ATT 1 - Statement of Work.pdf
PDF 629 KB Posted
- Solicitation number
- EEPZ247468
About this file
This is a Design-Build Statement of Work for a fire alarm system replacement project at Columbus Air Force Base, Mississippi (Project EEPZ247468), dated 18 December 2025. The contractor must provide complete design and construction services to replace obsolete MONACO radio-based fire alarm systems with new Notifier fiber-based systems across six buildings: B99 (Visitor Center), B155 (Hazardous Storage Area), B214 (Dog Kennel), B348 (Youth Center), B916 (Education Center), and B998 (Fire Station). Work scope includes demolishing existing MONACO panels and devices, furnishing and installing new Notifier 320 panels with single-mode fiber cards, installing new conduit and fiber runs, replacing all existing devices, programming new systems to communicate with the fire station, and updating the Onyx Workstation with imported drawings and audio file programming. The contractor must also furnish dedicated electrical circuits, perform required duct detector and tamper switch installations, handle kitchen suppression system microswitches, and address code compliance issues including explosion-proof devices where required per UFC and NFPA standards.
The period of performance is 365 days from Notice to Proceed, with design submissions required at 35%, 65%, 95%, and 100% completion stages at 21-day intervals. The contractor must submit material submittals within 21 days of 100% design approval and maintain a Quality Control Plan with daily inspections. The contractor is responsible for all design professional services, field investigations, constructability verification, and code compliance. Government will not furnish equipment or materials, and will not salvage existing systems. Key compliance requirements include adherence to UFC 3-600-01 (Fire Protection), UFC 3-501-01 and 3-520-01 (Electrical), NFPA 72 and 101, NEC 70, and Columbus AFB Installation Facility Standards. All drawings must be provided in AutoCAD Release 2020 and PDF formats. Standard warranty is one year from total project acceptance, with contractor responsible for system programming, testing, training, operation and maintenance manuals, and spare parts adequate for two years beyond warranty.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sources Sought Questionnaire.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DESIGN-BUILD STATEMENT OF WORK
PROJECT NUIMBER: EEPZ247468
Replace Fire Alarms, B99, B155, B214, B348, B916, B998
COLUMBUS AFB, MISSISSIPPI
18 Dec 2025
COLUMBUS AFB, MS PROJECT NUMBER: EEPZ247468
TABLE OF CONTENTS
NOMENCLATURE
1.1 ACRONYMS & ABBREVIATIONS
1.2 BASIC TERMS
DESCRIPTION OF PROJECT
2.1 SUMMARY (EXAMPLE BELOW)
2.2 BACKGROUND
2.3 SCOPE OF PROJECT
2.4 GOVERNMENT FURNISHED EQUIPMENT/MATERIALS (DETAILS NOT ALWAYS
NECESSARY, IF NOT, SAY THE GOVERNMENT WILL NOT FURNISH ANYTHING FOR THIS
PROJECT; THIS IS AN EXAMPLE BELOW)
2.5 SALVAGE (DETAILS NOT ALWAYS NECESSARY, IF NOT, SAY THE GOVERNMENT WILL
NOT SALVAGE ANYTHING FROM THIS PROJECT; THIS IS AN EXAMPLE BELOW)
DESIGN REQUIREMENTS
3.1 SUMMARY
3.2 NATURE/EXTENT OF DESIGN (CHANGE THIS FOR PROJECT SPECIFICS, EXAMPLE
BELOW) 10
3.3 RESPONSIBILITY
3.4 DESIGN STANDARDS (ADD ANY OTHER RELEVANT UFCs, CODES, AND STANDARDS)10
3.5 DRAWINGS
3.6 DESIGN SUBMITTALS (CHECK DAYS IN RED IN SECTION 3.6.2)
3.7 DESIGN REVIEWS
3.8 CONFERENCES
ADMINISTRATION OF CONSTRUCTION
4.1 PERFORMANCE CAPABILITIES (VERIFY RED TEXT IN THIS SECTION ON EACH PROJECT)
4.2 COMMENCEMENT, PROSECUTION & COMPLETION (PERIOD OF PERFORMANCE IN 4.2.3)
4.3 SCHEDULING
4.4 MANAGING
4.5 MATERIAL SUBMITTALS AND SHOP DRAWINGS
4.6 WORK BY GOVERNMENT
4.7 PRE-FINAL AND FINAL INSPECTION
4.8 WARRANTY
4.9 CONTRACTOR OFFICE
4.10 CONSTRUCTION SITES
4.11 CONSTRUCTION EQUIPMENT
4.12 AVAILABILITY OF UTILITY SERVICES AT JOB SITES
4.13 TEMPORARY UTILITIES
4.14 CONSTRUCTION SECURITY
QUALITY REQUIREMENTS
5.1 QUALITY CONTROL PLAN
5.2 TESTING AND INSPECTION SERVICES
5.3 MANUFACTURERS' FIELD SERVICES
5.4 PRODUCT REQUIREMENTS
5.5 CLOSEOUT PROCEDURES
SAFETY, HEALTH AND ENVIRONMENTAL PROTECTION
6.1 SAFETY AND HEALTH
6.2 GENERAL
6.3 HAZARDOUS MATERIAL
6.4 PROJECT EXECUTION
6.5 HAZARDOUS WASTE GENERATION/DISPOSAL
6.6 RECYCLING
6.7 PROHIBITED MATERIAL/ACTIONS
6.8 SPILLS AND CLEANUP
6.9 AIR CONSIDERATIONS
6.10 AFFIRMATIVE/GREEN PROCUREMENT/BIO-BASED/ENERGY
6.11 ASBESTOS/LEAD BASED PAINT
6.12 DRINKING WATER
6.13 EMS
6.14 HISTORICAL AND CULTURAL ARTIFACTS
6.15 NATURAL RESOURCES
6.16 NOISE
6.17 PESTICIDES/FERTILIZERS
6.18 STORM WATER PROTECTION
6.19 REQUEST FOR CE SERVICE/ACTION/CLEARANCE; AF FORMS 332/813
6.20 TANKS
6.21 LIMITS AND EXCEPTIONS
6.22 LEGAL AUTHORITY
NOMENCLATURE
1.1 ACRONYMS & ABBREVIATIONS
AF Air Force AFI Air Force Instruction AFM Air Force Manual AFUE Annual Fuel Utilization Efficiency AHU Air Handling Unit ATFP Anti-terrorism/Force Protection BCE Base Civil Engineer CAD Computer Assisted (or Aided) Design CAFB Columbus Air Force Base CDs Construction Documents CEPM Civil Engineering Project Manager CES Civil Engineering Squadron cfm cubic feet per minute CFR Code of Federal Regulations CHW Chilled Water CMI 14CES Construction Manager Inspector CO Contracting Officer COR Contracting Officer Representative Comm Communications CPM Contractor’s Project Manager CSS Contractor’s Site Superintendent DP Design Professional EMCS Energy Management & Control System EMI Electromagnetic Interference EPA Environmental Protection Agency ETL Engineering Technical Letter FAR Federal Acquisition Regulation FCU Fan Coil Unit FM Factory Mutual
