This is a Furniture Item Description (FID) document for metal storage furniture at Camp Buckner, Japan SATCOM facility, serving as Attachment #2 to solicitation W912DY-25-Q-0014.

The FID details specifications for three types of industrial storage units: (1) SH5 Industrial Storage Cabinet - 36"W x 24"D x 78-82"H with 4 adjustable steel shelves and 1500 lb minimum shelf capacity; (2) SH3 Open Industrial Storage Shelving - 60"W x 36"D x 84"H with 4 box form shelves; and (3) SH4 Open Industrial Storage Shelving - 36"W x 24"D x 84"H with 5 box form shelves. All units must be knocked-down/flat-packed, constructed of cold-rolled steel with powder coat finish, and include cross braces and floor/wall attachment capabilities. The cabinet requires 14-gauge steel construction with 16-gauge doorframe, while shelving units require heavy beaded or angle post uprights with adjustment capabilities. Notably, 22 other furniture construction requirements sections are marked as "NOT USED," indicating this procurement focuses solely on industrial storage solutions.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Furniture Item Descriptions (FID) Camp Buckner, Japan – SATCOM PN 62783

Attachment #2 Last Update: 2/10/2023 Page 1 of 9

Attachment #2

ADMIN NC

Attachment #2 Last Update: 2/10/2023 Page 2 of 9

TABLE OF CONTENTS PAGE NO.

1.0 GENERAL

1.1 Submittal Requirements

1.1.1 RFQ Response

1.1.2 Non-Conforming RFQ Response

1.2 Submittal and Clarifications Format

1.3 Post Award Submittal

1.4 Contractor General Notes

1.4.1 General

1.4.2 Fabrics & Materials

2.0 Construction Requirements - Panel Supported Workstations - NOT USED

3.0 Construction Requirements - Benching Systems - NOT USED

4.0 Construction Requirements - Console Systems - NOT USED

5.0 Construction Requirements - Demountable Walls - NOT USED

6.0 Construction Requirements - Metal/Laminate Desks - NOT USED

7.0 Construction Requirements - Metal/Laminate Open Frame Technical Workstations -

NOT USED

8.0 Construction Requirements - Metal Furniture: Bookcases - NOT USED

9.0 Construction Requirements - Laminate Tables, Metal Bases - NOT USED

10.0 Construction Requirements - Wood Casegoods, Executive II - NOT USED

11.0 Construction Requirements - Wood Casegoods, Executive III – NOT USED

12.0 Construction Requirements - Wood Conference Tables, Executive II - NOT USED

13.0 Construction Requirements - Wood Conference Tables, Executive III - NOT USED

14.0 Construction Requirements - Laminate Casegoods - NOT USED

15.0 Construction Requirements - Laminate Conference Tables - NOT USED

16.0 Construction Requirements - Ergonomic Task & Conference Seating - NOT USED

17.0 Construction Requirements - Executive Task Seating - NOT USED

18.0 Construction Requirements - Ergonomic Task Stool - NOT USED

19.0 Construction Requirements - Traditional Executive Seating - NOT USED

20.0 Construction Requirements - Seating, Metal Frame, Thermoplastic/Polypropylene-

NOT USED

21.0 Construction Requirements - Seating, Wood Frame - NOT USED

22.0 Construction Requirements - Common Space Furnishings - NOT USED

23.0 Construction Requirements – Industrial Storage Cabinet

23.1 SH5: Industrial Storage Cabinet, Metal

24.0 Ancillary Items

24.1 SH3: Open Industrial Storage Shelving, Metal

24.2 SH4: Open Industrial Storage Shelving, Metal

Attachment #2 Last Update: 2/10/2023 Page 3 of 9

1.0 General

Item descriptions and quality requirements, as described in the FID (Furniture Item Descriptions), are for the quality, functional performance, and design intent of the furnishings required for this project. Products quoted that meet all functional and quality requirements, including all salient features listed in the product descriptions, will be considered responsive provided they are fully compliant with the RFQ requirements.

Compliance shall be determined by performance, features, quality, design intent, and value. Any item descriptions, salient features, or quality requirements listed within this document are not intended to be proprietary.

