleet Modernization Program. Services will be purchased at the fully burdened (loaded) hourly labor rate for each labor category as specified in the "Labor Hour Price List" (Section J, Attachment 1).

Period of Performance:

01 APRIL 2027 – 31 MAR 2028

Estimated Labor CostNTE:$ - 0
CLIN 4001 Total EstimateNTE:$ - 0
CLIN No.DescriptionTotal
CLIN
4010TRAVEL SUPPORT

TYPE: Cost Contractor must perform all travel as required for services and support in accordance with the Statement of Work (SOW), "Enterprise Services & Fleet Modernization Program Management Support Services," Section C.6 (Section J, Att.1).

Period of Performance:

01 APRIL 2027 – 31 MAR 2028

Estimated CostNTE:$ 10,000.00
CLIN 4002 Total EstimateNTE:$ 10,000.00
OPT YEAR III
ESTIMATED TOTALNTE:$ 10,000.00
TOTAL CONTRACT ESTIMATENTE:$ 66,581.60
Need @ CFO15%$ 9,987.24
$ 76,568.84

BASE PERIOD

INSTRUCTION:

- Please provide a base labor rate at J10 -J21 (The outlying contract years will auto-populate)

- It is not recommended, However, The Offeror may propose a different quantity at Column I 10-21 at each year

- Please update Cells K13, 17, & 18 only if the Wage Determination is different at the Proposal Prep (The CO will adjust during analysis also)

- Please complete Cells L9 -O9 (The outlying contract years will auto-populate)

- Cell J26 is an NTE amount, HOWEVER, the Offeror may make a recommendation (at Column L25) and provide a rationale (at Column M25) The CO will consider the proposed recommendation at the time of evaluation.

- Please complete Rows 40 - 62

Labor Rates - Base Period
BASE Year Period of Performance: 01 JULY 2024 – 31 JULY 2025
TypeCLIN No.Labor CategoryStatus
FT/PTSCA
StatusESAS EquivalentHoursQnty.Direct Labor RatePILBFringeOverheadG&AProfitFully Burdened Labor RateSubTotalTotal
6%3%5%4%
FFP0001[Task 1] Project ManagerExemptProgram Manager18401$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
[Task 2] First Line Supervisor (1)ExemptAcqfBusfFin Mgt Level 218401$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
[Task 2] First Line Supervisor (2)ExemptAcqfBusfFin Mgt Level 218401$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
[Task 1] Administrative AssistantNon-ExmptAcqfBusfFin Mgt Level 318401$ - 0$ 4.41$ - 0$ - 0$ - 0$ - 0$ 4.41$ 8,114.40$ 8,114.40
LABOR/ HOUR0002[Task 3] Full-Time Contract InstructorExemptAcqfBusfFin Mgt Level 2184020$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
0003[Task 3] Part-Time Contract InstructorExemptAcqfBusfFin Mgt Level 396020$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
0004[Task 3] Subject Matter Expert (SME)ExemptSubject Matter Expert18401$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
0005[Task 3] Graphic ArtistNon-ExmptAcqfBusfFin Mgt Level 19601$ - 0$ 4.41$ - 0$ - 0$ - 0$ - 0$ 4.41$ 4,233.60$ 4,233.60
0006[Task 3] Technical Writer IINon-ExmptSubject Matter Expert9601$ - 0$ 4.41$ - 0$ - 0$ - 0$ - 0$ 4.41$ 4,233.60$ 4,233.60
0007[Task 3] eLearning/Web DesignerExemptSubject Matter Expert9601$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
0008[Task 3] Instructional Systems Designer (ISD)ExemptSubject Matter Expert9601$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
0009[Task 4] NAS SIM/Remote Course AdminExemptSubject Matter Expert7501$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Total Estimated Hours for Year 116590Total Labor Cost for Year 1$ 16,581.60
TypeCLIN No.DescriptionTotalOfferor Recommendation
C/R0010OTHER DIRECT COSTS (ODCs) - TRAVEL
BASE YEAR 1
Estimated CostNTE:$ 10,000.00$ - 0
TypeCLIN No.DescriptionTotal
FFP0011DATA NOT SEPARATELY PRICED
BASE YEAR 1
Estimated CostNSP$ - 0
TypeCLIN No.DescriptionTotal
FFP0012TRANSITION (Phase-In)
BASE YEAR 1
Estimated CostNSP$ - 0

Total Estimated Hours for 2nd BASE YR: 16590 Total Labor Cost 2nd BASE YR: $ 26,581.60

SUMMARY [Excerpt from Volume IV] RATIONALE/METHODOLOGY NOTES FOR ALL FACTORS FOR ALL PERFORMANCE PERIODS:
ESCALATION [Effective OPT YR I]

FRINDGE

OVERHEAD

GENERAL & ADMINISTRATIVE (G&A)

PROFIT

Any Factor exceeding 3% requires a rationale for the Risk assessed.

