ATT 1 Statement of Work-FR 2159 Soil Water Improvement Project.pdf

PDF 134 KB Posted

Attached to
FR 2159 Road Improvement Project Mark Twain National Forest
Solicitation number
12363N25Q4046
Issued by

About this file

This document is a Statement of Work (SOW) for the FR 2159 Soil and Water Improvement Project located in the Potosi-Fredericktown Ranger District of Mark Twain National Forest in Madison County, Missouri. The project involves road improvement work on FR 2159 spanning 1.00 miles, which includes comprehensive road reconditioning activities such as reshaping drainage dips, cleaning outlet ditches, mowing and limbing roadway vegetation, and road surface improvements.

Specific work details include maintaining the existing 12-foot subgrade and 10-foot road base, clearing vegetation to a 14-foot height, and spreading 2-inch base crushed aggregate across the road width. The work involves multiple types of drainage dip reshaping (A-type and B-type), placing 3-4 inches of clean crushed aggregate in these dips as directed by the Contracting Officer's Representative (COR), and cleaning various outlet ditches. The project concludes with maintaining a turnaround area and placing 30 tons of 2-inch base crushed aggregate on that area, with all road improvement work ending at the 0.95 milepost.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FR 2159 Soil and Water Improvement Project FR 2192 – 1.00 miles

Potosi-Fredericktown Ranger District Mark Twain National Forest

Madison County, Missouri

Scope of Work

Road improvement work will do done on FR 2159 for 1.00 miles This will include road reconditioning (ditch outlets, ditch lines, drainage dips and roadbed); mowing and limbing roadway; spreading 2” base crushed aggregate onto 1.00 miles of road; and placing 3-4” clean crushed aggregate into drainage dips as directed by the COR.

Description of Work

Milepost

0.0 Begin reconstruction of FR 2159 as described below and shown on the Road typicals. Maintain the existing subgrade of a width of 12 feet and The road base a width of 10 feet.

Begin mowing and limbing of vegetation on both sides of roadway To the existing clearing limit (to tree line) and a 14- foot clearing height.

Begin spreading 2” base crushed aggregate at a width of 10 feet and a Depth of 2 inches.

0.03 Reshape existing B-type drainage dip.

Place 3-4” clean crushed aggregate into dip as directed by COR.

Clean B-B type outlet ditch on left.

0.06 Reshape existing B-type drainage dip.

0.11 Reshape existing B-type drainage dip.

Clean B-B type outlet ditch on left.

0.20 Reshape existing B-type drainage dip.

Place 3-4” clean crushed aggregate into dip as directed by COR.

0.24 Maintain exiting turn(curve) widening area on right.

FR 2159

Milepost Description of Work

0.27 Reshape existing B-type drainage dip.

Place 3-4” clean crushed aggregate in dip as directed by COR.

Clean B-B type outlet ditch on left.

0.35 Reshape existing B-type drainage dip.

Place 3-4” clean crushed aggregate in dip as directed by COR.

Clean B-B type outlet ditch on left.

0.37 Reshape existing B-type drainage dip.

Place 3-4” clean crushed aggregate in dip as directed by COR.

Clean B-B type outlet ditch on left.

0.43 Reshape existing A-type drainage dip.

Place 3-4” clean crushed aggregate in dip as directed by COR.

Clean B-B type outlet ditch on left.

0.46 Reshape existing A-type drainage dip.

Place 3-4” clean crushed aggregate in dip as directed by COR.

Clean B-B type outlet ditch on left.

0.52 Reshape existing A-type drainage dip.

Place 3-4” clean crushed aggregate in dip as directed by COR.

Clean B-B type outlet ditch on left.

0.54 Reshape existing A-type drainage dip.

Place 3-4” clean crushed aggregate in dip as directed by COR.

Clean B-B type outlet ditch on left.

0.55 Reshape existing A-type drainage dip.

Place 3-4” clean crushed aggregate in dip as directed by COR.

Clean B-B/A-A type outlet ditch on left.

0.61 Reshape existing A-type drainage dip.

Place 3-4” clean crushed aggregate in dip as directed by COR.

Clean B-B/A-A type outlet ditch on left.

0.64 Reshape existing A-type drainage dip.

Place 3-4” clean crushed aggregate in dip as directed by COR.

Clean B-B/A-A type outlet ditch on left.

FR 2159

Milepost Description of Work

0.67 Reshape existing A-type drainage dip.

Place 3-4” clean crushed aggregate in dip as directed by COR.

Clean B-B/A-A type outlet ditch on left.

0.74 Reshape existing A-type drainage dip.

Place 3-4” clean crushed aggregate in dip as directed by COR.

Clean B-B/A-A type outlet ditch on left.

0.78 Reshape existing A-type drainage dip.

Place 3-4” clean crushed aggregate in dip as directed by COR.

Clean B-B/A-A type outlet ditch on left.

0.79 Reshape existing A-type drainage dip.

Place 3-4” clean crushed aggregate in dip as directed by COR.

Clean B-B/A-A type outlet ditch on left.

0.81 Reshape existing A-type drainage dip.

Place 3-4” clean crushed aggregate in dip as directed by COR.

Clean B-B/A-A type outlet ditch on left.

0.86 Reshape existing A-type drainage dip.

Place 3-4” clean crushed aggregate in dip as directed by COR.

Clean A-A/B-B type outlet ditch left.

0.87 Reshape existing A-type drainage dip.

Place 3-4” clean crushed aggregate in dip as directed by COR.

Clean A-A/B-B type outlet ditch left.

0.93 Clean A-A type outlet ditches left and right.

0.95 Maintain turnaround area.

Place 30 tons of 2” base crushed aggregate onto turnaround area.

End of FR 2159 road improvement work.

End spreading 2” base crushed aggregate at a width of 10 feet and a Depth of 2 inches.

File details come from the government source that posted it. Updated .