This document is an Amendment to a Solicitation for the Forest Road 2159 Improvement Project in the Mark Twain National Forest. The amendment includes questions and answers from a pre-bid conference held on 02APR2025 and updates provisions and clauses from recent Executive Orders. The project involves road improvement work with a projected start date in the first week of June 2025 and completion by mid-August 2025. The period of performance is specifically set from 04/25/2025 to 08/15/2025.
Key project details include road improvements with requirements such as mowing, limbing, reshaping drainage dips, and managing fallen tree tops and brush. Potential contractors were informed about quarry locations (Central Stone in Farmington and Capital Quarry in Arcadia/Ironton, Missouri), lead testing procedures, and bonding requirements. Bonding specifics indicate no requirements for quotes under $35,000, with Alternative Payment Protections required for quotes between $35,000-$150,000. The pre-bid conference was attended by multiple excavation and construction companies, with USDA Forest Service representatives present.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
12363N25Q4046 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
64R4
ROLLA MO 65401
401 FAIRGROUNDS ROAD
MARK TWAIN NATIONAL FOREST
363N
WASHINGTON DC 20250-1138
MS-1138
1400 INDEPENDENCE AVE SW
USDA-FS STEWARDSHIP CONTRACTING BR
03/21/20250001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
03/21/2025
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Amended to include Questions and Answers from Pre-Bid Conference and to update Provisions and Clauses from Executive Orders 14148, 14173, and 14168.
All documents are included in this Amendment to ensure nothing is left out. Any missing items from potential contractor's submission will be clarified after receipt but before award.
Period of Performance: 04/25/2025 to 08/15/2025
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
JOHN V. SWIZDOR
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
09APR2025
12363N25Q4046
FOREST ROAD 2159 IMPROVEMENT
PRE-BID CONFERENCE
02APR2025
1. Where do I go to register for this project?
Answer: www.sam.gov.
2. Where is the nearest quarry that is acceptable near project area?
Answer: Central Stone quarry in Farmington, Mo & Capital Quarry in Arcadia/Ironton, Mo.
3. Does contractor need to work with Quarry to obtain lead testing information?
Answer: No. Awarded Contractor will need to work with COR. Forest Service personnel will work with Quarry personnel to obtain the lead test samples for project. No extra cost will occur for lead testing requirements to contractor.
4. Will the drainage dips need to be improved/reshaped?
Answer: Yes. They all will need to be reconditioned/reshaped as directed by COR to improve water drainage as stated in work description.
5. Since there is not much of tree line on right side of road, how far does the mowing/limbing need to be?
Answer: There is a few smaller trees that can be used as the tree line, but it needs to be at least 3 foot off where the brush/tree branches are not in the roadbed area. Measure as example if you drive your dump truck down, if it hits it, then it needs to be removed.
6. After we limb the road, what do we do with the limbs/brush?
Answer: As per specifications included in the contract, you place them passed the tree line about 5 feet out of the clearing limit way (roadbed plus sides to tree line).
7. Can we use a piece of equipment to push the tree tops that had fallen on right side of road up away from roadway instead of cutting them?
Answer: The tree tops and brush will need to be cut back away from roadway area due to equipment causing damage on side hill area and causing more erosion.
8. What is the timeline for this project?
Answer: Start date will be approximately in the first week of June 2025 and completion near the middle of August 2025
9. What are the bonding requirements?
Answer: Quotes less than $35,000 have no bonding requirements. $35,000-$150,000 will require Alternative Payment Protections in the form of Irrevocable Letter of Credit or a Payment Bond.
http://www.sam.gov/
12363N25Q4046
FOREST ROAD 2159 IMPROVEMENT
PRE-BID CONFERENCE
02APR2025
ATTENDEES:
Name and Company Email Address Brooks Campbell, May Excavating jesse@mayexcavating.com Robert Reece, Steve’s Hauling and Excavating Pleimann.34@gmail.com Michael Pike & Steve Sadler, Soil and Land Services mpike@doerun.com
Tony Abney & Joe Stevens, Tony Abney Construction tabney@misn.com
Carl & Jonnie Jones, Carl Jones Excavating and Hauling jonesjonnie@hotmail.com
USDA-Forest Service Dana Sturgeon, Contracting Officer Representative
Dana.sturgeon@usda.gov
John Swizdor, Contracting Officer John.swizdor@usda.gov mailto:jesse@mayexcavating.com mailto:Plieman.34@gmail.com mailto:mpike@doerun.com mailto:tabney@misn.com mailto:jonesjonnie@hotmail.com mailto:Dana.sturgeon@usda.gov mailto:John.swizdor@usda.gov
| 12363N25Q4046 0001 MTNF FR2159 Road Improvement.pdf |
| Pre-Bid Q&A |
File details come from the government source that posted it. Updated .