FOD Foreign Object Debris fps feet per second
ft. foot or feet GFCI Government Furnished Contractor Installed gpm gallons per minute Hazmat Hazardous Materials HMW Hazardous Material or Waste HTW Hazardous and Toxic Waste HVAC Heating, Ventilating and Air Conditioning NEC National Electrical Code NTP Notice to Proceed O&M Operation and Maintenance OSP Originally Specified Product PDF Portable Document Format PE Professional Engineer Ph Phase (electrical) PM Project Manager psi pounds per square inch QCP Quality Control Plan RFP Request for Proposal SOW Statement of Work TI Technical Instruction TL Technical Letter TM Technical Manual UFC Unified Facilities Criteria UPS Uninterruptible Power Supply VAV Variable Air Volume V Volts W Watts
1.2 BASIC TERMS
The following table provides many of the meanings of words or phrases commonly used in this document.
All directives, informative, etc. statements are directed to the Contractor even if the term “contractor” or the contractor name is not included (e.g. “Provide a nail.” is equivalent to “The contractor shall provide a nail.” And “remove” is equivalent to “The Contractor shall remove”). Also, the Contractor shall ably and competently execute all directives including all directly or indirectly related tasks required to safely and legally perform the directive (e.g. “remove debris from CAFB” includes “safe and legal removal, disposal and obtaining all necessary permits, etc.)
A device, equipment or system referred to in the singular (e.g. “the pump”, or “the ___ system”) includes all related devices, elements and components required to Provide (see below in this table) that device, equipment, or system.
The Term Shall Mean (*=Shall in Addition Mean) Approved (by CAFB) *without waiving or suspending the full force of Contractor obligation to fulfill the CDs Aspect Distinct feature or element of the project CAFB Government contracting Authority on Columbus Air Force Base
Construction Documents
Drawings, specifications and their references including all Design Criteria and Design & Construction Requirements for this Project.
Contractor The Design-Build entity holding a current Government contract including all personnel in direct or indirect employ of same entity servicing same contract including partners, consultants, subcontractors, suppliers, and manufacturers.
Design Professional (Abbreviated: DP) Professionals including Architects, Engineers and Landscape Architects licensed to practice in one or more states of the U.S.
Day Calendar day unless noted otherwise.
DP Licensed Design Professional fully responsible for all professional design on this project.
Engineer DP For example (e.g.) One among many possible examples Government Columbus Air Force Base Contracting Officer Including [Includes] Including, but not limited to [Includes, but is not limited to] Provide Furnish and install complete, functional, and ready for use without added government action Provision Furnishing & installation complete, functional, and ready for use without added government action Will, must, shall & similar Terms are mandatory directives whereby ‘Term’ = ‘Term + to CAFB satisfaction’ Work The whole or any part, product, system or subsystem of this project Replace Demolish and dispose of existing element. Provide new element of equal or greater value.
Review Review and, if and when acceptable to the government, approval Subcontractor Subcontractor and all personnel in Subcontractor’s direct or indirect employ on any given
Project including suppliers and manufacturers
DESCRIPTION OF PROJECT
2.1 SUMMARY
The Contractor must provide all plant, labor, equipment, transportation, and tools required to complete a full replacement of the entire Fire Alarm Reporting System for various facilities. The work shall include but not be limited to the replacement of Fire Alarm Control Panel, conduit where needed, wire, and all existing devices in the facilities listed below. Perform all work according to this Statement of Work (SOW), the Concept Design Drawings, and all related AF requirements and other codes and references.
2.2 BACKGROUND
This project is to replace various obsolete fire alarm report systems throughout Columbus AFB. The systems requiring replacement are MONACO radio systems. The new systems shall be a Notifier fiber system. The facilities where replacement of the Fire Alarm System is to occur are B99, B155, B214, B348, B916, and B998.
2.3 SCOPE OF PROJECT
Building 99 Visitor Center:
2.3.1 Demolish existing MONACO panel. Furnish and install new Notifier 320 with single mode fiber card. The Contractor shall furnish and install new conduit and fiber to the new Notifier 320 with single mode fiber card. The contractor shall pull from existing fiber internal to the facility.
2.3.2 Demolish existing wiring between MANACO Panel and demolish existing devices. Furnish and install new Notifier devices in place of each existing device. Furnish and install new wiring between new Notifier panel and new Notifier devices. Reuse existing conduit where able, replace with new conduit when needed. Follow UFC 3- 600-01 9-18.9.3.1 for wire labeling.