OPT YEAR I

INSTRUCTION:

- Please provide an escalation rate at H4 (The outlying contract years will auto-populate)

- Please complete Cells F11 -I20

- Cell J26 is an NTE amount, HOWEVER, the Offeror may make a recommendation (at Column L25) and provide a rationale (at Column M25) The CO will consider the proposed recommendation at the time of evaluation.

ESCALATION RATE: 2.30%

Labor Rates - OPTION YEAR I

Period of Performance: 01 AUG 2025 – 31 JUL 2026

TypeCLIN No.Labor CategoryStatus
FT/PTSCA
StatusESAS EquivalentHoursQnty.Direct Labor RatePILBFrindgeOverheadG&AProfitFully Burdened Labor RateSubTotalTotal
6%3%5%4%
FFP0001[Task 1] Project Manager0ExemptProgram Manager18401$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
[Task 2] First Line Supervisor (1)0ExemptAcqfBusfFin Mgt Level 218401$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
[Task 2] First Line Supervisor (2)0ExemptAcqfBusfFin Mgt Level 218401$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Administrative Assistant0Non-ExmptAcqfBusfFin Mgt Level 318401$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
LABOR/ HOUR0002[Task 3] Full-Time Contract Instructor0ExemptAcqfBusfFin Mgt Level 2184020$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
0003[Task 3] Part-Time Contract Instructor0ExemptAcqfBusfFin Mgt Level 396020$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
0004[Task 3] Subject Matter Expert (SME)0ExemptSubject Matter Expert18401$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
0005[Task 3] Graphic Artist0Non-ExmptAcqfBusfFin Mgt Level 19201$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
0006[Task 3] Technical Writer0Non-ExmptSubject Matter Expert9201$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
0007[Task 3] eLearning/Web Designer0ExemptSubject Matter Expert9201$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
0008[Task 3] Instructional Systems Designer (ISD)0ExemptSubject Matter Expert9201$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
0009[Task 4] NAS SIM/Remote Course Admin0ExemptSubject Matter Expert9201$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Total Estimated Hours for OPT YR I16600Total Estimated Labor Cost for OPT YR I$ - 0
TypeCLIN No.DescriptionTotalOfferor Recommendation
C/R0010OTHER DIRECT COSTS (ODCs) - TRAVEL
Estimated CostNTE:$ 10,000.00$ - 0
TypeCLIN No.DescriptionTotal
FFP0011DATA NOT SEPARATELY PRICED
Estimated CostNSP$ - 0
TypeCLIN No.DescriptionTotal
FFP0012Estimated CostNSP$ - 0

Total Estimated Hours for OPT YR I: 16600 Total Labor Cost OPT YR I: $ 10,000.00

OPT YEAR II

INSTRUCTION:

- Cell J26 is an NTE amount, HOWEVER, the Offeror may make a recommendation (at Column L25) and provide a rationale (at Column M25) The CO will consider the proposed recommendation at the time of evaluation.

ESCALATION RATE: 2.30%

Labor Rates - OPTION YEAR II
4th Period of Performance: 01 AUG 2026 – 31 JUL 2027
TypeCLIN No.Labor CategoryStatus
FT/PTSCA
StatusESAS EquivalentHoursQnty.Direct Labor RatePILBFrindgeOverheadG&AProfitFully Burdened Labor RateSubTotalTotal
6%3%5%4%
FFP0001[Task 1] Project Manager0ExemptProgram Manager18401$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
[Task 2] First Line Supervisor (1)0ExemptAcqfBusfFin Mgt Level 218401$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
[Task 2] First Line Supervisor (2)0ExemptAcqfBusfFin Mgt Level 218401$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Administrative Assistant0Non-ExmptAcqfBusfFin Mgt Level 318401$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
LABOR/ HOUR0002[Task 3] Full-Time Contract Instructor0ExemptAcqfBusfFin Mgt Level 2184020$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
0003[Task 3] Part-Time Contract Instructor0ExemptAcqfBusfFin Mgt Level 396020$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
0004[Task 3] Subject Matter Expert (SME)0ExemptSubject Matter Expert18401$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
0005[Task 3] Graphic Artist0Non-ExmptAcqfBusfFin Mgt Level 19201$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
0006[Task 3] Technical Writer0Non-ExmptSubject Matter Expert9201$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
0007[Task 3] eLearning/Web Designer0ExemptSubject Matter Expert9201$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
0008[Task 3] Instructional Systems Designer (ISD)0ExemptSubject Matter Expert9201$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
0009[Task 4] NAS SIM/Remote Course Admin0ExemptSubject Matter Expert9201$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Total Estimated Hours for Year 116600Total Estimated Labor Cost for Year II$ - 0
TypeCLIN No.DescriptionTotalOfferor Recommendation
C/R0010OTHER DIRECT COSTS (ODCs) - TRAVEL
Estimated CostNTE:$ 10,000.00$ - 0
TypeCLIN No.DescriptionTotal
FFP0011DATA NOT SEPARATELY PRICED
Estimated CostNSP$ - 0
TypeCLIN No.DescriptionTotal
FFP0012Estimated CostNSP$ - 0