1.1 Submittal Requirements

All manufacturers shall provide manufacturer’s technical documentation and manufacturer’s construction specifications for each item quoted for verification the proposed products meet all requirements listed in the FID. The RFQ response shall be submitted in the format outlined below. For assistance in preparing the RFQ Response, please contact the contracting specialist to request a .pdf of the How to RFQ Guide.

1.1.1 RFQ Response

RFQ technical responses are the documents which, together with contractual documents (SF18, SF30, Attachment 1 in Excel, Attachment 8), make up an overall RFQ response (the quote). RFQ technical responses shall be clearly organized into (1) Adobe Acrobat (PDF) document. The PDF document shall be searchable, include bookmarks for each item number, and be organized per item number of the FID. Each RFQ is a separate contract activity, and specifications from previous projects will not be retrieved and reviewed. All product specifications and information presented shall be legible.

All technical documentation related to each item number shall be located within the same tab in the RFQ response and shall be submitted in the following order:

1. Product Information Required for Each Item Number:

a. Item number for each product submitted in the RFQ response.

b. Manufacturer, product line, and model number for each item and its components.

c. Overall dimensions.

d. Product image.

e. Fabric and finish options proposed for RFQ that have been priced for each item.

2. Drawings:

a. Provide plan view drawings clearly legible and labeled showing legend of components and dimensions for each freestanding desk and panel-supported workstation, including clusters.

b. Provide elevations or isometrics.

i. Elevations required with stacking/segmented drawings for panel tiles

Attachment #2 Last Update: 2/10/2023 Page 4 of 9

c. Electrical and data shall be on a separate drawing from itemized component drawing. Drawing shall be clearly legible and labeled, identifying all locations of electrical and data/communication outlets.

3. Product Specific Compliance Documentation:

a. Provide published, detailed, technical documentation including, but not limited to, specification guides, and price catalogs to demonstrate compliance with requirements.

b. Highlight, circle, or mark the model, size, type, and any optional features proposed in the RFQ response.

4. Technical Supporting Compliance Documentation:

a. Provide manufacturer’s technical and construction specifications demonstrating compliance to requirements.

b. Documentation shall only be submitted once for multiple items from the same product line.

c. Clearly indicate the item numbers that submitted documentation supports.

5. Testing Documentation:

a. Contractors are NOT required to submit testing documentation with quotes; however, the Contracting Officer reserves the right to request actual copies of test reports at any time before or after award.

6. Environmental Documentation:

a. Contractors are NOT required to submit environmental documentation with quotes; however, the Contracting Officer reserves the right to request actual copies of environmental documentation at any time before or after award.

i. Upon request, contractor shall provide certification for Indoor Air Quality

(GREENGUARD or equivalent).

ii. Upon request, contractor shall provide documentation regarding recycled content and recyclability for all products submitted.

7. Warranty Documentation:

a. Warranty documentation is required to be submitted for seating only.

b. Contractors are NOT required to submit warranty documentation with quotes; however, the Contracting Officer reserves the right to request actual copies of warranties at any time before or after award.

c. Although all other items do not require warranty documentation, the contractor is responsible for providing warranty coverage as required in the FID.

d. Provide any additional or extended warranty that exceeds manufacturer’s standard warranty; extended warranty shall be clearly stated on manufacturer’s letterhead and include a verifiable digital signature containing encryption or handwritten signature, date, and title of the company official accepting technical responsibility.

e. Refer to item descriptions for specific warranty requirements by product type.

1.1.2 Non-Conforming RFQ Response

Submittal of product brochures shall not be acceptable in place of technical documentation or construction specifications. Submittal of a general price list containing large amounts of items not relevant to the procurement is not acceptable. Extended

Attachment #2 Last Update: 2/10/2023 Page 5 of 9 warranties shall not be typed onto the manufacturer’s current warranty. Submittals not in compliance with Section 1.1.1 of the FID shall be considered non-conforming and declined.

1.2 Submittal and Clarifications Format

The RFQ shall be submitted via electronic communications as stated in Section 1.1.1.

The technical supporting documentation shall be submitted in a searchable Adobe Acrobat (PDF) document, organized, and bookmarked by item number of the FID.