2.3.3 Locate new Notifier 320 with single mode fiber card on the interior of the facility. Furnish and install a new dedicated electrical circuit including circuit breaker from existing electrical panel to supply power to new Notifier 320 with single mode fiber card.
2.3.4 Demolish existing antenna, conduit, and wire associated with MONACO panel. Repair and finish walls to match existing finish where needed as a result of demolition.
2.3.5 The existing panel in the Visitor Center also controls the devices in the vehicle inspection bay, main gate guard shack, and the guard kiosks. The contractor shall also demolish existing devices in these areas. The contractor shall furnish and install new devices.
2.3.6 The contractor shall pay special attention to requirements listed in UFC 4-022-01 Security Engineering: Entry Control Facilities/Access Control Points.
2.3.7 The contractor may use an existing spare conduit between the visitor center and the main guard shack. For other wire pulls the contractor shall reuse existing conduit.
2.3.8 Demolish existing antenna, conduit, and wire associated with MONACO panel. Repair and finish walls to match existing finish where needed.
2.3.9 The Contractor shall program new panel and all new devices to communicate between each other and the fire station. Onyx Workstation shall be updated with imported drawings, images of pertinent equipment such as sprinkler risers, icons of devices overlaid on floor plans, multiple screens for each project to enable efficient navigation and identification of alarm/trouble/supervisory conditions, and programming for audio files according to base requirements which may or may not be generated by the workstation microphone (where applicable).
Building 155 Hazardous Storage Area:
2.3.10 Demolish existing MONACO panel. Furnish and install new Notifier 320 with single mode fiber card. The Notifier 320 with single mode fiber card shall have a fiber card for future use with fiber. The contractor shall be responsible for making the connection with fiber internal to the facility.
2.3.11 Demolish existing wiring between MANACO Panel and demolish existing devices. The contractor shall furnish and install new devices to bring facility up to code compliance. Furnish and install new wiring between new Notifier panel and new Notifier devices. Reuse existing conduit where able, replace with new conduit when needed.
This includes furnishing and installing explosion proof devices and conduit should they be required per code. Follow UFC 3-600-01 9-18.9.3.1 for wire labeling.
2.3.12 Furnish and install Notifier smoke detector over the new Notifier panel. Tie in and program new Notifier smoke detector.
2.3.13 The Contractor shall program new panel and all new devices to communicate between each other and the fire station. Onyx Workstation shall be updated with imported drawings, images of pertinent equipment such as sprinkler risers, icons of devices overlaid on floor plans, multiple screens for each project to enable efficient navigation and identification of alarm/trouble/supervisory conditions, and programming for audio files according to base requirements which may or may not be generated by the workstation microphone (where applicable).
Building 214 Dog Kennel:
2.3.14 Demolish existing MONACO panel. Furnish and install new Notifier 320 with single mode fiber card.
Furnish and install a dedicated circuit including conductor, conduit, and breaker serving the new panel. The Contractor shall furnish and install new conduit and fiber to the new Notifier 320 with single mode fiber card. The contractor shall pull from existing fiber internal to the facility.
2.3.15 Furnish and install required duct detectors to meet NFPA and UFC requirements. Tie in and program new duct detectors into the new Notifier panel.
2.3.16 Demolish existing devices and wiring throughout facility. Furnish and install new Notifier devices and wiring in place of existing. Reuse existing conduit where able. Tie in and program new devices into new Notifier panel.
Follow UFC 3-600-01 9-18.9.3.1 for wire labeling.
2.3.17 Furnish and install Notifier smoke detector over the new Notifier panel. Tie in and program new Notifier smoke detector.
2.3.18 Demolish any existing Tamper Switches. Furnish and install new Tamper Switches in place of existing devices.
2.3.19 Demolish existing antenna, conduit, and wire associated with MONACO panel. Repair and finish walls to match existing finish where needed.
2.3.20 The Contractor shall program new panel and all new devices to communicate between each other and the fire station. Onyx Workstation shall be updated with imported drawings, images of pertinent equipment such as sprinkler risers, icons of devices overlaid on floor plans, multiple screens for each project to enable efficient navigation and identification of alarm/trouble/supervisory conditions, and programming for audio files according to base requirements which may or may not be generated by the workstation microphone (where applicable).
Building 348 Youth Center:
2.3.21 Demolish the two existing MONACO panels serving the facility. Furnish and install 1 new Notifier 320 with Single Mode Fiber Card to serve the facility in its entirety. The new Panel shall be located in the main entrance of the facility. The Contractor shall furnish and install new conduit and fiber to the new Notifier 320 with single mode fiber card. The contractor shall pull from existing fiber internal to the facility.
2.3.22 Demolish existing devices and wiring connecting to the existing MONACO panels. Furnish and install new Notifier devices, new conduit, and new wiring connecting to the new Notifier panel. Program the new devices.
Follow UFC 3-600-01 9-18.9.3.1 for wire labeling.
2.3.23 Furnish and install a micro switch serving the kitchen suppression system. Furnish and install new conduit and wiring to tie the micro switch to the new Notifier panel. Perform required programing for micro switch and panel.
2.3.24 Demolish existing antenna, conduit, and wire associated with MONACO panel. Repair and finish walls to match existing finish where needed.
2.3.25 The Contractor shall program new panel and all new devices to communicate between each other and the fire station. Onyx Workstation shall be updated with imported drawings, images of pertinent equipment such as sprinkler risers, icons of devices overlaid on floor plans, multiple screens for each project to enable efficient navigation and identification of alarm/trouble/supervisory conditions, and programming for audio files according to base requirements which may or may not be generated by the workstation microphone (where applicable).