Total Estimated Hours for OPT YR II: 16600 Total Labor Cost OPT YR II: $ 10,000.00

OPT YEAR III

INSTRUCTION:

- Cell J26 is an NTE amount, HOWEVER, the Offeror may make a recommendation (at Column L25) and provide a rationale (at Column M25) The CO will consider the proposed recommendation at the time of evaluation.

ESCALATION RATE: 2.30%

Labor Rates - OPTION YEAR III
5th Period of Performance: 01 AUG 2027 – 31 JUL 2028
TypeCLIN No.Labor CategoryStatus
FT/PTSCA
StatusESAS EquivalentHoursQnty.Direct Labor RatePILBFrindgeOverheadG&AProfitFully Burdened Labor RateSubTotalTotal
6%3%5%4%
FFP3001[Task 1] Project Manager0ExemptProgram Manager18401$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
[Task 2] First Line Supervisor (1)0ExemptAcqfBusfFin Mgt Level 218401$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
[Task 2] First Line Supervisor (2)0ExemptAcqfBusfFin Mgt Level 218401$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Administrative Assistant0Non-ExmptAcqfBusfFin Mgt Level 318401$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
LABOR/ HOUR3002[Task 3] Full-Time Contract Instructor0ExemptAcqfBusfFin Mgt Level 2184020$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
3003[Task 3] Part-Time Contract Instructor0ExemptAcqfBusfFin Mgt Level 396020$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
3004[Task 3] Subject Matter Expert (SME)0ExemptSubject Matter Expert18401$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
3005[Task 3] Graphic Artist0Non-ExmptAcqfBusfFin Mgt Level 19201$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
3006[Task 3] Technical Writer0Non-ExmptSubject Matter Expert9201$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
3007[Task 3] eLearning/Web Designer0ExemptSubject Matter Expert9201$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
3008[Task 3] Instructional Systems Designer (ISD)0ExemptSubject Matter Expert9201$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
3009[Task 4] NAS SIM/Remote Course Admin0ExemptSubject Matter Expert9201$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Total Estimated Hours for Year 116600Total Estimated Labor Cost for Year III$ - 0
TypeCLIN No.DescriptionTotalOfferor Recommendation
C/R3010OTHER DIRECT COSTS (ODCs) - TRAVEL
Estimated CostNTE:$ 10,000.00$ - 0
TypeCLIN No.DescriptionTotal
FFP3011DATA NOT SEPARATELY PRICED
Estimated CostNSP$ - 0
TypeCLIN No.DescriptionTotal
FFP0012TRANSITION (Phase-Out)
Estimated CostNSP$ - 0

Total Estimated Hours for OPT YR III: 16600 Total Labor Cost OPT YR III: $ 10,000.00

OPT YEAR IV

INSTRUCTION:

- Cell J26 is an NTE amount, HOWEVER, the Offeror may make a recommendation (at Column L25) and provide a rationale (at Column M25) The CO will consider the proposed recommendation at the time of evaluation.

- At Cell R38; Provide the estimated additional cost for 15 additional days at Phase-Out