Embedded objects, i.e., embedded links, files, and images within clarification responses shall be considered non-conforming.

1.3 Post Award Submittal

Refer to Statement of Work (SOW).

1.4 Contractor General Notes

1.4.1 General

1. All products proposed to be installed within one office, suite, or area shall consist of items of one style and finish. All products shall be free of rough or sharp edges.

Proposed products shall include all components necessary to provide a complete and stable unit. Items shall have consistent quality standards as described and required in the FID.

2. Although such work is not specifically indicated, furnish and install all supplementary or miscellaneous items, appurtenances, and devices incidental to, or necessary for, sound, secure, and complete installation.

3. Awarded contractor is responsible for verifying all existing field conditions i.e., including, but not limited to base-infeed requirements and electrical conditions.

Contractor shall coordinate with power plans.

4. Awarded contractor shall coordinate all furniture locations with all wall mounted equipment including, but not limited to: A/V, televisions, VTC equipment, Visual Communication Boards, etc.

5. Plans provided may not match project requirements in all instances. Follow FID descriptions and configurations and Attachment 1 quantities and locations.

1.4.2 Fabrics & Materials

1. During technical review provide a minimum of (3) selections for each quoted item, unless noted otherwise (UNO). Refer to finish requirements in each item for more specific guidance.

2. Where equivalent finishes have been proposed, bidders shall provide actual samples or color images and specifications for the alternate finish during technical review; Actual samples and specifications for the alternate finish shall be submitted at the post award kickoff, if awarded. The Government retains the right to reject any alternates that are not equal to the required specification.

Attachment #2 Last Update: 2/10/2023 Page 6 of 9

END OF SECTION

Attachment #2 Last Update: 2/10/2023 Page 7 of 9

2.0 Construction Requirements - Panel Supported Workstations - NOT USED

3.0 Construction Requirements - Benching Systems - NOT USED

4.0 Construction Requirements - Console Systems - NOT USED

5.0 Construction Requirements - Demountable Walls - NOT USED

6.0 Construction Requirements - Metal/Laminate Desks - NOT USED

7.0 Construction Requirements - Metal/Laminate Open Frame Technical Workstations

- NOT USED

8.0 Construction Requirements - Metal Furniture: Bookcases - NOT USED

9.0 Construction Requirements - Laminate Tables, Metal Bases - NOT USED

10.0 Construction Requirements - Wood Casegoods, Executive II - NOT USED

11.0 Construction Requirements - Wood Casegoods, Executive III – NOT USED

12.0 Construction Requirements - Wood Conference Tables, Executive II - NOT USED

13.0 Construction Requirements - Wood Conference Tables, Executive III - NOT USED

14.0 Construction Requirements - Laminate Casegoods - NOT USED

15.0 Construction Requirements - Laminate Conference Tables - NOT USED

16.0 Construction Requirements - Ergonomic Task & Conference Seating - NOT USED

17.0 Construction Requirements - Executive Task Seating - NOT USED

18.0 Construction Requirements - Ergonomic Task Stool - NOT USED

19.0 Construction Requirements - Traditional Executive Seating - NOT USED

20.0 Construction Requirements - Seating, Metal Frame, Thermoplastic/Polypropylene-

NOT USED

21.0 Construction Requirements - Seating, Wood Frame - NOT USED

22.0 Construction Requirements - Common Space Furnishings - NOT USED

23.0 Construction Requirements – Industrial Storage Cabinet

Attachment #2 Last Update: 2/10/2023 Page 8 of 9

1. Cabinets shall be constructed of cold rolled steel.

2. Cabinets shall be free of rust and scale. Unit shall be cleaned and pretreated with phosphate to resist rust and corrosion.