Building 916 Education Center:
2.3.26 Demolish existing MONACO panel. Furnish and install new Notifier 320 with single mode fiber card, locate the new panel in the main entrance. The Contractor shall furnish and install new conduit and fiber to the new Notifier 320 with single mode fiber card. The contractor shall pull from existing fiber internal to the facility.
2.3.27 Demolish existing devices. The contractor shall determine proper location, quantity, and type of devices required. Furnish and install new Notifier devices in the determined quantity, location, and types per design. This shall include furnishing and installing new wire and conduit. Follow UFC 3-600-01 9-18.9.3.1 for wire labeling.
2.3.28 Demolish existing antenna, conduit, and wire associated with MONACO panel. Repair and finish walls to match existing finish where needed.
2.3.29 The Contractor shall program new panel and all new devices to communicate between each other and the fire station. Onyx Workstation shall be updated with imported drawings, images of pertinent equipment such as sprinkler risers, icons of devices overlaid on floor plans, multiple screens for each project to enable efficient navigation and identification of alarm/trouble/supervisory conditions, and programming for audio files according to base requirements which may or may not be generated by the workstation microphone (where applicable).
Building 998 Fire Station:
2.3.30 Demolish existing MONACO panel. Furnish and install new Notifier 320 with single mode fiber card. The Contractor shall furnish and install new conduit and fiber to the new Notifier 320 with single mode fiber card. The contractor shall pull from existing fiber internal to the facility. Locate the new panel in the vestibule. The contractor shall furnish and install all necessary conduit and wiring for the new location of the panel.
2.3.31 Demolish existing wiring between MANACO Panel and demolish existing devices. Furnish and install new Notifier devices in place of each existing device. Furnish and install new wiring between new Notifier panel and new Notifier devices. Reuse existing conduit where able, replace with new conduit when needed. The contractor shall also comply with requirements per UFC 4-730-10 in addition to standard design requirements. Follow UFC 3- 600-01 9-18.9.3.1 for wire labeling.
2.3.32 The bunk rooms in the fire station currently have both a carbon monoxide detector and a smoke detector. The contractor shall furnish and install a single notifier device to serve both purpose in each bunk room. The contractor shall be responsible for repairing all finishes and covering all holes from previous devices. The contractor shall color match repair work to existing finishes.
2.3.33 The contractor shall furnish and install code compliant smoke detector for the kitchen area. The contractor shall furnish and install microswitches for the stoves and vent hoods in the kitchen.
2.3.34 The contractor shall relocate the annunciator panel in the dispatch room to code compliant location in the dispatch room such that is has 3 feet of working space. The contractor shall furnish and install any necessary conduit and wiring to accomplish this.
2.3.35 Incorporate existing dry and wet pipe systems that serve the facility into the new notifier system such that they function together in a code compliant manner.
2.3.36 Demolish existing antenna, conduit, and wire associated with MONACO panel. Repair and finish walls to match existing finish where needed.
2.3.37 The Contractor shall program new panel and all new devices to communicate between each other and the fire station. Onyx Workstation shall be updated with imported drawings, images of pertinent equipment such as sprinkler risers, icons of devices overlaid on floor plans, multiple screens for each project to enable efficient navigation and identification of alarm/trouble/supervisory conditions, and programming for audio files according to base requirements which may or may not be generated by the workstation microphone (where applicable).
2.4 GOVERNMENT FURNISHED EQUIPMENT/MATERIALS
The Government will not furnish anything for this project.
2.5 SALVAGE
The Government will not salvage anything from this project.
DESIGN REQUIREMENTS
3.1 SUMMARY
Design will consist of all site investigations and design work associated with preparing complete contract documents for this project as described in this SOW. The design documents must be developed from the functional and technical data contained in this SOW and include construction drawings, schedules, and design analysis. The Contractor will also be required to submit design documents for review as described in Paragraph 3.6 as well as final contract documents. The Contractor will be required to attend review and conference meetings as needed and requested by the Government.
3.2 NATURE/EXTENT OF DESIGN
This project requires the services of licensed Design Professionals. The project requires Fire Alarm Reporting Systems design and details for the demolition and subsequent reconstruction of new Fire Alarm Reporting Systems including interior to facility fiber runs. Professionally sealed drawings are required.
Design/shop/coordination drawings, materials and equipment submittals, and final as-built record drawings are required for this project. Contractor must maintain accurate redline As-Builts throughout construction and must submit final As-Built drawings (with any of the redline changes updated on the drawings) upon project completion (see paragraph 4.7.2 for more information).
3.3 RESPONSIBILITY
3.3.1 Contractor must perform all services, including travel, required to prepare and to furnish complete design documents consisting of drawings, analysis, and addenda as required, for the construction of the project in accordance with this SOW.
3.3.2 Record drawings (attached) are provided to the Contractor as a courtesy at the discretion of the Government, but their accuracy is not guaranteed. The Contractor is responsible for doing his own field investigations of the utilities, existing conditions, and other items in the area.
3.3.3 The Government may provide conceptual drawings to the Contractor, but their accuracy is not guaranteed. The Contractor must do his own field investigations of the utilities, existing conditions, and other items in the area and base his design accordingly.
3.3.4 The Contractor is responsible for all remaining design and coordination to provide an acceptable final product that meets intent of this SOW. Contractor is responsible for ensuring constructability and code compliance.
3.3.5 The Contractor must immediately notify the contracting officer and secure any documents found with “Classified”, “Controlled Unclassified Information” (CUI) or personal information. The Contracting Officer will direct disposition of these documents.