ESCALATION RATE: 2.30%

Labor Rates - OPTION YEAR III
5th Period of Performance: 01 AUG 2028 – 15 SEP 2029
TypeCLIN No.Labor CategoryStatus
FT/PTSCA
StatusESAS EquivalentHoursQnty.Direct Labor RatePILBFrindgeOverheadG&AProfitFully Burdened Labor RateSubTotalSubTotal
6%3%5%4%
FFP4001[Task 1] Project Manager0ExemptProgram Manager18401$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
[Task 2] First Line Supervisor (1)0ExemptAcqfBusfFin Mgt Level 218401$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
[Task 2] First Line Supervisor (2)0ExemptAcqfBusfFin Mgt Level 218401$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Administrative Assistant0Non-ExmptAcqfBusfFin Mgt Level 318401$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
LABOR/ HOUR4002[Task 3] Full-Time Contract Instructor0ExemptAcqfBusfFin Mgt Level 2184020$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
4003[Task 3] Part-Time Contract Instructor0ExemptAcqfBusfFin Mgt Level 396020$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
4004[Task 3] Subject Matter Expert (SME)0ExemptSubject Matter Expert18401$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
4005[Task 3] Graphic Artist0Non-ExmptAcqfBusfFin Mgt Level 19201$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
4006[Task 3] Technical Writer0Non-ExmptSubject Matter Expert9201$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
4007[Task 3] eLearning/Web Designer0ExemptSubject Matter Expert9201$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
4008[Task 3] Instructional Systems Designer (ISD)0ExemptSubject Matter Expert9201$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
4009[Task 4] NAS SIM/Remote Course Admin0ExemptSubject Matter Expert9201$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Total Estimated Hours for Year 116600Total Estimated Labor Cost for Year IV$ - 0
TypeCLIN No.DescriptionTotalOfferor Recommendation
C/R4010OTHER DIRECT COSTS (ODCs) - TRAVEL
Estimated CostNTE:$ 10,000.00$ - 0
TypeCLIN No.DescriptionTotal
FFP3011DATA NOT SEPARATELY PRICED
Estimated CostNSP$ - 0
TypeCLIN No.DescriptionTotal
FFP0012TRANSITION (Phase-Out)
Estimated CostNSP$ - 0

Total Estimated Hours for OPT YR III: 16600 Total Labor Cost OPT YR IV: $ 10,000.00

Estimated Additional Cost @45-Day Transition $ - 0

Total @ 45-Day Transition $ 10,000

Contract Labor Summary

Direct LaborDirect LaborDirect HrsBillableTotalPaidTotal[Task 1] Project ManagerExempt1840195.15122.650253225676.46552
Descriptionfor PeriodRateRevenueRateDirect Cost[Task 2] First Line Supervisor (1)Exempt1840174.696.160892176936.04128
[Task 1] Project Manager9200$ 122.65$ 1,128,380.00$ 48.94$ 450,248.00[Task 2] First Line Supervisor (2)Exempt1840174.696.160892176936.04128
[Task 3] Subject Matter Expert (SME)4600$ 61.73$ 283,958.00$ 40.03$ 184,138.00[Task 1] Administrative AssistantNon-Exmpt1840122.584.4133.516071661669.571744
[Task 3] eLearning/Web Designer5000$ 59.55$ 297,750.00$ 38.61$ 193,050.00[Task 3] Full-Time Contract InstructorExempt18402057.173.603042135429.59728
[Task 3] Instructional Systems Designer (ISD)5000$ 52.59$ 262,950.00$ 34.10$ 170,500.00[Task 3] Part-Time Contract InstructorExempt9602054.6270.406272467590.021504
[Task 4] NAS SIM/Remote Course Admin3750$ 58.24$ 218,400.00$ 37.77$ 141,637.50[Task 3] Subject Matter Expert (SME)Exempt1840154.6270.4062724129547.541216
[Task 3] Graphic ArtistNon-Exmpt960122.624.4133.567632432224.927104
Non-Exempt (PILB)[Task 3] Technical Writer IINon-Exmpt960130.384.4143.570427641827.610496
[Task 1] Administrative Assistant9200$ 38.74$ 356,408.00$ 22.58$ 207,736.00[Task 3] eLearning/Web DesignerExempt960146.960.45503858036.83648
[Task 3] Graphic Artist5000$ 36.14$ 180,700.00$ 20.81$ 104,050.00[Task 3] Instructional Systems Designer (ISD)Exempt96015368.3180665585.3376
[Task 3] Technical Writer5000$ 45.60$ 228,000.00$ 27.24$ 136,200.00[Task 4] NAS SIM/Remote Course AdminExempt750154.369.99378652495.3395

Full-Time Total $ 2,956,546.00 $ 1,587,559.50

Instructors
[Task 3] Full-Time Contract Instructor184000$ 54.72$ 10,068,480.00$ 38.61$ 7,104,240.00
[Task 3] Part-Time Contract Instructor4600$ 49.09$ 225,814.00$ 34.64$ 159,344.00
Part-Time Total$ 10,294,294.00$ 7,263,584.00

Total Direct Labor $ 13,250,840.00 $ 8,851,143.50

PILB HrsPILBTotal
Descriptionfor PeriodRatePILB
PILB19200$ 4.13$ 79,296.00

Total PILB Cost $ 79,296.00

TravelTravelTotalTotal
DescriptionMth EstMthsRevenueDirect Cost
Estimate$ 833.3360$ 50,000.00$ - 0$ 50,000.00
Total Travel$ 50,000.00$ - 0$ 50,000.00

File details come from the government source that posted it. Updated .