3. All exposed edges, corners and surfaces areas shall be smooth formed and free of shape edges.

4. Frames, sills, and headers shall be 16-gauge steel.

5. Doors shall be 21-gauge formed steel, reinforced with full length stiffener, and include knuckle hinges.

6. Hinges shall be welded to frames and riveted to the door.

7. Top, sides and back shall be a minimum of 22-gauge formed steel.

23.1 SH5: Industrial Storage Cabinet, Metal

Dimensions: 36”W x 24”D x 78-82”H

General Requirements:

a. Knocked down or pieces shall ship flat and not fully assembled, 14-gauge steel construction

b. 16-Gauge doorframe construction with knuckle hinges

c. (4) Adjustable steel shelves with fixed bottom shelf

d. Shelves shall have a weight capacity of 1500 lbs., minimum

e. Padlock hasp

Finish:

a. Metal: Manufacturer’s standard powder coat paint selection

24.0 Ancillary Items

24.1 SH3: Open Industrial Storage Shelving, Metal

Overall Dimensions: 60”W x 36”D x 84”H

General Requirements:

a. Knocked down or pieces shall ship flat and not fully assembled

b. Provide starter/adder units as required per floor plan

c. Heavy beaded or angle post uprights, punched for adjustment

d. Shelf clips with (2) hooks to engage uprights at (2) points

e. Provide cross braces at sides and back of shelving, refer to floor plan for quantity

f. (4) Box form shelves

i. (2) Adjustable shelves, minimum

ii. Fixed top and bottom shelf

g. Provide floor attachments or wall attachment kits, per manufacturer’s recommendation

24.2 SH4: Open Industrial Storage Shelving, Metal

Overall Dimensions: 36”W x 24”D x 84”H

Attachment #2 Last Update: 2/10/2023 Page 9 of 9

General Requirements:

a. Knocked down or pieces shall ship flat and not fully assembled

b. Provide starter/adder units as required per floor plan

c. Heavy beaded or angle post uprights, punched for adjustment

d. Shelf clips with (2) hooks to engage uprights at (2) points

e. Provide cross braces at sides and back of shelving, refer to floor plan for quantity

f. (5) Box form shelves

i. (3) Adjustable shelves, minimum

ii. Fixed top and bottom shelf

g. Provide floor attachments or wall attachment kits, per manufacturer’s recommendation

END OF SECTION

1.0 General
1.1 Submittal Requirements
1.1.1 RFQ Response
1.1.2 Non-Conforming RFQ Response
1.2 Submittal and Clarifications Format
1.3 Post Award Submittal
1.4 Contractor General Notes
1.4.1 General
1.4.2 Fabrics & Materials
2.0 Construction Requirements - Panel Supported Workstations - NOT USED
3.0 Construction Requirements - Benching Systems - NOT USED
4.0 Construction Requirements - Console Systems - NOT USED
5.0 Construction Requirements - Demountable Walls - NOT USED
6.0 Construction Requirements - Metal/Laminate Desks - NOT USED
7.0 Construction Requirements - Metal/Laminate Open Frame Technical Workstations - NOT USED
8.0 Construction Requirements - Metal Furniture: Bookcases - NOT USED
9.0 Construction Requirements - Laminate Tables, Metal Bases - NOT USED
10.0 Construction Requirements - Wood Casegoods, Executive II - NOT USED
11.0 Construction Requirements - Wood Casegoods, Executive III – NOT USED
12.0 Construction Requirements - Wood Conference Tables, Executive II - NOT USED
13.0 Construction Requirements - Wood Conference Tables, Executive III - NOT USED
14.0 Construction Requirements - Laminate Casegoods - NOT USED
15.0 Construction Requirements - Laminate Conference Tables - NOT USED
16.0 Construction Requirements - Ergonomic Task & Conference Seating - NOT USED
17.0 Construction Requirements - Executive Task Seating - NOT USED
18.0 Construction Requirements - Ergonomic Task Stool - NOT USED
19.0 Construction Requirements - Traditional Executive Seating - NOT USED
20.0 Construction Requirements - Seating, Metal Frame, Thermoplastic/Polypropylene- NOT USED
21.0 Construction Requirements - Seating, Wood Frame - NOT USED
22.0 Construction Requirements - Common Space Furnishings - NOT USED
23.0 Construction Requirements – Industrial Storage Cabinet
23.1 SH5: Industrial Storage Cabinet, Metal
24.0 Ancillary Items
24.1 SH3: Open Industrial Storage Shelving, Metal
24.2 SH4: Open Industrial Storage Shelving, Metal