3.4 DESIGN STANDARDS
All design and construction must be accomplished in accordance with applicable UFC’s, ETL’s, (UFC’s and ETL’s may be found on-line at www.wbdg.org.) local and national codes, Columbus AFB Installation Facility Standards (IFS) and all Appendices (Special Construction, Mechanical, and Electrical) and other guidance as modified by this SOW. The IFS document may be found at the following location:
http://www.wbdg.org/ffc/af-afcec/installation-facilities-standards-ifs/columbus-afb-ifs. The list of documents includes, but is not limited to, the latest editions of the following
• UFC 1-200-01 DoD Building Code (General Building Requirements)
• UFC 1-200-02 High Performance and Sustainable Building Requirements
• UFC 3-501-01 Electrical Engineering http://www.wbdg.org/ffc/af-afcec/installation-facilities-standards-ifs/columbus-afb-ifs
• UFC 3-520-01 Interior Electrical Systems
• UFC 3-600-01 Fire Protection Engineering for Facilities
• UFC 4-010-01 DoD Minimum Antiterrorism Standards for Buildings
• NFPA 101
• NFPA 72
• NEC 70
• Columbus AFB IFS
• CAFB Base Standards
The Contractor must submit a written request for approval of any deviations from the Government's established standards. No deviations from the Government's established standards will be permitted unless the Contracting Officer has issued prior written approval of such deviation.
3.5 DRAWINGS
Drawings under this Contract must be well prepared, complete, and accomplished in accordance with the best professional practice to show clearly and concisely the type and extent of work to be performed.
3.5.1 Drawings must be drawn to appropriate scales and dimensioned completely and accurately.
Lettering must be large enough to ensure legible half-size reduction and each dimensioned drawing must have a graphic scale. Use of fractions less than 1/8-inch for building dimensions must be avoided. Use standard building material indications and symbols for architectural items and for mechanical, electrical and plumbing equipment.
3.5.2 The Contractor will use paper sheets, 24" x 36". Each sheet will be numbered consecutively beginning with "1 of (x) Sheets" and continue to the last sheet. Number individual drawing sheets as follows:
Drawing Sheet Subject Notation Additional Sheets
Cover (Title Sheet, Map and Index)
T1 and following
Civil/Site Work C1 and following Demolition D1 and following Landscaping L1 and following Architectural A1 and following Structural S1 and following Plumbing P1 and following Mechanical M1 and following Electrical E1 and following
Note: All sheet subjects above may not be necessary for this project
3.5.3 Drawings must be prepared electronically in both AutoCAD (Release 2020) and PDF formats.
3.6 DESIGN SUBMITTALS
3.6.1 DELIVERY: Deliver two (2) hard copies of each submittal and one (1) digital copy via DoD SAFE containing each drawing sheet in PDF file format directly to the CO, along with AF Form 3000. For uploading to DoD SAFE, the Contractor must request an upload link from the CO and then upload the files using the details in the subsequent email from DoD SAFE. For the final design submittal (As-Builts in most cases), the contractor is to provide, in addition to the hard copies and digital copies via DoD SAFE, containing the PDF file as well as the associated CAD files in AutoCAD (Release 2020) .dwg file format. Hard copy submittals must be delivered to:
14th Contracting Squadron 495 Harpe Blvd, Suite 293 Columbus, MS 39710
3.6.2 SUBMITALS AT INTERMEDIATE STAGES OF DESIGN COMPLETION: To facilitate review and feedback throughout the design process, designs are submitted at various stages of completion as follows:
1) 35% DESIGN SUBMITTAL: Contractor must submit 35% design documents within 21 days after Notice to Proceed (NTP). The 35% design must include complete and thorough detailing to leave no question as to how demolition and construction is intended. All design documents must be clearly annotated (in both title block and revision block of drawings) with “35% REVIEW SET” and the date.
2) 65% DESIGN SUBMITTAL: Contractor must submit 65% design documents within 21 days after receipt of the “Approved” 35% design. The 65% design must include complete and thorough detailing to leave no question as to how demolition and construction is intended. All design documents must be clearly annotated (in both title block and revision block of drawings) with “65% REVIEW SET” and the date.
3) 95% DESIGN SUBMITTAL: Contractor must submit 95% design documents within 21 days after receipt of the “Approved” 65% design. The 95% design (essentially complete design and drawings, pending review and acceptance by Government as the 100% APPROVED CONSTRUCTION SET) must include complete and thorough detailing to leave no question as to how assembly is intended. All design documents must be clearly annotated (in both title block and revision block of drawings) with “95% REVIEW SET” and the date.
4) 100% DESIGN/APPROVED CONSTRUCTION SET: Contractor must submit the 100% DESIGN APPROVED CONSTRUCTION SET within 14 days after Contractor receipt of the “Approved” 95% design. The construction set must incorporate and/or address any Government comments on the 95% design and should leave no question to how demolition and construction will be done. If professionally stamped and sealed drawings are required for this project (paragraph 3.2), the approved construction set must include all stamped drawings. All final design documents must be clearly annotated (in both title block and revision block of drawings) with “APPROVED CONSTRUCTION SET” and the date.
5) For each holiday or extraordinary event in a submittal period, increase the required days for submittal by one day for each day in the event. Deliver no submittals within (before or after): one week of Thanksgiving; two weeks of Christmas; or one week of New Year’s Day. Extraordinary Events include: unscheduled holidays for base personnel; base-wide training exercises; etc. The Government may prohibit work during such events.
3.6.3 PARTIAL SUBMISSIONS: Partial submissions normally will not be accepted. However, under some circumstances, to expedite project execution, the Government may accept design/shop drawings or material submittals for major elements or long-lead-time equipment for review and approvals prior to 95% design submittal. Government approval of such items does not relieve the Contractor of his responsibility to ensure a complete, constructible, code-compliant design.
3.6.4 CONSTRUCTION PRIOR TO 100% DESIGN: Construction may not commence until Government approves the 100% design. Exception: To expedite contract completion, Contractor may petition CO for an Interim Notice to Proceed with specific elements of construction. Government review does not constitute approval or acceptance of any variations from this SOW, the Contractor’s Proposal, or the Contract unless authorized in writing by the CO. The Interim Notice to Proceed, if exercised, will in no way mitigate the responsibility of the Contractor to provide a complete, constructible, code-compliant design.
