US Department of Agriculture (USDA)
Statement of Work
Contents Project General Information
1.0 Scope of Work
2.0 Background
Contractor Requirements
3.0 Technical Requirements / Tasks
4.0 Government Furnished
5.0 Deliverables / Schedule
Attachment
Project White Sulphur Ranger District Electrical Upgrades
General Information
1.0 Scope of Work
The project shall consist of the installation of a total of 27 single gang duplex outlets, and 35 double CAT6 data ports.
There is access to the data rack as well as the electric panel in the utility room. The wires shall be ran in the attic, and drop inside of the walls from there. There are 3 single gang duplex outlets and 3 CAT6 double data ports that shall be fed with surface (wall) mounted wire molding (off white color) dropping from the attic and low-profile surface mounted boxes (off white color), as they are to be mounted on wood paneled walls. There shall also be 8 existing data ports to have an extra CAT6 wire pulled and converted to double ports. The contractor shall supply all materials and labor to install the outlets and complete any incidental work. Installation of conduit, wire, and any other work to electrify the outlets, or provide data to the ports shall be incidental to the installation of the electrical outlets and data ports. All work shall comply with the NEC. Proposed data ports and proposed electrical circuits shall be tested in the presence of the COR.
2.0 Background
The White Sulphur Springs Ranger District Office is in need of additional electrical and data outlet ports to support a growing staff and changing office environments. The desired locations are shown in the attached photos. The building was built in the 1990’s and is in need of an electrical update to meet modern office needs.
Contractor Requirements
3.0 Technical Requirements / Tasks
Contractor shall be a licensed electrician in the state of West Virginia and maintain liability insurance. NFPA 70, NEC, IBC shall supersede any other documentation provided.
4.0 Government Furnished
Government shall furnish access to the facility during regular business hours (M-F 8:00 AM – 4:30 PM), as well as restroom facilities onsite. No work shall be permitted on weekends or on federal holidays without the written permission of the CO. Any government provided property shall be returned prior to payment of the final invoice.
5.0 Deliverables / Schedule
Key Deliverables
Item No. Deliverable Objective Due 1 Electrical Outlets Install 27 single gang duplex electrical outlets 60 Days after notice to proceed 2 CAT6 Double Data
Ports Install 35 CAT6 double data ports 60 Days after notice to proceed
3 CAT6 Wire Pull Pull 8 additional runs of CAT6 and convert single data port to double
60 Days after notice to proceed
Attachment See Photos.
Figure 1: Existing Breaker Panels
Figure 2: Existing Data Rack
Figure 3: Wall to receive surface mounted wire mold and boxes
Figure 4: Space above drop ceiling. Wire conduits ran above shown gypsum board
Figure 5: Space above drop ceiling. Wire conduits ran above shown gypsum board