This solicitation seeks proposals for the digital access and distribution of aeronautical safety of navigation products and services. The United States Air Force Sustainment Center intends to award an indefinite delivery indefinite quantity contract with a two-year base period and three one-year option periods to Jeppesen, a Boeing company, for the provision of aeronautical database access, flight information publications, electronic flight bag services, technical support, other direct costs, travel and per diem, and data not separately priced. Proposals are due by August 31, 2020. The contract will have firm fixed pricing and include standard commercial warranties. Funds are not presently available and no award will be made until funding is secured.

The document includes a pricing matrix template for offerors to provide proposed unit prices on a monthly basis for each contract line item over the base and option periods. Total evaluated price will be automatically calculated. A price model for travel is also included to provide cost breakdowns by purpose, location, number of trips, travelers, and transportation mode.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Instructions

FOR OFFICIAL USE ONLY
Source Selection Information - See FAR 2.101 and 3.104
USAF SoN Pricing Matrix
Attachment 1
Instructions to complete this Pricing Matrix:
1Offerors are to input the proposed unit prices (i.e. per month) on this Pricing Matrix spreadsheet, Column j, in ALL yellow highlighted cells.
2Rounding: All dollar amounts shall be rounded to two decimal places.
3The extended price will be automatically calculated by multiplying the proposed unit price by the required quantity of months.
4A total price will be automatically calculated at the bottom of each year.
5The Total Evaluated Price (TEP), which includes the Base Period and all three options, will automatically calculate at the top of the Pricing Matrix.

Note: Populate the Price Models in the worksheet entitled "Price Model - Travel"

Pricing Matrix United States Air Force Safety of Navigation Solutions - Pricing Matrix

Period of PerformanceTotal Evaluated Price
Estimated Total Price for Base Period (24 Months)$ - 0
Estimated Total Price for Option Period I (12 Months)$ - 0
Estimated Total Price for Option Period II (12 Months)$ - 0
Estimated Total Price for Option Period III (12 Months)$ - 0
Total Evaluated Price TEP = (Base Period + 3 Option Periods
BASE PERIOD 24 MONTHS
CLINCLIN DescriptionQuantity unit of issusProposed AmountTotal Price
Month$PER
0001Aeronautical Database Access24$ - 0
0002Flight Information Publication (FLIP)240
0003Electronic Flight Bag (EFB)240
0004Technical Support240
0005Other Direct Cost (ODC)240
0006Travel & Per Diem240
0007Data NSP24NSPNSP
estmated total price for base period$ - 0
OPTION PERIOD I 12 MONTHS
CLINCLIN DescriptionQuantity unit of issusProposed AmountTotal Price
Month$PER
1001Aeronautical Database Access12$ - 0
1002Flight Information Publication (FLIP)12$ - 0
1003Electronic Flight Bag (EFB)12$ - 0
1004Technical Support12$ - 0
1005Other Direct Cost (ODC)12$ - 0
1006Travel & Per Diem12$ - 0
1007Data NSP12NSPNSP
estmated total price for base period$ - 0
OPTION PERIOD II 12 MONTHS
CLINCLIN DescriptionQuantity unit of issusProposed AmountTotal Price
Month$PER
2001Aeronautical Database Access12$ - 0
2002Flight Information Publication (FLIP)12$ - 0
2003Electronic Flight Bag (EFB)12$ - 0
2004Technical Support12$ - 0
2005Other Direct Cost (ODC)12$ - 0
2006Travel & Per Diem12$ - 0
2007Data NSP12NSPNSP
estmated total price for base period$ - 0
OPTION PERIOD III 12 MONTHS
CLINCLIN DescriptionQuantity unit of issusProposed AmountTotal Price
Month$PER
3001Aeronautical Database Access12$ - 0
3002Flight Information Publication (FLIP)12$ - 0
3003Electronic Flight Bag (EFB)12$ - 0
3004Technical Support12$ - 0
3005Other Direct Cost (ODC)12$ - 0
3006Travel & Per Diem12$ - 0
3007Data NSP12NSPNSP
estmated total price for base period$ - 0

Price Model -Travel

*In the contractor format, provide a breakdown of the proposed travel, to include (at a minimum) the purpose/location of the trip(s), the Number of trips, the number of traveller, the mode
of transportation, and the dollar mount proposed.
* Provide this information for the Base period and all three option period seprately.
* the total travel amounts shown in the model for each period should match the total proposed travel for each year in the Pricing Matrix worksheet (cells, K23, K40, K60, and K79)