All drawings, specifications, design analyses and other project materials become the property of the Government.
3.7 DESIGN REVIEWS
3.7.1 DESIGN PHASE REVIEWS: Government review of each XX% design submittal (where XX = 95 or 100 as required per 3.6.2) will require up to fourteen (14) days after Government receipt. The Government will determine the sufficiency of each XX% design submittal as follows:
1) Approved as Submitted. If design is sufficient to proceed without correction to the next phase submittal, one (1) copy of AF FORM 3000 marked "Approved" will be returned to the Contractor.
Contractor must advance to the next stage design submittal.
2) Approved - Except as Noted. Design submittals that have only minor errors or deficiencies will be marked in red to indicate necessary corrections. Marked materials, along with one (1) copy of AF FORM 3000 indicating "Approved - Except as Noted" will be returned to the Contractor.
Contractor must revise the design documents, making the necessary corrections, and advance to the next stage design submittal.
3) Disapproved. Design submittals that are incomplete or require more than minor corrections will be marked in red to indicate necessary corrections. Marked materials, along with one (1) copy of AF FORM 3000 marked “Disapproved” will be returned to the Contractor. Contractor must revise the design documents, making the necessary corrections, and re-submit as the current stage “XX% Design – 2nd (or subsequent) Submittal”.
4) Disapproved – Major Deficiency. Examples include, but are not limited to, design submittals that fall significantly short of indicated level of completion, grossly deviate from or misinterpret the SOW, or contain errors of a nature or quantity that indicate failure of Contractor to review submittals for completeness, correctness, and coordination between trades. For such submittals, the Government will not complete a comprehensive review or provide an exhaustive list of needed corrections. Rather, one (1) copy of AF FORM 3000 marked “Disapproved – Major Deficiency” along with general reason(s) for disapproval will be returned to the contractor. The CO will issue a written warning to the Contractor that any subsequent grossly incorrect/incomplete submittals constitute evidence of inability to complete the project and may result in declaring the Contractor “In Default.” Contractor must correct deficiencies and resubmit as current stage “XX% Design – 2nd (or subsequent) Submittal”.
3.7.2 100% DESIGN REVIEW: The Government will have fourteen (14) days to verify that all review comments have been addressed and no unapproved changes have been made. Upon Government approval of the 100% design documents, the Contractor may begin construction.
3.7.3 IMPACT OF REVIEW ON PERIOD OF PERFORMANCE: Contract completion time includes time for Government review of drawings, specifications, and material submittals. Unless otherwise noted, the Government will use no more than 14 calendar days for review of each design submittal and each subsequent re-submittal of “Disapproved” submittals (paragraph 3.7.1, c or d). There will be no increase in the period of performance for review of re-submittals.
3.7.4 RESPONSE TO REVIEW COMMENTS: The Contractor is required to respond to all review comments and submit their annotated comments as a design analysis appendix in the subsequent design submittal. All comments must either be accepted and incorporated into the next design submittal or satisfactorily rebutted.
3.7.5 DESIGN ACCOUNTABILITY: The Contractor is solely responsible for accurately designing and constructing everything necessary to provide a fully functional product. Government approval of any design or design-related submittal does not waive or remove full liability from the Contractor to provide a design, facility, or final product that meets the intent of this SOW, performs as intended, and adheres to all applicable codes and standards.
3.8 CONFERENCES
3.8.1 PRECONSTRUCTION CONFERENCE: A Preconstruction Conference (Pre-Con) will be held at the Contracting Office as indicated.
3.8.2 COORDINATION/REVIEW CONFERENCES: Coordination/review conferences may be held from time to time as required. The Contractor may request such conferences when it is deemed necessary by both parties to clarify the work or expedite the preparation of plans, specifications or construction.
3.8.3 REVIEW/CONFERENCE MINUTES: The Contractor will be responsible for making memoranda of record of any conversations and minutes of any meeting with Government personnel concerning this project and forward one copy of these memoranda/minutes to each party concerned and one copy to the Contracting Officer within seven (7) days. The final version of the meeting minutes will be approved and filed at the CO’s discretion. Each copy will be numbered consecutively and chronologically.
3.8.4 MEETING LOCATIONS: Meetings will be held in person at Columbus Air Force Base.
Contractor transportation costs for attending all conferences/reviews and meetings must be included in the Contractor’s Proposal. There will be no teleconferences unless permitted otherwise by the Contracting Officer.
End of Design Requirements
ADMINISTRATION OF CONSTRUCTION
4.1 PERFORMANCE CAPABILITIES
4.1.1 One week prior to the start of work under this contract, Contractor must submit in writing to the CO for review and possible approval the names and credentials of Contractor Project Manager, Contractor Site Superintendent, and Quality Control Manager. Subsequent proposed changes of approved personnel must be submitted in writing to and receive prior approval from the CO before working on the project. Each of these personnel may upon CO approval hold additional onsite duties which must not diminish their required performance. Contractor must demonstrate to the Government’s satisfaction that proposed personnel exceed education, technical and experience levels of personnel described in this Contract including the following:
1) Contractor Project Manager (CPM) - Provide management of the prime contract to include subcontract purchasing and administration, review of material submittals and shop drawings. CPM must have full authority to develop cost proposals, negotiate with Government and subcontractors, sign awards and modifications, supervise project superintendents, attend weekly CO/CE/PM Contractor status meetings as well as pre-performance site visits, pre-final and final inspections.
The CPM must have a minimum of 5 years previous experience as primary contract manager or equivalent experience as a primary estimator and negotiator with a contracting firm engaged in similar multi-discipline commercial construction projects. CPM must also have not less than 5 years’ experience managing subcontractors.
2) Contractor Site Superintendent (CSS) - Provide on-site construction superintendent(s) to oversee all work under this contract. Site supervision must be daily (constant throughout each day) and includes submission of detailed weekly progress reports, scheduling and coordination of subcontractors and material suppliers, and attendance at all construction progress meetings, CO site visits, and pre-final and final inspections. Superintendents must have a minimum of 5 years previous experience as a project superintendent (exclusive of time employed as a tradesman or working foreman) for a general contracting firm overseeing one or more multi-discipline commercial construction projects. The superintendent must be available within 15 minutes during all normal working hours, except for such incidental errands as required by his duties. The superintendent must be responsible for the proper coordination and timeliness of the work, and for the proper workmanship of all trades; therefore, his absence from the project site without a suitable substitute Contractor representative must be considered as damaging to the Government.
3) Quality Control Manager (QCM) - Provide quality control management for the project. QCM must continually (constant throughout each day) ensure full compliance with all safety requirements, verification that work and materials in place and stored on site are in accordance with the approved construction documents, shop drawings and material submittals. QCM must submit daily status reports recording activities at each project site, prepare and coordinate material submittal sheets and shop drawing submittals, schedule and coordinate testing procedures, prepare quality control reports for construction progress and other required meetings, and attend all pre-final and final inspections. QCM must have a minimum of five years’ experience in Quality Control Management of multidiscipline construction projects.
4.1.2 Contractor must have additional personnel including management, technical, service, labor or subcontractor, available as necessary to fulfill all construction contract requirements. The Government may restrict employment under this contract of any personnel identified as a potential threat to the health, safety, security, well-being, or operational mission of CAFB and its population.
4.1.3 Contractor must be available by telephone 24-hours a day, 7-days a week and upon 15 minutes’ notice during normal duty hours and 30 minutes’ notice during non-duty hours must meet the CO at a CO designated location.
4.2 COMMENCEMENT, PROSECUTION & COMPLETION
4.2.1 Contractor must start design and various construction phases at times specified by CO issued Notice(s) to Proceed (NTP), prosecute the work, and complete the entire work within the Period of Performance.
4.2.2 Contractor must provide a Submittal Log (Schedule of Material Submittals), Progress Schedules, Progress reports and Status Reports.
1) Submittal Log: See Material Submittals and Shop Drawings below.
2) Progress Schedule: (AF Form 3064) Submit the progress schedule to the CO within 10 days after contract award, unless otherwise specified by the CO. Subdivide total schedule into individual work items. Show completed work percentages at the end of each two-week reporting period. Progress schedule should only be resubmitted during the project duration if there’s an issue with Period of Performance or if deemed necessary by the CO as described in 4.2.2.3.
3) Progress Reports: (AF Form 3065) Submit Project Progress reports to the CO minimum twice per month on the first working day of each month and again on the 15th. Describe the percentage of work completed during the report period. If behind schedule, report in writing what actions will be taken to regain the schedule. If the CO agrees to add days to the contract performance period, Contractor must provide an amended schedule.
4) Status Reports: Submit to the CO daily reports of the work status. In each report, list the tasks accomplished for that day, any deliveries received, equipment currently on-site, weather conditions for that day, and number of personnel working on each area listed by trade. Photos may be included.
4.2.3 Period of Performance: Is the period between the issuance of the NTP and the time all construction is complete, including all punch list items, and final inspection is approved by the Government. The total Period of Performance for this project is 365 days.
4.2.4 Contract Completion: At contract conclusion, vacate all work areas, including: Contractor offices, storage and staging areas, and individual work sites. Restore these areas to their condition prior to Contractor occupancy not more than 14 days from the earlier of: approved final inspection or CO notification.
4.2.5 Coordination and Project Conditions: Schedule and manage submittals, materials, products, equipment, manpower, etc. to control all parts of the work efficiently and orderly. Verify compatibility of existing building utilities with new operating equipment. Coordinate required space, supports, and mechanical and electrical work shown (even if via diagrams) on Drawings. Follow routing shown for pipes, ducts, and conduit; place runs parallel with building lines. Use space efficiently to maximize maintenance and for repair accessibility for other systems. Conceal wiring behind finish surfaces and locate fixtures and outlets with finish elements. Coordinate pre-Substantial Completion clean-up in separate building areas.
After CAFB occupancy, coordinate site access to correct defective (or non-compliant with CDs) to minimize disruption of Government activities.
4.2.6 Cutting and Patching: Only employ skilled and experienced workers to cut and patch. Report in writing to the CO wherever cutting and patching might degrade: safety; appearance, structure, weatherproofing, O&M, or separate Contractor or government construction. Prevent damage to existing or new construction and provide proper surfaces to receive patching and finishing. Match new finishes to existing adjacent surfaces unless noted otherwise. Maintain integrity of existing walls, ceilings, or floors;
completely seal voids. Refinish entire assemblies and continuous surfaces to nearest intersection. Cut, fit, and patch where CDs require e.g.: mechanical and electrical penetrations; integration of new components with one another or with existing construction; removal and replacement of defective and non-conforming elements; remove samples for testing.
4.2.7 Special Procedures: Employ skilled and experienced tradespersons to perform alteration work.
Remove debris from open work areas and concealed spaces. Remove, cut, and patch to minimize damage and provide means of restoring products and finishes to original or specified condition. If a change of plane of 1/4 inch or more is discovered, submit recommendation to the CO for providing a smooth transition.
Patch or replace portions of existing surfaces which are damaged or showing other imperfections. Finish surfaces as specified.
4.2.8 Welding Permits: No cutting or welding will be permitted without first obtaining a permit issued by the Base Fire Department. All fire and safety regulations are to be followed stringently. Contractor’s failure to obtain a cutting or welding permit may not be reason for extending the contract performance period. Any damages incurred while welding work is done without a permit are the responsibility of Contractor.
4.3 SCHEDULING
4.3.1 Contractor must coordinate all work schedules and manage progress of work with the CO and CEPM prior to start of work. Weekly progress meetings will be conducted with the CO, CMI, and Contractor’s team which may require corporate management representation at CAFB discretion.
4.3.2 Contractor must schedule all work. Performance periods must not be established or extended to accommodate insufficient personnel resources. Contractor will not move crews on and off the project while making minimal progress on concurrent projects as this must be construed as having an inadequate work force to fulfill the contract requirements. Contractor’s CPM and CSS must not change more than two (2) times during project construction as this would demonstrate an inadequate management force to fulfill contract requirements.
4.3.3 Before construction begins, Contractor must agree with CO on a sequence of procedures; means of access to premises and buildings; materials and equipment storage space; delivery of materials and use of approaches, corridors, and stairways. Contractor may be required to revise the CD work-phasing schedule.
4.3.4 Interference and inconvenience to Government operations and personnel caused by project work including use and delivery of materials, tools and equipment must be kept to a minimum.
4.3.5 The Government may require that work, so far as practicable, be done in separate phases. Each phase may relate to a different occupied or unoccupied area, in which work in one area must be completed before work in another area may begin. Phased work areas must be clearly delineated and annotated in the CDs.
4.3.6 Hours of Work: Normal work hours will be Monday through Friday from 7:30am to 4:15pm excepting days observed as Federal Holidays as listed below:
New Year’s Day 1 January Martin Luther King’s Birthday Third Monday in January President’s Day Third Monday in February Memorial Day Last Monday in May Juneteenth Day 19 June Independence Day 4 July Labor Day First Monday in September Columbus Day Second Monday in October Veterans Day 11 November Thanksgiving Day Fourth Thursday in November Christmas Day 25 December
1) Observe Saturday holidays the preceding Friday. Observe Sunday holidays the succeeding Monday.
2) For weekend, after hours, or holiday work, submit a 72 hour advance written request to the CO, describing dates, locations, and types of work. CAFB has the right to approve or deny the request.
Work in CAFB occupied areas during extra-normal work hours require AF escorts in the occupied areas. Modification to contract sum or period of performance will not be allowed.
3) The Government’s request for Contractor to work outside of the normal duty hours must be justification for modification to contract sum or period of performance.
4) If CAFB observes an unscheduled holiday, participates in training exercises, etc. Contractor may be prohibited from working for part or the whole of a day. 14CES does not know how many or when these activities might be scheduled but anticipate not less than two per year. CMI will allow additional contract time for these disruptions. Zero-cost modification to period of performance will be allowed.
4.3.7 Construction Schedule: Submit preliminary schedule to the CO at the Preconstruction Meeting, but not later than fourteen (14) days after issuance of Notice to Proceed. After CAFB review and comment, revise and resubmit schedule within seven (7) days. Upon approval by the CO, the schedule becomes the official Construction Progress Schedule. Keep a copy available at Contractor (field) Office. This schedule will only be changed with prior approval of the CO through a contract Modification.
4.3.8 Construction Progress Schedule: Submit and maintain an accurate and current Gantt chart to track construction progress with a separate horizontal line for each major work activity of subcontractors, manufacturers, and suppliers. Vertical lines must identify the first workday of each week. Show complete sequence of construction by activity, identifying separate stages of work and other logically grouped activities. Indicate early and late start, early and late finish, float dates, and duration of each activity.
Revise chart weekly to accurately identify progress made, percentage completion, and projected completion date for each activity. Show activities modified and scope changes. Submit written report to identify problems, anticipated delays, corrective actions, and affected completion dates. Provide additional progress schedule information as requested by the CMI. Construction progress schedule update forms will be provided at the preconstruction conference.
4.4 MANAGING
4.4.1 Preconstruction Conference: at CAFB will be scheduled by the CO after issuing the NTP. Required attendees include the Contractor, Contractor Project Manager (CPM), and Contractor Site Superintendent (CSS). Contractor must record meeting minutes and within two days after the meeting distribute two (2) copies to all participants and to all others affected by decisions made at the meeting. The meeting Agenda will be issued in advance by the CO and will include one or more of the following:
1) Execution of Government-Contractor Agreement.
2) Submission of executed bonds and insurance certificates.
3) Distribution of Contract Documents.
4) Submission of Subcontractors list, products list, schedule of values, and progress schedule.
5) Designation of personnel representing the parties in Contract.
6) Procedures for processing field orders, submittals, substitutions, payment applications, proposal requests, Change Orders, and Contract closeout.
7) Construction Schedule
4.4.2 Site Mobilization Meeting: Prior to Contractor project site(s) occupancy, the CO will schedule a meeting at which required attendants include the CO, Contractor, Contractor’s Project Manager (CPM), Contractor’s Site Superintendent (CSS), and major Subcontractors. Contractor must record meeting minutes and within two days after the meeting distribute two (2) copies to all participants, and to all others affected by decisions made at the meeting. The Agenda for this meeting will include:
1) Government and Contractor Use of Premises.
2) Government Requirements.
3) Construction facilities and controls provided by Government.
4) Temporary utilities provided by Government.
5) Security and Housekeeping Procedures.
6) Construction Schedules.
7) Application for Payment Procedures.
8) Testing Procedures.
9) Record Documents Maintenance Procedures.
4.4.3 Weekly Progress Meetings: with the CMI will occur throughout construction duration. Required attendants include the CO, Contractor, the CPM, and the CSS. Contractor must record meeting minutes and within two days after the meeting distribute two (2) copies to all participants, and to all others affected by decisions made at the meeting. The agenda for these meetings will include the following:
1) Review previous week’s work progress.